Differences between revisions 54 and 60 (spanning 6 versions)
Revision 54 as of 2012-07-13 22:51:13
Size: 2363
Comment:
Revision 60 as of 2012-07-16 21:30:10
Size: 2527
Comment:
Deletions are marked like this. Additions are marked like this.
Line 9: Line 9:
   * '''''[[https://wiki-40m.ligo.caltech.edu/vent?action=AttachFile&do=get&target=Laseroptik.pdf|Laseroptik (final)]]'''''    * '''[[https://wiki-40m.ligo.caltech.edu/vent?action=AttachFile&do=get&target=Laseroptik.pdf|Laseroptik (final)]]'''
Line 12: Line 12:
 * '''''We have mirrors in hand!'''''
 * P
hase map of mirror, in and out of tip-tilt mounts
 * --([[http://nodus.ligo.caltech.edu:8080/40m/6907|optics in hand]])--
 * __
'''''phase map of mirror, in and out of tip-tilt mounts'''''__
   * '''''what resolution do we need?'''''
Line 21: Line 22:
 * '''''being baked...'''''  * --(manufactured)--
 *
being baked...
Line 24: Line 26:
 * requirements:
Line 27: Line 30:
 * '''''[[http://nodus.ligo.caltech.edu:8080/40m/6472|final design]]'''''  * '''[[http://nodus.ligo.caltech.edu:8080/40m/6472|final design]]'''
Line 30: Line 33:
 * '''''Ready to install'''''  * '''ready to install'''
Line 33: Line 36:
 * --('''''Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts...''''')--
 * '''''We have tip-tilts from LHO'''''
 * --(Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts)--
 * tip-tilts:
  * --(tip-tilts from LHO)--
Line 36: Line 40:
    * assembled
 * Needed electronics:
    * DAC?
    * anti-image filters?
    * dewhite filters?
    * coil drivers?
    * eurocrate?
 * __'''''Need in vacuum-compatible ones and the non-vacuum ones'''''__
 * Full assembly with mirrors
 * Prepare feedthrough connectors
 * Digital controls
    * --(assembled)--
    * add mirrors
    * level
 * in-vac cables (quadrapuses)
    * __'''''place order with RND Cables'''''__
 * electronics:
    * gather components:
      * DAC
      * anti-image filters
      * dewhite filters
      * coil drivers
      * eurocrate
      * cables
    * install
    * test in DAQ
Line 48: Line 56:
(5) Mode-matching telescope adjustments (Jenne/Suresh)
 * Need to determine what exactly the problem is.
   * What needs to be moved?
(5) New periscope plate
  * --(manufactured)--
  * --(baked)--
  * '''ready to install'''
  * __'''''need shorter pedestals for green PBS and beam dump'''''__

Vent plans

Prep for next vent

(1) Dichroic mirror for recycling cavities (Jamie)

(2) Black glass beam dumps

(3) OSEM mount screws

  • requirements:
    • Hex-top, longer, sliver-plated
    • Qty = 100
    • No-plastic
  • final design

  • manufactured

  • baked

  • ready to install

(4) Active tip-tilts (Suresh/Jamie)

  • Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts

  • tip-tilts:
    • tip-tilts from LHO

    • baked

    • assembled

    • add mirrors
    • level
  • in-vac cables (quadrapuses)
    • place order with RND Cables

  • electronics:
    • gather components:
      • DAC
      • anti-image filters
      • dewhite filters
      • coil drivers
      • eurocrate
      • cables
    • install
    • test in DAQ

(5) New periscope plate

  • manufactured

  • baked

  • ready to install

  • need shorter pedestals for green PBS and beam dump

(6) Cavity scattering measurements? (Jan)

(7) Review IP{ANG,POS} alignment/closeup proceedure

Previous