Line 16: Line 16:
(2) Active tip-tilts (Suresh/Jamie) (2) [[IO Active tip-tilts|Suspensions/Tip_Tilts_IO]] (Suresh/Jamie)

Vent plans

Prep for next vent

(1) Dichroic mirror replacements for PR3 and SR3

(2) Suspensions/Tip_Tilts_IO (Suresh/Jamie)

  • Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts

  • tip-tilts:
    • tip-tilts from LHO

    • bake

    • assemble

    • add mirrors
    • level
  • in-vac cables (quadrapuses)
    • ship parts to RND Cables

    • place order with RND Cables

    • bake
  • electronics:
    • gather components:
      • DAC
      • anti-image filters
      • dewhite filters
      • coil drivers
      • eurocrate
      • cables
    • install
    • test in DAQ

(3) Black glass beam dumps

(4) OSEM mount screws

  • requirements:
    • Hex-top, longer, sliver-plated
    • Qty = 100
    • No-plastic
  • final design

  • manufacture

  • bake

  • ready to install

(5) New periscope plate

  • manufacture

  • bake

  • ready to install

  • need shorter pedestals for green PBS and beam dump

(6) Cavity scattering measurements? (Jan)

(7) Review IP{ANG,POS} alignment/closeup proceedure

tip-tilt wiring

40m-tt-wiring.svg

relevant pictures:

  • BSC table, from north, above output PZT0: 1, 2

    • Do we have 3 available 25-pin connectors on BSC table??

  • IOO table, from west, through AC, input PZT0 detail: 1, 2

    • It looks like we have (or will have) 1 available 25-pin connector on IOO, which is all we need!

  • OMC table, from east, through AC, output PZT1 detail: 1, 2

    • unclear what is available here