== Prep for next vent ==

(1) Dichroic mirror for recycling cavities (Jamie)
 * [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=87589|spec in DCC]]
 * wedge angle = 2 deg
 * quotes:
   * [[https://wiki-40m.ligo.caltech.edu/vent?action=AttachFile&do=get&target=ATF.pdf|ATF]]
   * '''''[[https://wiki-40m.ligo.caltech.edu/vent?action=AttachFile&do=get&target=Laseroptik.pdf|Laseroptik (final)]]'''''
     * note: 2 deg wedge quote has Fused Silica grade F = 5 ppm homogeneity & micro roughness 0.3 nm RMS, Rana OKed both, 3 wks delivery, Jamie takes care of ordering
 * [[Optical_Layout#PR3SR3|Optical table layout needs to be modified]]

(2) Black glass beam dumps (Koji)
 * Large baffle style covers for the suspensions
 * Small V-shape pieces for generic purpose
   * [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=77367|hexagonal]]
   * [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=77543|diamond shaped]]
   * [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=77545|diamond shaped (2inch)]]
 * '''''being baked...'''''

(3) OSEM mount screws (Steve)
 * Hex-top, longer, sliver-plated
 * Qty = 100
 * No-plastic
 * '''''[[http://nodus.ligo.caltech.edu:8080/40m/6472|final design]]'''''
 * '''''manufactured and being baked...'''''

(4) Active tip-tilts (Suresh/Jamie)
 * to get:
   * tip-tilts from LHO
   * Electronics
   * Cables including vacuum-compatible ones and the non-vacuum ones
   * Prepare mirrors
   * Assembly and baking
   * Prepare feedthrough connectors
   * Digital controls
 * '''''Suresh is going to LHO April 15-25 for assembly/shipping...'''''

(5) OMC activation (Jenne)
 * Calculate the mode matching solutions and prepare appropriate telescopes
 * Draw optical layout
 * Digital controls

(6) OSEM upgrade (somebody)
 * Need a discussion

== Previous ==
Line 4: Line 51:
 * [[Vent_Jul_2010|2010 July]]
 * [[Optics_Cleaning| 2009 Dec]]
 * [[Vent_Sep_2006|2006 September]]
Line 5: Line 55:
 * [[Vent_Jul_2010|2010 July]]
 * [[Vent_Sep_2006|2006 September]]
 * [[Upgrade_09|IFO Upgrade 2009-2010]]

Vent plans

Prep for next vent

(1) Dichroic mirror for recycling cavities (Jamie)

(2) Black glass beam dumps (Koji)

(3) OSEM mount screws (Steve)

  • Hex-top, longer, sliver-plated
  • Qty = 100
  • No-plastic
  • final design

  • manufactured and being baked...

(4) Active tip-tilts (Suresh/Jamie)

  • to get:
    • tip-tilts from LHO
    • Electronics
    • Cables including vacuum-compatible ones and the non-vacuum ones
    • Prepare mirrors
    • Assembly and baking
    • Prepare feedthrough connectors
    • Digital controls
  • Suresh is going to LHO April 15-25 for assembly/shipping...

(5) OMC activation (Jenne)

  • Calculate the mode matching solutions and prepare appropriate telescopes
  • Draw optical layout
  • Digital controls

(6) OSEM upgrade (somebody)

  • Need a discussion