Differences between revisions 71 and 78 (spanning 7 versions)
Revision 71 as of 2012-10-04 01:08:06
Size: 3643
Comment:
Revision 78 as of 2017-08-30 18:12:01
Size: 3325
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:

 * [[vent/checklist|pre-vent/pre-closeup checklists]]

== Tasks for next vent after Aug 30 2017 - not in any particular order ==
 * Installing new RC folding mirrors, PR3 and SR3 (we need to get the actual optics + new Tip-Tilt suspension design)
 * Flip existing PR2 and SR2
 * Installation of Ruby standoffs for selected optics (we need to get a better magnet gluing fixture ready)
 * MC1 suspension inspection and fixing
 * ITMX magnet re-gluing
 * Baffling (?)
 * Installation of steering mirrors to facilitate viewing of optic faces with GigE cameras
 * FC cleaning
Line 16: Line 28:
(2) [[IO Active tip-tilts|Suspensions/Tip_Tilts_IO]] (Suresh/Jamie) (2) [[Suspensions/Tip_Tilts_IO|IO Active tip-tilts]] (Suresh/Jamie)
Line 70: Line 82:
== tip-tilt wiring ==

{{attachment:40m-tt-wiring.svg}}

relevant pictures:
 * BSC table, from north, above output PZT0: [[https://picasaweb.google.com/foteee/BSchamber_general_2July2012#5760738286971644386|1]], [[https://picasaweb.google.com/foteee/InVacWork4Aug2011#5637286023354525762|2]]
   * '''''Do we have 3 available 25-pin connectors on BSC table??'''''
 * IOO table, from west, through AC, input PZT0 detail: [[https://picasaweb.google.com/foteee/InVacWorkNov232010#5544001991913055442|1]], [[https://picasaweb.google.com/foteee/InVacWorkNov232010#5544002001413250658|2]]
   * '''''It looks like we have (or will have) 1 available 25-pin connector on IOO, which is all we need!'''''
 * OMC table, from east, through AC, output PZT1 detail: [[https://picasaweb.google.com/foteee/InVacWork4Aug2011#5637288817950887378|1]], [[https://picasaweb.google.com/foteee/InVacWork4Aug2011#5637288262639879746|2]]
   * '''''unclear what is available here'''''
Line 83: Line 84:
 * [[vent/201610|2016 October]]
 * [[vent/201605|2016 May-August]]

Vent plans

Tasks for next vent after Aug 30 2017 - not in any particular order

  • Installing new RC folding mirrors, PR3 and SR3 (we need to get the actual optics + new Tip-Tilt suspension design)
  • Flip existing PR2 and SR2
  • Installation of Ruby standoffs for selected optics (we need to get a better magnet gluing fixture ready)
  • MC1 suspension inspection and fixing
  • ITMX magnet re-gluing
  • Baffling (?)
  • Installation of steering mirrors to facilitate viewing of optic faces with GigE cameras
  • FC cleaning

Prep for next vent

(1) Dichroic mirror replacements for PR3 and SR3

(2) IO Active tip-tilts (Suresh/Jamie)

  • Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts

  • tip-tilts:
    • tip-tilts from LHO

    • bake

    • assemble

    • add mirrors
    • level
  • in-vac cables (quadrapuses)
    • ship parts to RND Cables

    • place order with RND Cables

    • bake
  • electronics:
    • gather components:
      • DAC
      • anti-image filters
      • dewhite filters
      • coil drivers
      • eurocrate
      • cables
    • install
    • test in DAQ

(3) Black glass beam dumps

(4) OSEM mount screws

  • requirements:
    • Hex-top, longer, sliver-plated
    • Qty = 100
    • No-plastic
  • final design

  • manufacture

  • bake

  • ready to install

(5) New periscope plate

  • manufacture

  • bake

  • ready to install

  • need shorter pedestals for green PBS and beam dump

(6) Cavity scattering measurements? (Jan)

(7) Review IP{ANG,POS} alignment/closeup proceedure

Previous