|
Size: 6113
Comment:
|
Size: 6084
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 14: | Line 14: |
| List down the sub tasks here: |
Vent planning for Fall 2021
Clean Room SUS Work
Overall Requirements
List items you need before completing this whole section
Clean 3"->2" optics adapter parts (Side blocks, balance weights, mirror clamps)
HeNe Laser
- Suspension Wire
- Dummy 2" mirror
- The mirrors that actually go into the vacuum.
Specific tasks and details
Gluing / SUS building [Oct 4 to Oct 11] (YD, JV, TE)
Requirements:
- Dumbell+magnet assemblies need to be glued onto the optics adapter. 4 on the ring and 1 on a side block for each SOS.
- One last round of dumbell+magnet gluing.
- Testing of bond strength of last dumbell+magnet batches.
Estimated time: 3 Days
Suspending [Oct 4 to Oct 11] (YD, TE)
Requirements:
- Need to push a few already clean Viton tips into 1/4" screws to be used as EQ stops. Assemble those EQ stops onto the SOSs.
- Suspend dummy mirror for balance testing.
Balance the dummy mirror using the HeNe laser. Adding and moving weights for adjustments.
- Suspend and balance actual mirrors that go into the vacuum using what we learned by experimenting with the dummy mirror.
Estimated time: 2 weeks
Vent [Oct 18 to Dec 6]
Overall Requirements
List item you need before completing this whole section
List every action (maybe from other sections) you need completed before completing this section
Specific tasks and details
List down the sub tasks here:
In vacuum cable procurement [Oct 4 to Nov 8] (CO, KA)
Requirements: None
Details of the task:
Estimated time: 5 weeks
Chamber opening [Oct 25 to Nov 1] (CO ++)
Requirements:
- The optics have been suspended and are ready for installation.
Details of the task.
Estimated time: 1 week
Vacuum repair [Oct 18 to Nov 1] (JV, CO)
Requirements:
Details of the task.
Estimated time:
Existing optics Alignment/ table cleaning [Oct 18 to Nov 1] (PS, AG)
Requirements: None
Details of the task:
- Match the current layout with the schematic and mark what is changed.
- Remove the optics that need to be taken out for space for new stuff.
- Align the existing optics better.
Estimated time: 2 weeks
Align the new optics [Oct 25 to Nov 22] (PS, AG, YD, TE)
Requirements: Space cleared as per new optical layout.
Details of the task:
- Install the new suspended optics in their place.
Estimated time: 4 weeks
In vacuum cable installation [Nov 8 to Nov 15] (JV, CO ++)
Requirements: All in-vac cables procured
Details of the task:
Estimated time: 1 week
Vertex Racks
Overall Requirements
List item you need before completing this whole section
- 1 GBps Ethernet cables from 1Y3 to 1X6.
List every action (maybe from other sections) you need completed before completing this section
- Suspending the optics
Specific tasks and details
List down the sub tasks here:
In-air cable procurement [Oct 4 to Oct 25] (KA)
Requirements: None
Details of the task.
Estimated time:4 weeks
Electronics rack work [Oct 4 to Oct 11] (PS, AG)
Requirements: None
Details of the task:
- Clear the rack space in YARM 1Y3.
Estimated time: 1 week
Vertex electronics design [Oct 4 to Oct 18] (KA)
Requirements: None
Details of the task.
Estimated time: 3 weeks
Vertex electronics proc [Oct 25 to Nov 1] (KA)
Requirements: Design needs to be finished
Details of the task.
Estimated time: 2 weeks
New Simulink models & medm screens [Oct 11 to Oct 25] (IM)
Requirements: None
Details of the task:
- Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++.
- Copy the esiting suspension models from C1SUS to make C1SUS2 model.
- New medm screens for the new suspensions and BHD.
Estimated time: 2 weeks
CDS integration work [Nov 15 to Nov 22] (AG, IM)
Requirements:
- Need to finish testing teststand
- 1Y3 rack needs to be cleared up.
- 1 GBps Ethernet cables from 1Y3 to 1X6.
- Make sure we have all cables are there with required lengths.
Details of the task:
- C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack.
Estimated time: 1 week
Damping test [Nov15 to Nov 22] (AG, PS)
Requirements:
- All suspensions must be suspended by now.
- All electronics should be in their positions with requried cabling.
- C1SUS2 and C1BHD must be installed and running.
- All realtime models for new suspensions must be built, installed and started.
Details of the task:
- Do in-air tests of suspension damping.
Estimated time: 1 week
End Racks
Overall Requirements
List item you need before completing this whole section
List every action (maybe from other sections) you need completed before completing this section
Specific tasks and details
List down the sub tasks here:
End electronics Design [Oct 18 to Oct 25] (KA)
Requirements: None
Details of the task.
Estimated time: 1 week
End electronics proc [Oct 25 to Nov 1] (CO, KA)
Requirements: After designing.
Details of the task.
Estimated time: 2 weeks
End electronics fab [Nov 1 to Nov 8] (TE, PS)
Requirements: After procurement.
Details of the task.
Estimated time: 1 weeks ...
BHD Tasks
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements:
Details of the task.
Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements:
Details of the task.
Estimated time: ...
