Line 3: Line 3:
== Prep for next vent ==

(1) Dichroic mirror for recycling cavities (Kiwamu)
 * Figure out required spec
    * [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=87589|spec in DCC]]
    * wedge angle = 2 deg
    * dichroic mirror quotes:
      [[https://wiki-40m.ligo.caltech.edu/vent?action=AttachFile&do=get&target=ATF.pdf|ATF]]
      [[https://wiki-40m.ligo.caltech.edu/vent?action=AttachFile&do=get&target=Laseroptik.pdf|Laseroptik]]
     

    * [[Optical_Layout#PR3SR3|Optical table layout needs to be modified]]

 * Get a quote from ATF.
 * Qty = 3 (2 + 1 spare )
 * Start ordering (in a week)

(2) Black glass beam dumps (Koji)
 * Large baffle style covers for the suspensions
 * Small V-shape pieces for generic purpose
   * [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=77367|hexagonal]]
   * [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=77543|diamond shaped]]
   * [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=77545|diamond shaped (2inch)]]

(3) OSEM mount screws (Steve)
 * Hex-top, longer, sliver-plated
 * Qty = 100
 * No-plastic
 * http://131.215.115.52:8080/40m/6232

(4) Active tip-tilts (Suresh/Jamie)
 * Electronics
 * Cables including vacuum-compatible ones and the non-vacuum ones
 * Prepare mirrors
 * Assembly and baking
 * Prepare feedthrough connectors
 * Digital controls

(5) OMC activation (Jenne)
 * Calculate the mode matching solutions and prepare appropriate telescopes
 * Draw optical layout
 * Digital controls

(6) OSEM upgrade (somebody)
 * Need a discussion

== Previous ==
 * [[vent/checklist|Common Pre-closeup checklists]]
 * [[vent/planningFall2021|Vent Fall 2021]]
 * [[vent/planningFall2020 |2020 Fall]]
 * [[vent/201905 |2019 May]]
 * [[vent/oldUnknownTime | Unknown Time ]]
 * [[vent/201812 |2018 October]]
 * [[vent/201708 |Tasks for next vent after Aug 30 2017]]
 * [[vent/201610|2016 October]]
 * [[vent/201605|2016 May-August]]
Line 55: Line 16: