Line 7: Line 7:
 * wedge angle = 2 deg
Line 9: Line 8:
   * [[https://wiki-40m.ligo.caltech.edu/vent?action=AttachFile&do=get&target=ATF.pdf|ATF]]    * --([[https://wiki-40m.ligo.caltech.edu/vent?action=AttachFile&do=get&target=ATF.pdf|ATF]])--
Line 13: Line 12:
 * '''''order placed...''''' '''(ETA still unknown)'''  * '''''We have mirrors in hand!'''''
 * Phase map of mirror, in and out of tip-tilt mounts
Line 24: Line 24:
 * Hex-top, longer, sliver-plated
 * Qty = 100
 * No-plastic
   * Hex-top, longer, sliver-plated
   * Qty = 100
   * No-plastic
Line 28: Line 28:
 * '''''manufactured and being baked...'''''  * --(manufactured)--
 * --(baked)--
 * '''''Ready to install'''''
Line 31: Line 33:
 * to get:
   * Tip-tilts from LHO
   * Electronics
   * Cables including vacuum-compatible ones and the non-vacuum ones
   * Prepare mirrors
   * Assembly and baking
   * Prepare feedthrough connectors
   * Digital controls
 * '''''Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts...'''''
 * --('''''Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts...''''')--
 * '''''We have tip-tilts from LHO'''''
    * --(baked)--
    * assembled
 * Needed electronics:
    * DAC?
    * anti-image filters?
    * dewhite filters?
    * coil drivers?
    * eurocrate?
 * __'''''Need in vacuum-compatible ones and the non-vacuum ones'''''__
 * Full assembly with mirrors
 * Prepare feedthrough connectors
 * Digital controls

Vent plans

Prep for next vent

(1) Dichroic mirror for recycling cavities (Jamie)

(2) Black glass beam dumps

(3) OSEM mount screws

  • Hex-top, longer, sliver-plated
  • Qty = 100
  • No-plastic

(4) Active tip-tilts (Suresh/Jamie)

  • Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts...

  • We have tip-tilts from LHO

    • baked

    • assembled
  • Needed electronics:
    • DAC?
    • anti-image filters?
    • dewhite filters?
    • coil drivers?
    • eurocrate?
  • Need in vacuum-compatible ones and the non-vacuum ones

  • Full assembly with mirrors
  • Prepare feedthrough connectors
  • Digital controls

(5) Mode-matching telescope adjustments (Jenne/Suresh)

  • Need to determine what exactly the problem is.
    • What needs to be moved?

(6) Cavity scattering measurements? (Jan)

(7) Review IP{ANG,POS} alignment/closeup proceedure