== Vent Fall 2021 ==

[[vent/planningFall2021|Planning page for Vent in Fall 2021]]
----
Line 5: Line 9:
== Tasks for Vent of Fall 2020 ==
* '''Primary objective''' - re-glue broken magnet on ETMY and re-suspend it.
   1. Take back the 70% light split off to the OMC in the AS path.
   1. Investigate TT hysterisis [low priority as this would require 3rd door to be off].
[[vent/planningFall2020|planning page]]
Line 6: Line 15:
== Tasks for Vent of Nov 2018 ==
 * '''Primary objective''' - carry out upgrade of the vacuum control system to Acromag
   1. Do we have necessary hardware?
   1. Steve has acquired some test Serial->Ethernet converter, needs to be checked and interfaced.
   1. use the Polaroid / GoPro to film Steve.
Line 12: Line 16:
 * ''Secondary tasks'' - depends on how many chambers we want to open:
   1. Fix clipping situation in Y arm.
   1. ETMX suspension cage yaw rotation.
   1. SRC length adjustment to allow [[https://nodus.ligo.caltech.edu:8081/40m/14164|Signal-Recycled]] locking.
   1. Clean arm cavity optics with first contact.
   1. Commission existing OMC.
   1. Bring back IP POS/ANG ?
== Tasks for Vent of May 2019 ==
 * '''Primary objective''' - Suspension diagnosis
   1. Fix ETMY (one eigenmode missing?) and ITMY (frequently gets stuck) suspension
   1. Check that the AS beam exits the vacuum cleanly. Take back the 70% light split off to the OMC in the AS path.
   1. Investigate TT hysterisis

Vent plans

Vent Fall 2021

Planning page for Vent in Fall 2021


Tasks for Vent of Fall 2020

* Primary objective - re-glue broken magnet on ETMY and re-suspend it.

  1. Take back the 70% light split off to the OMC in the AS path.
  2. Investigate TT hysterisis [low priority as this would require 3rd door to be off].

planning page

Tasks for Vent of May 2019

  • Primary objective - Suspension diagnosis

    1. Fix ETMY (one eigenmode missing?) and ITMY (frequently gets stuck) suspension
    2. Check that the AS beam exits the vacuum cleanly. Take back the 70% light split off to the OMC in the AS path.
    3. Investigate TT hysterisis

Tasks for next vent after Aug 30 2017 - not in any particular order

  • Installing new RC folding mirrors, PR3 and SR3 (we need to get the actual optics + new Tip-Tilt suspension design)
  • Flip existing PR2 and SR2
  • Installation of Ruby standoffs for selected optics (we need to get a better magnet gluing fixture ready)
  • MC1 suspension inspection and fixing
  • ITMX magnet re-gluing
  • Baffling (?)
  • Installation of steering mirrors to facilitate viewing of optic faces with GigE cameras
  • FC cleaning

Prep for next vent

(1) Dichroic mirror replacements for PR3 and SR3

(2) IO Active tip-tilts (Suresh/Jamie)

  • Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts

  • tip-tilts:
    • tip-tilts from LHO

    • bake

    • assemble

    • add mirrors
    • level
  • in-vac cables (quadrapuses)
    • ship parts to RND Cables

    • place order with RND Cables

    • bake
  • electronics:
    • gather components:
      • DAC
      • anti-image filters
      • dewhite filters
      • coil drivers
      • eurocrate
      • cables
    • install
    • test in DAQ

(3) Black glass beam dumps

(4) OSEM mount screws

  • requirements:
    • Hex-top, longer, sliver-plated
    • Qty = 100
    • No-plastic
  • final design

  • manufacture

  • bake

  • ready to install

(5) New periscope plate

  • manufacture

  • bake

  • ready to install

  • need shorter pedestals for green PBS and beam dump

(6) Cavity scattering measurements? (Jan)

(7) Loss Measurements

  • Improve resolution in the scope
  • Configs to measure:

    • X-arm misaligned
      • validate insensitivity to misalignment
    • Y-arm misaligned
      • validate insensitivity to misalignment
    • ~3-5 different beam positions each
  • Analysis

    • Sources of error?

(8) OMC Commissioning

  • Electronics

    • DB-? cables from the DAC to HV drives
    • Goal is to align onto OMC trans PDs
    • Extra PD on AS table can be used for 'backup' in-air PD
  • Locking Script

    • Scan the OMC cavity before the vent, make sure script works
    • Lock before vent to ensure procedure makes sense.
  • Chambers to Open

    • OMC Chamber only
  • Align into PDs

    • Lock OMC using OMC REFL signal
    • Align transmitted beam into TRANS PDs
    • Will require ~1 day of work
  • Backup Plan

    • If the PDs don't work as expected, steer beam to the AS table
    • Rotate and move (+x) SM5, which directs the beam to the TRANS PDs
    • Beam will come out near the current AS beam
    • may have to remove one extra steering mirror (SM5 trans PO)

(9) Review IP{ANG,POS} alignment/closeup proceedure