Line 53: Line 53:
 * Item 1
 * Item 2
 * 1 GBps Ethernet cables from 1Y3 to 1X6.
Line 57: Line 56:
 * Action 1
 * Action 2
 * Suspending the optics
Line 67: Line 65:
Requirements: Requirements: None
Line 82: Line 80:
Estimated time: 2 weeks

==== New Simulink models & medm screens [Oct 11 to Oct 25] (IM) ====
Requirements: None
Details of the task:
 * Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++.
 * Copy the esiting suspension models from C1SUS to make C1SUS2 model.
 * New medm screens for the new suspensions and BHD.

Vent planning for Fall 2021


Clean Room SUS Work

Overall Requirements

List item you need before completing this whole section

  • Item 1
  • Item 2

List every action (maybe from other sections) you need completed before completing this section

  • Action 1
  • Action 2

Specific tasks and details

List down the sub tasks here:

Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)

Requirements: Details of the task. Estimated time:

Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)

Requirements: Details of the task. Estimated time: ...


Vent

Overall Requirements

List item you need before completing this whole section

  • Item 1
  • Item 2

List every action (maybe from other sections) you need completed before completing this section

  • Action 1
  • Action 2

Specific tasks and details

List down the sub tasks here:

Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)

Requirements: Details of the task. Estimated time:

Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)

Requirements: Details of the task. Estimated time: ...


Vertex Racks

Overall Requirements

List item you need before completing this whole section

  • 1 GBps Ethernet cables from 1Y3 to 1X6.

List every action (maybe from other sections) you need completed before completing this section

  • Suspending the optics

Specific tasks and details

List down the sub tasks here:

In-air cable procurement [Oct 4 to Oct 25] (KA)

Requirements: None Details of the task. Estimated time:4 weeks

Electronics rack work [Oct 4 to Oct 11] (PS, AG)

Requirements: None

Details of the task: Clear the rack space in YARM 1Y3.

Estimated time: 1 week

Vertex electronics design [Oct 4 to Oct 18] (KA)

Requirements: None Details of the task. Estimated time: 3 weeks

Vertex electronics proc [Oct 25 to Nov 1] (KA)

Requirements: Design needs to be finished Details of the task. Estimated time: 2 weeks

Requirements: None Details of the task:

  • Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++.
  • Copy the esiting suspension models from C1SUS to make C1SUS2 model.
  • New medm screens for the new suspensions and BHD.

Estimated time: 2 weeks

CDS integration work [Nov 15 to Nov 22] (AG ++)

Requirements:

  • Need to finish testing teststand
  • 1Y3 rack needs to be cleared up.
  • 1 GBps Ethernet cables from 1Y3 to 1X6.
  • Make sure we have all cables are there with required lengths.

Details of the task:

  • C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack.

Estimated time: 1 week

Damping test [Nov15 to Nov 22] (AG, PS)

Requirements:

  • All suspensions must be suspended by now.
  • All electronics should be in their positions with requried cabling.
  • C1SUS2 and C1BHD must be installed and running.
  • All realtime models for new suspensions must be built, installed and started.

Details of the task:

  • Do in-air tests of suspension damping.

Estimated time: 1 week


End Racks

Overall Requirements

List item you need before completing this whole section

  • Item 1
  • Item 2

List every action (maybe from other sections) you need completed before completing this section

  • Action 1
  • Action 2

Specific tasks and details

List down the sub tasks here:

Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)

Requirements: Details of the task. Estimated time:

Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)

Requirements: Details of the task. Estimated time: ...


BHD Tasks

Overall Requirements

List item you need before completing this whole section

  • Item 1
  • Item 2

List every action (maybe from other sections) you need completed before completing this section

  • Action 1
  • Action 2

Specific tasks and details

List down the sub tasks here:

Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)

Requirements: Details of the task. Estimated time:

Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)

Requirements: Details of the task. Estimated time: ...