Line 1: Line 1:
#pragma section-numbers off
#pragma section-numbers 2
Line 2: Line 4:
<<TableOfContents(4)>>
Line 6: Line 9:
List item you need before completing this whole section
 * Item 1
 * Item 2

List every action (maybe from other sections) you need completed before completing this section
 * Action 1
 * Action 2

=== Specific tasks and details ===
List down the sub tasks here:
==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ====
Requirements:
Details of the task.
List items you need before completing this whole section
 * Clean 3"->2" optics adapter parts (Side blocks, balance weights, mirror clamps)
        * Adapter rings, wire clamp, wire block and retainer rings are all clean on the flow bench
        * Waiting for machined balance masses from RDL ETA ~1 week
        * All hardware except 8-32 Helicoils are cleaned and ready for assembly, eta on Helicoils ~1 week
 * HeNe Laser
 * Suspension Wire (wrapped and stored in the clean room)
 * Dummy 2" mirror
 * The mirrors that actually go into the vacuum.

=== Specific tasks and details ===

==== Gluing / SUS building [Oct 4 to Oct 11] (YD, JV, TE) ====
Requirements:

 * Dumbell+magnet assemblies need to be glued onto the optics adapter. 4 on the ring and 1 on a side block for each SOS.
 * One last round of dumbell+magnet gluing.
 * Testing of bond strength of last dumbell+magnet batches.

 * for the side magnets, we need longer assembly to avoid interference with the clamping screws. -> an additional magnet will be glued on a magnet-dumbbel pair.

Estimated time: 3 Days

 * Assembly drawing ~75% complete, will be ready 10/11/21
 
==== Suspending [Oct 4 to Oct 11] (YD, TE) ====
Requirements:

 * Need to push a few already clean Viton tips into 1/4" screws to be used as EQ stops. Assemble those EQ stops onto the SOSs.
 * Suspend dummy mirror for balance testing.
 * Balance the dummy mirror using the HeNe laser. Adding and moving weights for adjustments.
 * Suspend and balance actual mirrors that go into the vacuum using what we learned by experimenting with the dummy mirror.
 * Suspension order of optics and origin of the optics:
   1. PR3 | [[https://dcc.ligo.org/LIGO-E1800089|E1800089]] | Arrived in Feb 2019. In Clean Optic Cabinet in Xend.
   2. SR2 | [[https://dcc.ligo.org/LIGO-E1800089|E1800089]] | Arrived in Feb 2019. In Clean Optic Cabinet in Xend.
   3. LO1 | [[https://dcc.ligo.org/LIGO-E2000226|E2000226-C]] | Lambda Optic. In Clean Optic Cabinet in Xend.
   4. LO2 | [[https://dcc.ligo.org/LIGO-E1800089|E1800089]] | Arrived in Feb 2019. In Clean Optic Cabinet in Xend.
   5. AS1 | [[https://dcc.ligo.org/LIGO-E2000226|E2000226-A]] | Lambda Optic. In Clean Optic Cabinet in Xend.
   6. AS4 | [[https://dcc.ligo.org/LIGO-E2000226|E2000226-B]] | Lambda Optic. In Clean Optic Cabinet in Xend.
   7. PR2 | Use existing PR2. | Kept in the cleanroom in old small suspension.
 * OSEM use:
   || Optic || Face OSEMS || Side OSEM || Long Yellow Grade || Long Green Grade|| Small Yellow Grade|| Small Green Grade||
   || LO1 || 4 Long Yellow || 1 Small Yellow || 4 || 0 || 1 || 0 ||
   || LO2 || 4 Small Yellow|| 1 Small Yellow || 0 || 0 || 5 || 0 ||
   || AS1 || 4 Long Green || 1 Long Green || 0 || 5 || 0 || 0 ||
   || AS4 || 4 Long Green || 1 Long Green || 0 || 5 || 0 || 0 ||
   || PR2 || 4 Small (3G, 1Y)|| 1 Small Green|| 0 || 0 || 1 || 4 ||
   || PR3 || 4 Small Green || 1 Small Green || 0 || 0 || 0 || 5 ||
   || SR2 || 4 Small Green || 1 Small Green || 0 || 0 || 0 || 5 ||
   || Total to use|| - || - || 4 || 10 || 7 || 14 ||
   || In-hand|| - || - || 12 || 10 || 8 || 14 ||

