| === Overall Requirements === List item you need before completing this whole section * List every action (maybe from other sections) you need completed before completing this section * === Specific tasks and details === List down the sub tasks here: ==== Gluing / SUS building [Oct 4 to Oct 11] (YD, JV, TE) ==== Requirements: Details of the task. Estimated time:2 weeks ==== Suspending [Oct 4 to Oct 11] (YD, TE) ==== Requirements: Details of the task. Estimated time: 2 weeks ---- == Vent [Oct 18 to Dec 6] == |
|
| Line 16: | Line 37: |
| ==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ==== | ==== Chamber opening [Oct 25 to Nov 1] (CO ++) ==== Requirements: * The optics have been suspended and are ready for installation. Details of the task. Estimated time: 1 week ==== Vacuum repair [Oct 18 to Nov 1] (JV, CO) ==== |
| Line 20: | Line 47: |
| ==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ==== Requirements: Details of the task. Estimated time: ... ---- == Vent == === Overall Requirements === |
|
| Line 29: | Line 48: |
| List item you need before completing this whole section * Item 1 * Item 2 |
==== Existing optics Alignment/ table cleaning [Oct 18 to Nov 1] (PS, AG) ==== Requirements: None Details of the task: * Match the current layout with the schematic and mark what is changed. * Remove the optics that need to be taken out for space for new stuff. * Align the existing optics better. Estimated time: 2 weeks |
| Line 33: | Line 56: |
| List every action (maybe from other sections) you need completed before completing this section * Action 1 * Action 2 |
==== Align the new optics [Oct 25 to Nov 22] (PS, AG, YD, TE) ==== Requirements: Space cleared as per new optical layout. Details of the task: * Install the new suspended optics in their place. * |
| Line 37: | Line 62: |
| === Specific tasks and details === List down the sub tasks here: ==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ==== Requirements: Details of the task. Estimated time: ==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ==== Requirements: Details of the task. Estimated time: ... |
|
| Line 53: | Line 68: |
| * Item 1 * Item 2 |
* 1 GBps Ethernet cables from 1Y3 to 1X6. |
| Line 57: | Line 71: |
| * Action 1 * Action 2 |
* Suspending the optics |
| Line 62: | Line 75: |
| ==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ==== | ==== In-air cable procurement [Oct 4 to Oct 25] (KA) ==== Requirements: None Details of the task. Estimated time:4 weeks ==== Electronics rack work [Oct 4 to Oct 11] (PS, AG) ==== Requirements: None Details of the task: Clear the rack space in YARM 1Y3. Estimated time: 1 week ==== Vertex electronics design [Oct 4 to Oct 18] (KA) ==== Requirements: None Details of the task. Estimated time: 3 weeks ==== Vertex electronics proc [Oct 25 to Nov 1] (KA) ==== Requirements: Design needs to be finished Details of the task. Estimated time: 2 weeks ==== New Simulink models & medm screens [Oct 11 to Oct 25] (IM) ==== Requirements: None Details of the task: * Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++. * Copy the esiting suspension models from C1SUS to make C1SUS2 model. * New medm screens for the new suspensions and BHD. Estimated time: 2 weeks ==== CDS integration work [Nov 15 to Nov 22] (AG, IM) ==== |
| Line 64: | Line 107: |
| Details of the task. Estimated time: ==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ==== |
* Need to finish testing teststand * 1Y3 rack needs to be cleared up. * 1 GBps Ethernet cables from 1Y3 to 1X6. * Make sure we have all cables are there with required lengths. Details of the task: * C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack. Estimated time: 1 week ==== Damping test [Nov15 to Nov 22] (AG, PS) ==== |
| Line 68: | Line 119: |
| Details of the task. Estimated time: ... |
* All suspensions must be suspended by now. * All electronics should be in their positions with requried cabling. * C1SUS2 and C1BHD must be installed and running. * All realtime models for new suspensions must be built, installed and started. Details of the task: * Do in-air tests of suspension damping. Estimated time: 1 week |
| Line 76: | Line 134: |
| * Item 1 * Item 2 |
* |
| Line 80: | Line 137: |
| * Action 1 * Action 2 |
* |
| Line 85: | Line 141: |
| ==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ==== Requirements: |
==== End electronics Design [Oct 18 to Oct 25] (KA) ==== Requirements: None |
| Line 88: | Line 144: |
| Estimated time: ==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ==== Requirements: |
Estimated time: 1 week ==== End electronics proc [Oct 25 to Nov 1] (CO, KA) ==== Requirements: After designing. |
| Line 92: | Line 149: |
| Estimated time: | Estimated time: 2 weeks ==== End electronics fab [Nov 1 to Nov 8] (TE, PS) ==== Requirements: After procurement. Details of the task. Estimated time: 1 weeks |
Vent planning for Fall 2021
1. Clean Room SUS Work
1.1. Overall Requirements
List item you need before completing this whole section
List every action (maybe from other sections) you need completed before completing this section
1.2. Specific tasks and details
List down the sub tasks here:
1.2.1. Gluing / SUS building [Oct 4 to Oct 11] (YD, JV, TE)
Requirements: Details of the task. Estimated time:2 weeks
1.2.2. Suspending [Oct 4 to Oct 11] (YD, TE)
Requirements: Details of the task. Estimated time: 2 weeks
2. Vent [Oct 18 to Dec 6]
2.1. Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
2.2. Specific tasks and details
List down the sub tasks here:
2.2.1. Chamber opening [Oct 25 to Nov 1] (CO ++)
Requirements:
- The optics have been suspended and are ready for installation.
