| ==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ==== | ==== In-air cable procurement [Oct 4 to Oct 25] (KA) ==== Requirements: None Details of the task. Estimated time:4 weeks ==== Electronics rack work [Oct 4 to Oct 11] (PS, AG) ==== |
| Line 64: | Line 68: |
Details of the task: Clear the rack space in YARM 1Y3. Estimated time: 1 week ==== Vertex electronics design [Oct 4 to Oct 18] (KA) ==== Requirements: None |
|
| Line 65: | Line 77: |
| Estimated time: ==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ==== |
Estimated time: 3 weeks ==== Vertex electronics proc [Oct 25 to Nov 1] (KA) ==== Requirements: Design needs to be finished Details of the task. Estimated time: 2 weeks ==== CDS integration work [Nov 15 to Nov 22] (AG ++) ==== |
| Line 68: | Line 86: |
| Details of the task. Estimated time: ... |
* Need to finish testing teststand * 1Y3 rack needs to be cleared up. * 1 GBps Ethernet cables from 1Y3 to 1X6. * Make sure we have all cables are there with required lengths. Details of the task: * C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack. Estimated time: 1 week ==== Damping test [Nov15 to Nov 22] (AG, PS) ==== Requirements: * All suspensions must be suspended by now. * All electronics should be in their positions with requried cabling. * C1SUS2 and C1BHD must be installed and running. * All realtime models for new suspensions must be built, installed and started. Details of the task: * Do in-air tests of suspension damping. Estimated time: 1 week |
Vent planning for Fall 2021
Clean Room SUS Work
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...
Vent
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...
Vertex Racks
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
In-air cable procurement [Oct 4 to Oct 25] (KA)
Requirements: None Details of the task. Estimated time:4 weeks
Electronics rack work [Oct 4 to Oct 11] (PS, AG)
Requirements:
Details of the task: Clear the rack space in YARM 1Y3.
Estimated time: 1 week
Vertex electronics design [Oct 4 to Oct 18] (KA)
Requirements: None Details of the task. Estimated time: 3 weeks
Vertex electronics proc [Oct 25 to Nov 1] (KA)
Requirements: Design needs to be finished Details of the task. Estimated time: 2 weeks
CDS integration work [Nov 15 to Nov 22] (AG ++)
Requirements:
- Need to finish testing teststand
- 1Y3 rack needs to be cleared up.
- 1 GBps Ethernet cables from 1Y3 to 1X6.
- Make sure we have all cables are there with required lengths.
Details of the task:
- C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack.
Estimated time: 1 week
Damping test [Nov15 to Nov 22] (AG, PS)
Requirements:
- All suspensions must be suspended by now.
- All electronics should be in their positions with requried cabling.
- C1SUS2 and C1BHD must be installed and running.
- All realtime models for new suspensions must be built, installed and started.
Details of the task:
- Do in-air tests of suspension damping.
Estimated time: 1 week
End Racks
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...
BHD Tasks
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...