Estimated time: 2 weeks

----
== Vent [Oct 18 to Dec 6] ==

Current 40m in-vac optics layout [[https://caltech.box.com/s/83x9fgb1n36f6k5n073zsgxhx321vjo5]]

New 40m in-vac optics layout [[https://caltech.box.com/s/gm4smqn8quelxqlgtch038asinwfgyfv]]

=== Overall Requirements ===

List item you need before completing this whole section
 * SOS kicking test (~Oct 14)
 * IFO alignment / Oplev centering / QPD centering / MC power reduction and locking
 * N2 bottles (x2)

List every action (maybe from other sections) you need completed before completing this section
 *

=== Specific tasks and details ===
List down the sub tasks here:

==== In vacuum cable procurement [Oct 4 to Nov 8] (CO, JV, KA) ====

20 cable quote taken, the order placed. Arrived 10/21/2021

Associated hardware: invacuum cable brackets, assessment in the elog [[https://nodus.ligo.caltech.edu:8081/40m/16404]]. We will order Qty6. Jordan is on it.

==== Chamber opening [Oct 25 to Nov 1] (CO ++) ====
Requirements:
 * The optics have been suspended and are ready for installation.

Details of the task.

Estimated time: 1 week

==== Vacuum repair [Oct 18 to Nov 1] (JV, CO) ====
Requirements:
 * 10" CF gaskets
 * Silver plated hardware for 10" clearance flange

Details of the task.
 
Line 20: Line 106:
==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ====
Requirements:
Details of the task.
Estimated time:
...
----
== Vent ==
=== Overall Requirements ===

List item you need before completing this whole section
 * Item 1
 * Item 2

List every action (maybe from other sections) you need completed before completing this section
 * Action 1
 * Action 2

=== Specific tasks and details ===
List down the sub tasks here:
==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ====
Requirements:
Details of the task.
Estimated time:
==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ====
Requirements:
Details of the task.
Estimated time:
...

==== Existing optics Alignment/ table cleaning [Oct 18 to Nov 1] (PS, AG) ====
Requirements: None

Details of the task:
 * Match the current layout with the schematic and mark what is changed.
 * Remove the optics that need to be taken out for space for new stuff.
 * Align the existing optics better.

Estimated time: 2 weeks

==== Align the new optics [Oct 25 to Nov 22] (PS, AG, YD, TE) ====
Requirements: Space cleared as per new optical layout.

Details of the task:
 * Install the new suspended optics in their place.
 *

Estimated time: 4 weeks

==== In vacuum cable installation [Nov 8 to Nov 15] (JV, CO ++) ====
Requirements: All in-vac cables procured

Details of the task:

Estimated time: 1 week
Line 52: Line 137:

[[attachment:rack_plan_211101.pdf|{{attachment:rack_plan_211101.png||width=1000}}]]
Line 60: Line 148:
Line 62: Line 151:
Details of the task.
Estimated time:4 weeks

Details of the task
 * [[vent/planningFall2021/VertexRacks_InAirCable|Cable lengths assessment]]

Estimated time: 4 weeks

Status: Custom/Long DB cables ordered (11/1, KA, CO) -> Delivered -> C&Bed -> ready to be installed

-> 4 cables for ITMX installed [[https://nodus.ligo.caltech.edu:8081/40m/16513]]
Line 65: Line 162:
Requirements: None

Details of the task:
Clear the rack space in YARM 1Y3.

Requirements: None

Details of the task:
 * Clear the rack space in YARM 1Y3.
Line 73: Line 171:
Requirements: None
Details of the task.

