Differences between revisions 70 and 111 (spanning 41 versions)
Revision 70 as of 2012-08-22 21:48:26
Size: 3611
Comment:
Revision 111 as of 2021-10-06 21:16:22
Size: 5256
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:

* [[vent/checklist|pre-vent/pre-closeup checklists]]

== Vent Fall 2021 ==

[[vent/planningFall2021|Planning page for Vent in Fall 2021]]
----

== Tasks for Vent of Fall 2020 ==
* '''Primary objective''' - re-glue broken magnet on ETMY and re-suspend it.
   1. Take back the 70% light split off to the OMC in the AS path.
   1. Investigate TT hysterisis [low priority as this would require 3rd door to be off].
[[vent/planningFall2020|planning page]]
----

== Tasks for Vent of May 2019 ==
 * '''Primary objective''' - Suspension diagnosis
   1. Fix ETMY (one eigenmode missing?) and ITMY (frequently gets stuck) suspension
   1. Check that the AS beam exits the vacuum cleanly. Take back the 70% light split off to the OMC in the AS path.
   1. Investigate TT hysterisis


== Tasks for next vent after Aug 30 2017 - not in any particular order ==
 * Installing new RC folding mirrors, PR3 and SR3 (we need to get the actual optics + new Tip-Tilt suspension design)
 * Flip existing PR2 and SR2
 * Installation of Ruby standoffs for selected optics (we need to get a better magnet gluing fixture ready)
 * MC1 suspension inspection and fixing
 * ITMX magnet re-gluing
 * Baffling (?)
 * Installation of steering mirrors to facilitate viewing of optic faces with GigE cameras
 * FC cleaning
Line 16: Line 47:
(2) Active tip-tilts (Suresh/Jamie) (2) [[Suspensions/Tip_Tilts_IO|IO Active tip-tilts]] (Suresh/Jamie)
Line 68: Line 99:
(7) Review IP{ANG,POS} alignment/closeup proceedure (7) Loss Measurements
  * Improve resolution in the scope
  * Configs to '''measure''':
    * X-arm misaligned
      * validate insensitivity to misalignment
   * Y-arm misaligned
      * validate insensitivity to misalignment
   * ~3-5 different beam positions each
   *
  * '''Analysis'''
    * Sources of error?
Line 70: Line 111:
== tip-tilt wiring == (8) OMC Commissioning
  * '''Electronics'''
    * DB-? cables from the DAC to HV drives
    * Goal is to align onto OMC trans PDs
    * Extra PD on AS table can be used for 'backup' in-air PD
  * '''Locking Script'''
    * Scan the OMC cavity before the vent, make sure script works
    * Lock before vent to ensure procedure makes sense.
  * '''Chambers to Open'''
    * OMC Chamber only
  * '''Align into PDs'''
    * Lock OMC using OMC REFL signal
    * Align transmitted beam into TRANS PDs
    * Will require ~1 day of work
  * '''Backup Plan'''
    * If the PDs don't work as expected, steer beam to the AS table
    * Rotate and move (+x) SM5, which directs the beam to the TRANS PDs
    * Beam will come out near the current AS beam
    * may have to remove one extra steering mirror (SM5 trans PO)
Line 72: Line 131:
{{attachment:40m-tt-wiring.svg}} (9) Review IP{ANG,POS} alignment/closeup proceedure
Line 74: Line 133:
relevant pictures:
 * BSC table, from north, above output PZT0: [[https://picasaweb.google.com/foteee/BSchamber_general_2July2012#5760738286971644386|1]], [[https://picasaweb.google.com/foteee/InVacWork4Aug2011#5637286023354525762|2]]
   * '''''Do we have 3 available 25-pin connectors on BSC table??'''''
 * IOO table, from west, through AC, input PZT0 detail: [[https://picasaweb.google.com/foteee/InVacWorkNov232010#5544001991913055442|1]], [[https://picasaweb.google.com/foteee/InVacWorkNov232010#5544002001413250658|2]]
   * '''''It looks like we have (or will have) 1 available 25-pin connector on IOO, which is all we need!'''''
 * OMC table, from east, through AC, output PZT1 detail: [[https://picasaweb.google.com/foteee/InVacWork4Aug2011#5637288817950887378|1]], [[https://picasaweb.google.com/foteee/InVacWork4Aug2011#5637288262639879746|2]]
   * '''''unclear what is available here'''''
Line 83: Line 135:
 * [[vent/201812 |2018 October]]
 * [[vent/201610|2016 October]]
 * [[vent/201605|2016 May-August]]

