Vent planning for Fall 2021
Contents
- Clean Room SUS Work
-
Vent [Oct 18 to Dec 6]
- Overall Requirements
-
Specific tasks and details
- In vacuum cable procurement [Oct 4 to Nov 8] (CO, JV, KA)
- Chamber opening [Oct 25 to Nov 1] (CO ++)
- Vacuum repair [Oct 18 to Nov 1] (JV, CO)
- Existing optics Alignment/ table cleaning [Oct 18 to Nov 1] (PS, AG)
- Align the new optics [Oct 25 to Nov 22] (PS, AG, YD, TE)
- In vacuum cable installation [Nov 8 to Nov 15] (JV, CO ++)
-
Vertex Racks
- Overall Requirements
-
Specific tasks and details
- In-air cable procurement [Oct 4 to Oct 25] (KA)
- Electronics rack work [Oct 4 to Oct 11] (PS, AG)
- Vertex electronics design [Oct 4 to Oct 18] (KA)
- Vertex electronics proc [Oct 25 to Nov 1] (KA)
- New Simulink models & medm screens [Oct 11 to Oct 25] (IM)
- CDS integration work [Nov 15 to Nov 22] (AG, IM)
- Damping test [Nov15 to Nov 22] (AG, PS, IM)
- End Racks
- BHD Tasks
1. Clean Room SUS Work
1.1. Overall Requirements
List items you need before completing this whole section
Clean 3"->2" optics adapter parts (Side blocks, balance weights, mirror clamps)
- Adapter rings, wire clamp, wire block and retainer rings are all clean on the flow bench
- Waiting for machined balance masses from RDL ETA ~1 week
- All hardware except 8-32 Helicoils are cleaned and ready for assembly, eta on Helicoils ~1 week
HeNe Laser
- Suspension Wire (wrapped and stored in the clean room)
- Dummy 2" mirror
- The mirrors that actually go into the vacuum.
1.2. Specific tasks and details
1.2.1. Gluing / SUS building [Oct 4 to Oct 11] (YD, JV, TE)
Requirements:
- Dumbell+magnet assemblies need to be glued onto the optics adapter. 4 on the ring and 1 on a side block for each SOS.
- One last round of dumbell+magnet gluing.
- Testing of bond strength of last dumbell+magnet batches.
for the side magnets, we need longer assembly to avoid interference with the clamping screws. -> an additional magnet will be glued on a magnet-dumbbel pair.
Estimated time: 3 Days
- Assembly drawing ~75% complete, will be ready 10/11/21
1.2.2. Suspending [Oct 4 to Oct 11] (YD, TE)
Requirements:
- Need to push a few already clean Viton tips into 1/4" screws to be used as EQ stops. Assemble those EQ stops onto the SOSs.
- Suspend dummy mirror for balance testing.
Balance the dummy mirror using the HeNe laser. Adding and moving weights for adjustments.
- Suspend and balance actual mirrors that go into the vacuum using what we learned by experimenting with the dummy mirror.
- Suspension order of optics and origin of the optics:
PR3 | E1800089 | Arrived in Feb 2019. In Clean Optic Cabinet in Xend.
SR2 | E1800089 | Arrived in Feb 2019. In Clean Optic Cabinet in Xend.
LO1 | E2000226-C | Lambda Optic. In Clean Optic Cabinet in Xend.
LO2 | E1800089 | Arrived in Feb 2019. In Clean Optic Cabinet in Xend.
AS1 | E2000226-A | Lambda Optic. In Clean Optic Cabinet in Xend.
AS4 | E2000226-B | Lambda Optic. In Clean Optic Cabinet in Xend.
- PR2 | Use existing PR2. | Kept in the cleanroom in old small suspension.
- OSEM use:
Optic
Face OSEMS
Side OSEM
Long Yellow Grade
Long Green Grade
Small Yellow Grade
Small Green Grade
LO1
4 Long Yellow
1 Small Yellow
4
0
1
0
LO2
4 Small Yellow
1 Small Yellow
0
0
5
0
AS1
4 Long Green
1 Long Green
0
5
0
0
AS4
4 Long Green
1 Long Green
0
5
0
0
PR2
4 Small (3G, 1Y)
1 Small Green
0
0
1
4
PR3
4 Small Green
1 Small Green
0
0
0
5
SR2
4 Small Green
1 Small Green
0
0
0
5
Total to use
-
-
4
10
7
14
In-hand
-
-
12
10
8
14
Estimated time: 2 weeks
2. Vent [Oct 18 to Dec 6]
Current 40m in-vac optics layout https://caltech.box.com/s/83x9fgb1n36f6k5n073zsgxhx321vjo5
New 40m in-vac optics layout https://caltech.box.com/s/gm4smqn8quelxqlgtch038asinwfgyfv
2.1. Overall Requirements
List item you need before completing this whole section
- SOS kicking test (~Oct 14)
- IFO alignment / Oplev centering / QPD centering / MC power reduction and locking
- N2 bottles (x2)
List every action (maybe from other sections) you need completed before completing this section
2.2. Specific tasks and details
List down the sub tasks here:
2.2.1. In vacuum cable procurement [Oct 4 to Nov 8] (CO, JV, KA)
20 cable quote taken, the order placed. Arrived 10/21/2021
Associated hardware: invacuum cable brackets, assessment in the elog https://nodus.ligo.caltech.edu:8081/40m/16404. We will order Qty6. Jordan is on it.
