| Line 53: | Line 53: |
| * Item 1 * Item 2 |
* 1 GBps Ethernet cables from 1Y3 to 1X6. |
| Line 57: | Line 56: |
| * Action 1 * Action 2 |
* Suspending the optics |
| Line 67: | Line 65: |
| Requirements: | Requirements: None |
| Line 82: | Line 80: |
| Estimated time: 2 weeks ==== New Simulink models & medm screens [Oct 11 to Oct 25] (IM) ==== Requirements: None Details of the task: * Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++. * Copy the esiting suspension models from C1SUS to make C1SUS2 model. * New medm screens for the new suspensions and BHD. |
Vent planning for Fall 2021
Clean Room SUS Work
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...
Vent
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...
Vertex Racks
Overall Requirements
List item you need before completing this whole section
- 1 GBps Ethernet cables from 1Y3 to 1X6.
List every action (maybe from other sections) you need completed before completing this section
- Suspending the optics
Specific tasks and details
List down the sub tasks here:
In-air cable procurement [Oct 4 to Oct 25] (KA)
Requirements: None Details of the task. Estimated time:4 weeks
Electronics rack work [Oct 4 to Oct 11] (PS, AG)
Requirements: None
Details of the task: Clear the rack space in YARM 1Y3.
Estimated time: 1 week
Vertex electronics design [Oct 4 to Oct 18] (KA)
Requirements: None Details of the task. Estimated time: 3 weeks
Vertex electronics proc [Oct 25 to Nov 1] (KA)
Requirements: Design needs to be finished Details of the task. Estimated time: 2 weeks
New Simulink models & medm screens [Oct 11 to Oct 25] (IM)
Requirements: None Details of the task:
- Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++.
- Copy the esiting suspension models from C1SUS to make C1SUS2 model.
- New medm screens for the new suspensions and BHD.
Estimated time: 2 weeks
CDS integration work [Nov 15 to Nov 22] (AG ++)
Requirements:
- Need to finish testing teststand
- 1Y3 rack needs to be cleared up.
- 1 GBps Ethernet cables from 1Y3 to 1X6.
- Make sure we have all cables are there with required lengths.
Details of the task:
- C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack.
Estimated time: 1 week
Damping test [Nov15 to Nov 22] (AG, PS)
Requirements:
- All suspensions must be suspended by now.
- All electronics should be in their positions with requried cabling.
- C1SUS2 and C1BHD must be installed and running.
- All realtime models for new suspensions must be built, installed and started.
Details of the task:
- Do in-air tests of suspension damping.
Estimated time: 1 week
End Racks
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...
BHD Tasks
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...