| A more [[Detailed Vent Plan|detailed]] plan is coming soon. | ## page was renamed from Plan of Action |
| Line 3: | Line 3: |
| General: | ------ We vented from 9/19/06 through 10/5/06 to install the DC readout in-vacuum beamline and adjust suspension OSEMs. The following were the plans we assembled prior to the vent. Everything proceeded more-or-less according to plan, but please see the ilog for details. |
| Line 5: | Line 9: |
| 1. Implement DC readout at the 40m 1. Detect Gravitational Waves |
VacVentPicturesOct2006 |
| Line 8: | Line 11: |
| [[Rough Schedule]] | ------ |
| Line 10: | Line 13: |
| [[In-vacuum tasks]] | [[Rough_Schedule]] |
| Line 12: | Line 15: |
| [[DC readout requirements]] | [[Detailed_Vent_Plan]] |
| Line 14: | Line 17: |
| [[Additional in-vacuum requirements]] | [[In-vacuum_tasks]] |
| Line 16: | Line 19: |
| [[Triggers for breaking vacuum]] | [[DC_readout_requirements]] |
| Line 18: | Line 21: |
| [[In Air Pre-Alignment]] | [[Additional_in-vacuum_requirements]] |
| Line 20: | Line 23: |
| [[Misc In Vac Work]] | [[Triggers_for_breaking_vacuum]] [[In_Air_Pre-Alignment]] [[OSEM_adjustment_proceedure]] [[Misc_In_Vac_Work]] |
We vented from 9/19/06 through 10/5/06 to install the DC readout in-vacuum beamline and adjust suspension OSEMs. The following were the plans we assembled prior to the vent. Everything proceeded more-or-less according to plan, but please see the ilog for details.