2.2.2. Chamber opening [Oct 25 to Nov 1] (CO ++)
Requirements:
- The optics have been suspended and are ready for installation.
Details of the task.
Estimated time: 1 week
2.2.3. Vacuum repair [Oct 18 to Nov 1] (JV, CO)
Requirements:
- 10" CF gaskets
- Silver plated hardware for 10" clearance flange
Details of the task.
Estimated time:
2.2.4. Existing optics Alignment/ table cleaning [Oct 18 to Nov 1] (PS, AG)
Requirements: None
Details of the task:
- Match the current layout with the schematic and mark what is changed.
- Remove the optics that need to be taken out for space for new stuff.
- Align the existing optics better.
Estimated time: 2 weeks
2.2.5. Align the new optics [Oct 25 to Nov 22] (PS, AG, YD, TE)
Requirements: Space cleared as per new optical layout.
Details of the task:
- Install the new suspended optics in their place.
Estimated time: 4 weeks
2.2.6. In vacuum cable installation [Nov 8 to Nov 15] (JV, CO ++)
Requirements: All in-vac cables procured
Details of the task:
Estimated time: 1 week
3. Vertex Racks
3.1. Overall Requirements
List item you need before completing this whole section
- 1 GBps Ethernet cables from 1Y3 to 1X6.
List every action (maybe from other sections) you need completed before completing this section
- Suspending the optics
3.2. Specific tasks and details
List down the sub tasks here:
3.2.1. In-air cable procurement [Oct 4 to Oct 25] (KA)
Requirements: None
Details of the task
Estimated time: 4 weeks
Status: Custom/Long DB cables ordered (11/1, KA, CO) -> Delivered -> C&Bed -> ready to be installed
-> 4 cables for ITMX installed https://nodus.ligo.caltech.edu:8081/40m/16513
3.2.2. Electronics rack work [Oct 4 to Oct 11] (PS, AG)
Requirements: None
Details of the task:
- Clear the rack space in YARM 1Y3.
Estimated time: 1 week
3.2.3. Vertex electronics design [Oct 4 to Oct 18] (KA)
Requirements: None
Details of the task.
Estimated time: 3 weeks
3.2.4. Vertex electronics proc [Oct 25 to Nov 1] (KA)
Requirements: Design needs to be finished
Details of the task.
Estimated time: 2 weeks
3.2.5. New Simulink models & medm screens [Oct 11 to Oct 25] (IM)
Requirements: None
Details of the task:
- Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++.
- Copy the esiting suspension models from C1SUS to make C1SUS2 model.
- New medm screens for the new suspensions and BHD.
Estimated time: 2 weeks
3.2.6. CDS integration work [Nov 15 to Nov 22] (AG, IM)
Requirements:
- Need to finish testing teststand
- 1Y3 rack needs to be cleared up.
- 1 GBps Ethernet cables from 1Y3 to 1X6.
- Make sure we have all cables are there with required lengths.
Details of the task:
Live link to plan. Anyone can edit with ligo.org credentials.
Estimated time: 1 week
3.2.7. Damping test [Nov15 to Nov 22] (AG, PS, IM)
Requirements:
- All suspensions must be suspended by now.
- All electronics should be in their positions with requried cabling.
- C1SUS2 and C1BHD must be installed and running.
- All realtime models for new suspensions must be built, installed and started.
Details of the task:
- Do in-air tests of suspension damping.
Estimated time: 1 week
4. End Racks
4.1. Overall Requirements
List item you need before completing this whole section
List every action (maybe from other sections) you need completed before completing this section
4.2. Specific tasks and details
List down the sub tasks here:
4.2.1. End QPD cable [Oct 18 to Oct 25] (KA)
Detail: There was a mistake in the IDC40-DB9 cable. Fix it. Update/create DCC entries.
4.2.2. End electronics Design [Oct 18 to Oct 25] (KA)
Requirements: None
Details: Design ADC adapter unit PCB / Front & rear panels.
Estimated time: 1 week
4.2.3. End electronics proc [Oct 25 to Nov 1] (CO, KA)
Requirements: After designing.
Details: Procure PCBs for ADC/DAC adapter unit. Procure Front/rear Panels. Procure components.
Estimated time: 2 weeks
4.2.4. End electronics fab [Nov 1 to Nov 8] (TE, PS)
Requirements: After procurement.
Details: Build electronics.
Estimated time: 1 weeks
5. BHD Tasks
5.1. Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
5.2. Specific tasks and details
List down the sub tasks here:
5.2.1. Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements:
Details of the task.
Estimated time:
5.2.2. Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements:
Details of the task.
Estimated time: ...