Details of the task. Estimated time: 1 week
2.2.2. Vacuum repair [Oct 18 to Nov 1] (JV, CO)
Requirements: Details of the task. Estimated time:
2.2.3. Existing optics Alignment/ table cleaning [Oct 18 to Nov 1] (PS, AG)
Requirements: None Details of the task:
- Match the current layout with the schematic and mark what is changed.
- Remove the optics that need to be taken out for space for new stuff.
- Align the existing optics better.
Estimated time: 2 weeks
2.2.4. Align the new optics [Oct 25 to Nov 22] (PS, AG, YD, TE)
Requirements: Space cleared as per new optical layout. Details of the task:
- Install the new suspended optics in their place.
3. Vertex Racks
3.1. Overall Requirements
List item you need before completing this whole section
- 1 GBps Ethernet cables from 1Y3 to 1X6.
List every action (maybe from other sections) you need completed before completing this section
- Suspending the optics
3.2. Specific tasks and details
List down the sub tasks here:
3.2.1. In-air cable procurement [Oct 4 to Oct 25] (KA)
Requirements: None Details of the task. Estimated time:4 weeks
3.2.2. Electronics rack work [Oct 4 to Oct 11] (PS, AG)
Requirements: None
Details of the task: Clear the rack space in YARM 1Y3.
Estimated time: 1 week
3.2.3. Vertex electronics design [Oct 4 to Oct 18] (KA)
Requirements: None Details of the task. Estimated time: 3 weeks
3.2.4. Vertex electronics proc [Oct 25 to Nov 1] (KA)
Requirements: Design needs to be finished Details of the task. Estimated time: 2 weeks
3.2.5. New Simulink models & medm screens [Oct 11 to Oct 25] (IM)
Requirements: None Details of the task:
- Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++.
- Copy the esiting suspension models from C1SUS to make C1SUS2 model.
- New medm screens for the new suspensions and BHD.
Estimated time: 2 weeks
3.2.6. CDS integration work [Nov 15 to Nov 22] (AG, IM)
Requirements:
- Need to finish testing teststand
- 1Y3 rack needs to be cleared up.
- 1 GBps Ethernet cables from 1Y3 to 1X6.
- Make sure we have all cables are there with required lengths.
Details of the task:
- C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack.
Estimated time: 1 week
3.2.7. Damping test [Nov15 to Nov 22] (AG, PS)
Requirements:
- All suspensions must be suspended by now.
- All electronics should be in their positions with requried cabling.
- C1SUS2 and C1BHD must be installed and running.
- All realtime models for new suspensions must be built, installed and started.
Details of the task:
- Do in-air tests of suspension damping.
Estimated time: 1 week
4. End Racks
4.1. Overall Requirements
List item you need before completing this whole section
List every action (maybe from other sections) you need completed before completing this section
4.2. Specific tasks and details
List down the sub tasks here:
4.2.1. End electronics Design [Oct 18 to Oct 25] (KA)
Requirements: None Details of the task. Estimated time: 1 week
4.2.2. End electronics proc [Oct 25 to Nov 1] (CO, KA)
Requirements: After designing. Details of the task. Estimated time: 2 weeks
4.2.3. End electronics fab [Nov 1 to Nov 8] (TE, PS)
Requirements: After procurement. Details of the task. Estimated time: 1 weeks ...
5. BHD Tasks
5.1. Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
5.2. Specific tasks and details
List down the sub tasks here:
5.2.1. Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
5.2.2. Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...