Requirements: None

Details of the task.
Line 79: Line 180:
Details of the task.
Details of the task.
Line 84: Line 187:
Line 88: Line 192:
Estimated time: 2 weeks

==== CDS integration work [Nov 15 to Nov 22] (AG ++) ====

Estimated time: 2 weeks

==== CDS integration work [Nov 15 to Nov 22] (AG, IM) ====
Line 98: Line 203:
 * C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack.

Estimated time: 1 week

==== Damping test [Nov15 to Nov 22] (AG, PS) ====
 * {{attachment:40mCDSPlanned.png|40m CDS Plan}}
 * [[https://drive.google.com/file/d/1x3xBWCHH0yJvsw1U1qMybt9uwJZjJpEb/view|Live link to plan]]. Anyone can edit with ligo.org credentials.


Estimated time: 1 week

==== Damping test [Nov15 to Nov 22] (AG, PS, IM) ====
Line 119: Line 226:
 *

List every action (maybe from other sections) you need completed before completing this section
 *

=== Specific tasks and details ===
List down the sub tasks here:

==== End QPD cable [Oct 18 to Oct 25] (KA) ====

Detail: There was a mistake in the IDC40-DB9 cable. Fix it. Update/create DCC entries.

==== End electronics Design [Oct 18 to Oct 25] (KA) ====

Requirements: None

Details: Design ADC adapter unit PCB / Front & rear panels.

Estimated time: 1 week

==== End electronics proc [Oct 25 to Nov 1] (CO, KA) ====

Requirements: After designing.

Details: Procure PCBs for ADC/DAC adapter unit. Procure Front/rear Panels. Procure components.

Estimated time: 2 weeks

==== End electronics fab [Nov 1 to Nov 8] (TE, PS) ====
Requirements: After procurement.

Details: Build electronics.

Estimated time: 1 weeks

----
== BHD Tasks ==
=== Overall Requirements ===

List item you need before completing this whole section
Line 130: Line 277:
Details of the task.
Details of the task.
Line 134: Line 283:
Details of the task.
Details of the task.
Line 138: Line 289:
== BHD Tasks ==
=== Overall Requirements ===

List item you need before completing this whole section
 * Item 1
 * Item 2

List every action (maybe from other sections) you need completed before completing this section
 * Action 1
 * Action 2

=== Specific tasks and details ===
List down the sub tasks here:
==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ====
Requirements:
Details of the task.
Estimated time:
==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ====
Requirements:
Details of the task.
Estimated time:
...
----

Vent planning for Fall 2021


1. Clean Room SUS Work

1.1. Overall Requirements

List items you need before completing this whole section

  • Clean 3"->2" optics adapter parts (Side blocks, balance weights, mirror clamps)

    • Adapter rings, wire clamp, wire block and retainer rings are all clean on the flow bench
    • Waiting for machined balance masses from RDL ETA ~1 week
    • All hardware except 8-32 Helicoils are cleaned and ready for assembly, eta on Helicoils ~1 week
  • HeNe Laser

  • Suspension Wire (wrapped and stored in the clean room)
  • Dummy 2" mirror
  • The mirrors that actually go into the vacuum.

1.2. Specific tasks and details

1.2.1. Gluing / SUS building [Oct 4 to Oct 11] (YD, JV, TE)

Requirements:

  • Dumbell+magnet assemblies need to be glued onto the optics adapter. 4 on the ring and 1 on a side block for each SOS.
  • One last round of dumbell+magnet gluing.
  • Testing of bond strength of last dumbell+magnet batches.
  • for the side magnets, we need longer assembly to avoid interference with the clamping screws. -> an additional magnet will be glued on a magnet-dumbbel pair.

