Line 32: Line 32:
 * '''Ready to install'''  * '''ready to install'''
Line 53: Line 53:
(5) Mode-matching telescope adjustments (Jenne/Suresh)
 * Need to determine what exactly the problem is.
   * What needs to be moved?
(5) New periscope plate
  * --(manufactured)--
  * --(baked)--
  * '''ready to install'''

Vent plans

Prep for next vent

(1) Dichroic mirror for recycling cavities (Jamie)

(2) Black glass beam dumps

(3) OSEM mount screws

  • requirements:
    • Hex-top, longer, sliver-plated
    • Qty = 100
    • No-plastic
  • final design

  • manufactured

  • baked

  • ready to install

(4) Active tip-tilts (Suresh/Jamie)

  • Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts

  • tip-tilts:
    • We have tip-tilts from LHO

    • baked

    • assembled

    • add mirrors
    • level
  • in-vac cables (quadrapuses)
    • Must place order with RND Cables

  • electronics:
    • gather components:
      • DAC
      • anti-image filters
      • dewhite filters
      • coil drivers
      • eurocrate
      • cables

(5) New periscope plate

  • manufactured

  • baked

  • ready to install

(6) Cavity scattering measurements? (Jan)

(7) Review IP{ANG,POS} alignment/closeup proceedure