Vent plans

* pre-vent/pre-closeup checklists

Vent Fall 2021

Planning page for Vent in Fall 2021


Tasks for Vent of Fall 2020

* Primary objective - re-glue broken magnet on ETMY and re-suspend it.

  1. Take back the 70% light split off to the OMC in the AS path.
  2. Investigate TT hysterisis [low priority as this would require 3rd door to be off].

planning page


Tasks for Vent of May 2019

  • Primary objective - Suspension diagnosis

    1. Fix ETMY (one eigenmode missing?) and ITMY (frequently gets stuck) suspension
    2. Check that the AS beam exits the vacuum cleanly. Take back the 70% light split off to the OMC in the AS path.
    3. Investigate TT hysterisis

Tasks for next vent after Aug 30 2017 - not in any particular order

  • Installing new RC folding mirrors, PR3 and SR3 (we need to get the actual optics + new Tip-Tilt suspension design)
  • Flip existing PR2 and SR2
  • Installation of Ruby standoffs for selected optics (we need to get a better magnet gluing fixture ready)
  • MC1 suspension inspection and fixing
  • ITMX magnet re-gluing
  • Baffling (?)
  • Installation of steering mirrors to facilitate viewing of optic faces with GigE cameras
  • FC cleaning

Prep for next vent

(1) Dichroic mirror replacements for PR3 and SR3

(2) IO Active tip-tilts (Suresh/Jamie)

  • Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts

  • tip-tilts:
    • tip-tilts from LHO

    • bake

    • assemble

    • add mirrors
    • level
  • in-vac cables (quadrapuses)
    • ship parts to RND Cables

    • place order with RND Cables

    • bake
  • electronics:
    • gather components:
      • DAC
      • anti-image filters
      • dewhite filters
      • coil drivers
      • eurocrate
      • cables
    • install
    • test in DAQ

(3) Black glass beam dumps

(4) OSEM mount screws

  • requirements:
    • Hex-top, longer, sliver-plated
    • Qty = 100
    • No-plastic
  • final design

  • manufacture

  • bake

  • ready to install

(5) New periscope plate

  • manufacture

  • bake

  • ready to install

  • need shorter pedestals for green PBS and beam dump

(6) Cavity scattering measurements? (Jan)

(7) Loss Measurements

  • Improve resolution in the scope
  • Configs to measure:

    • X-arm misaligned
      • validate insensitivity to misalignment
    • Y-arm misaligned
      • validate insensitivity to misalignment
    • ~3-5 different beam positions each
  • Analysis

    • Sources of error?

(8) OMC Commissioning

  • Electronics

    • DB-? cables from the DAC to HV drives
    • Goal is to align onto OMC trans PDs
    • Extra PD on AS table can be used for 'backup' in-air PD
  • Locking Script

    • Scan the OMC cavity before the vent, make sure script works
    • Lock before vent to ensure procedure makes sense.
  • Chambers to Open

    • OMC Chamber only
  • Align into PDs

    • Lock OMC using OMC REFL signal
    • Align transmitted beam into TRANS PDs
    • Will require ~1 day of work
  • Backup Plan

    • If the PDs don't work as expected, steer beam to the AS table
    • Rotate and move (+x) SM5, which directs the beam to the TRANS PDs
    • Beam will come out near the current AS beam
    • may have to remove one extra steering mirror (SM5 trans PO)

(9) Review IP{ANG,POS} alignment/closeup proceedure

Previous

vent (last edited 2021-10-27 19:08:20 by AnchalguptaATligoDOTorg)