Estimated time: 3 Days

  • Assembly drawing ~75% complete, will be ready 10/11/21

1.2.2. Suspending [Oct 4 to Oct 11] (YD, TE)

Requirements:

  • Need to push a few already clean Viton tips into 1/4" screws to be used as EQ stops. Assemble those EQ stops onto the SOSs.
  • Suspend dummy mirror for balance testing.
  • Balance the dummy mirror using the HeNe laser. Adding and moving weights for adjustments.

  • Suspend and balance actual mirrors that go into the vacuum using what we learned by experimenting with the dummy mirror.
  • Suspension order of optics and origin of the optics:
    1. PR3 | E1800089 | Arrived in Feb 2019. In Clean Optic Cabinet in Xend.

    2. SR2 | E1800089 | Arrived in Feb 2019. In Clean Optic Cabinet in Xend.

    3. LO1 | E2000226-C | Lambda Optic. In Clean Optic Cabinet in Xend.

    4. LO2 | E1800089 | Arrived in Feb 2019. In Clean Optic Cabinet in Xend.

    5. AS1 | E2000226-A | Lambda Optic. In Clean Optic Cabinet in Xend.

    6. AS4 | E2000226-B | Lambda Optic. In Clean Optic Cabinet in Xend.

    7. PR2 | Use existing PR2. | Kept in the cleanroom in old small suspension.
  • OSEM use:
    • Optic

      Face OSEMS

      Side OSEM

      Long Yellow Grade

      Long Green Grade

      Small Yellow Grade

      Small Green Grade

      LO1

      4 Long Yellow

      1 Small Yellow

      4

      0

      1

      0

      LO2

      4 Small Yellow

      1 Small Yellow

      0

      0

      5

      0

      AS1

      4 Long Green

      1 Long Green

      0

      5

      0

      0

      AS4

      4 Long Green

      1 Long Green

      0

      5

      0

      0

      PR2

      4 Small (3G, 1Y)

      1 Small Green

      0

      0

      1

      4

      PR3

      4 Small Green

      1 Small Green

      0

      0

      0

      5

      SR2

      4 Small Green

      1 Small Green

      0

      0

      0

      5

      Total to use

      -

      -

      4

      10

      7

      14

      In-hand

      -

      -

      12

      10

      8

      14

Estimated time: 2 weeks


2. Vent [Oct 18 to Dec 6]

Current 40m in-vac optics layout https://caltech.box.com/s/83x9fgb1n36f6k5n073zsgxhx321vjo5

New 40m in-vac optics layout https://caltech.box.com/s/gm4smqn8quelxqlgtch038asinwfgyfv

2.1. Overall Requirements

List item you need before completing this whole section

  • SOS kicking test (~Oct 14)
  • IFO alignment / Oplev centering / QPD centering / MC power reduction and locking
  • N2 bottles (x2)

List every action (maybe from other sections) you need completed before completing this section

2.2. Specific tasks and details

List down the sub tasks here:

2.2.1. In vacuum cable procurement [Oct 4 to Nov 8] (CO, JV, KA)

20 cable quote taken, the order placed. Arrived 10/21/2021

Associated hardware: invacuum cable brackets, assessment in the elog https://nodus.ligo.caltech.edu:8081/40m/16404. We will order Qty6. Jordan is on it.

2.2.2. Chamber opening [Oct 25 to Nov 1] (CO ++)

Requirements:

  • The optics have been suspended and are ready for installation.

Details of the task.

Estimated time: 1 week

2.2.3. Vacuum repair [Oct 18 to Nov 1] (JV, CO)

Requirements:

  • 10" CF gaskets
  • Silver plated hardware for 10" clearance flange

Details of the task.

Estimated time:

2.2.4. Existing optics Alignment/ table cleaning [Oct 18 to Nov 1] (PS, AG)

Requirements: None

Details of the task:

  • Match the current layout with the schematic and mark what is changed.
  • Remove the optics that need to be taken out for space for new stuff.
  • Align the existing optics better.

Estimated time: 2 weeks

2.2.5. Align the new optics [Oct 25 to Nov 22] (PS, AG, YD, TE)

Requirements: Space cleared as per new optical layout.

