Line 32: Line 32:
   * tip-tilts from LHO    * Tip-tilts from LHO
Line 41: Line 41:
(5) OMC activation (Jenne)
 * Calculate the mode matching solutions and prepare appropriate telescopes
 * Draw optical layout
 * Digital controls
(5) Mode-matching telescope adjustments (Jenne/Suresh)
 * Need to determine what exactly the problem is.
   * What needs to be moved?
Line 46: Line 45:
(6) OSEM upgrade (somebody)
 * Need a discussion
(6) Cavity scattering measurements? (Jan)

Vent plans

Prep for next vent

(1) Dichroic mirror for recycling cavities (Jamie)

(2) Black glass beam dumps

(3) OSEM mount screws

  • Hex-top, longer, sliver-plated
  • Qty = 100
  • No-plastic
  • final design

  • manufactured and being baked...

(4) Active tip-tilts (Suresh/Jamie)

  • to get:
    • Tip-tilts from LHO
    • Electronics
    • Cables including vacuum-compatible ones and the non-vacuum ones
    • Prepare mirrors
    • Assembly and baking
    • Prepare feedthrough connectors
    • Digital controls
  • Suresh is going to LHO April 15-25 for assembly/shipping of tip-tilts...

(5) Mode-matching telescope adjustments (Jenne/Suresh)

  • Need to determine what exactly the problem is.
    • What needs to be moved?

(6) Cavity scattering measurements? (Jan)