Major tasks for vent:

Later:

Preparation

Based on Koji's cavity length calculations, the ideal arm cavity length is:

L = 37.7974 m

The current cavity lengths are:

Based on pictures (elog #4585):

Lx = 37.54 m
Ly = 37.54 m

Based on RF sideband location technique

Lx = 37.5918 m
Ly = 37.5425 m

This means we need to move (negative equals back, ie. away from the vertex)

ETMX -> -0.2056 m = -20.56 cm = - 8.09 in
ETMY -> -0.2549 m = -25.49 cm = -10.04 in

Questions




Procedure and Time line

pre-vent days

CR:

  1. List up which suspensions should be touched
  2. Lock Y-arm green
  3. Reduce power to mode cleaner (appropriate level for in-air MC locking)
  4. Make sure IPANG and IPPOS are working and acquired to fb


1st day

  1. Shut down PZT HVs
  2. Vent at a speed of 1 torr/min.
  3. Change cylinders
  4. Monitor the pressure


2nd day

BS north door :

  1. Open BS north door (took ~ 15 min.)
  2. Adjust green periscope to extract Y green transmission
  3. Align X green trans through green periscope
  4. Table leveling of the BS table
  5. Check some possible beam clipping

Access connector

  1. Remove the access connector (took ~ 45 min.)
  2. Adjust the position of Green Telescope
  3. Make sure that the IR beam clears the input and output of the Faraday
  4. Check some possible beam clipping

CR:

  1. Lock X green


3rd day

CR:

  1. Take the shadow sensors' spectra

EYC north access:

  1. Open EY door
  2. Move ETMY for YARM
  3. ETMY OSEM adjustment, including minimization of coupling and OSEM range
  4. ETMY shadow sensors need to be carefully investigated

EXC west access:

  1. Open EX door
  2. Move ETMX for XARM
  3. ETMX OSEM adjustment?

BSC north access:

  1. Adjust IPANG
  2. BSC OSEM adjustment?
  3. PRM OSEM adjustment?


4th day

IXC east access:

  1. Adjust POP, POX for vacuum extraction
  2. ITMX OSEM adjustment?

IYC north access:

  1. Adjust POY for vacuum extraction
  2. ITMY OSEM adjustment?
  3. SRM OSEM adjustment?


5th day

  1. Check all the OSEM values
  2. Check POP, POY and POX
  3. Check IPANG and IPPOS
  4. Drag and wipe ETMY
  5. Close EYC door
  6. Drag and wipe ITMY
  7. Close IYC door
  8. Drag and wipe ITMX
  9. Close IXC door
  10. Drag and wipe ETMX
  11. Close EX door
  12. Close BS door
  13. Place the access connector
  14. Pumping down

6th day

  1. Pumping down


For a later vent: fix cavity lengths

Preparation

We need precise measurements of the cavity lengths in order to determine where exactly we need to move the test masses.

Measurements:

MICH = lx - ly = 3.62 cm
PRCL = (lx+ly)/2 + lsr = ?
SRCL = (lx+ly)/2 + lpr = ?

Vent

door removal

  1. BSC north
  2. ITMYC north
  3. ITMXC west
  4. ETMYC north
  5. ETMXC west

Procedure

This is a preliminary procedure plan:

CR:

  1. Lock Y-arm green
  2. Reduce power to mode cleaner (appropriate level for in-air MC locking)

IOC west access (through access connector):

  1. Adjust green periscope to extract Y green transmission

CR:

  1. Lock X green

BSC north access:

  1. Align X green trans through green periscope

BSC north access:

  1. Adjust IPANG

CR:

  1. Misalign PRM

IYC north access:

  1. Move ITMY into position

IXC west access:

  1. Move ITMX into position

CR:

  1. Realign PRM

EYC north access:

  1. Move ETMY for YARM

EXC west access:

  1. Move ETMX for XARM

BSC north access:

  1. Move PRM for PRC

BSC north access:

  1. Move SRM for SRC
  2. Align pick-offs