Details of the task:

  • Install the new suspended optics in their place.

Estimated time: 4 weeks

2.2.6. In vacuum cable installation [Nov 8 to Nov 15] (JV, CO ++)

Requirements: All in-vac cables procured

Details of the task:

Estimated time: 1 week


3. Vertex Racks

3.1. Overall Requirements

attachment:rack_plan_211101.pdf

List item you need before completing this whole section

  • 1 GBps Ethernet cables from 1Y3 to 1X6.

List every action (maybe from other sections) you need completed before completing this section

  • Suspending the optics

3.2. Specific tasks and details

List down the sub tasks here:

3.2.1. In-air cable procurement [Oct 4 to Oct 25] (KA)

Requirements: None

Details of the task

Estimated time: 4 weeks

Status: Custom/Long DB cables ordered (11/1, KA, CO) -> Delivered -> C&Bed -> ready to be installed

-> 4 cables for ITMX installed https://nodus.ligo.caltech.edu:8081/40m/16513

3.2.2. Electronics rack work [Oct 4 to Oct 11] (PS, AG)

Requirements: None

Details of the task:

  • Clear the rack space in YARM 1Y3.

Estimated time: 1 week

3.2.3. Vertex electronics design [Oct 4 to Oct 18] (KA)

Requirements: None

Details of the task.

Estimated time: 3 weeks

3.2.4. Vertex electronics proc [Oct 25 to Nov 1] (KA)

Requirements: Design needs to be finished

Details of the task.

Estimated time: 2 weeks

Requirements: None

Details of the task:

  • Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++.
  • Copy the esiting suspension models from C1SUS to make C1SUS2 model.
  • New medm screens for the new suspensions and BHD.

Estimated time: 2 weeks

3.2.6. CDS integration work [Nov 15 to Nov 22] (AG, IM)

Requirements:

  • Need to finish testing teststand
  • 1Y3 rack needs to be cleared up.
  • 1 GBps Ethernet cables from 1Y3 to 1X6.
  • Make sure we have all cables are there with required lengths.

Details of the task:

Estimated time: 1 week

3.2.7. Damping test [Nov15 to Nov 22] (AG, PS, IM)

Requirements:

  • All suspensions must be suspended by now.
  • All electronics should be in their positions with requried cabling.
  • C1SUS2 and C1BHD must be installed and running.
  • All realtime models for new suspensions must be built, installed and started.

Details of the task:

  • Do in-air tests of suspension damping.

Estimated time: 1 week


4. End Racks

4.1. Overall Requirements

List item you need before completing this whole section

List every action (maybe from other sections) you need completed before completing this section

4.2. Specific tasks and details

List down the sub tasks here:

4.2.1. End QPD cable [Oct 18 to Oct 25] (KA)

Detail: There was a mistake in the IDC40-DB9 cable. Fix it. Update/create DCC entries.

4.2.2. End electronics Design [Oct 18 to Oct 25] (KA)

Requirements: None

Details: Design ADC adapter unit PCB / Front & rear panels.

Estimated time: 1 week

4.2.3. End electronics proc [Oct 25 to Nov 1] (CO, KA)

Requirements: After designing.

Details: Procure PCBs for ADC/DAC adapter unit. Procure Front/rear Panels. Procure components.

Estimated time: 2 weeks

4.2.4. End electronics fab [Nov 1 to Nov 8] (TE, PS)

Requirements: After procurement.

Details: Build electronics.

Estimated time: 1 weeks


5. BHD Tasks

5.1. Overall Requirements

List item you need before completing this whole section

  • Item 1
  • Item 2

List every action (maybe from other sections) you need completed before completing this section

  • Action 1
  • Action 2

5.2. Specific tasks and details

List down the sub tasks here:

5.2.1. Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)

Requirements:

Details of the task.

Estimated time:

5.2.2. Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)

Requirements:

Details of the task.

Estimated time: ...