| ---- == Clean Room SUS Work == === Overall Requirements === |
|
| Line 3: | Line 6: |
| == Clean Room Work == | List item you need before completing this whole section * Item 1 * Item 2 |
| Line 5: | Line 10: |
| List every action (maybe from other sections) you need completed before completing this section * Action 1 * Action 2 === Specific tasks and details === List down the sub tasks here: ==== Gluing / SUS building [Oct 4 to Oct 11] (YD, JV, TE) ==== Requirements: Details of the task. Estimated time:2 weeks ==== Suspending [Oct 4 to Oct 11] (YD, TE) ==== Requirements: Details of the task. Estimated time: 2 weeks ---- |
|
| Line 6: | Line 27: |
| === Overall Requirements === | |
| Line 7: | Line 29: |
| List item you need before completing this whole section * Item 1 * Item 2 List every action (maybe from other sections) you need completed before completing this section * Action 1 * Action 2 === Specific tasks and details === List down the sub tasks here: ==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ==== Requirements: Details of the task. Estimated time: ==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ==== Requirements: Details of the task. Estimated time: ... ---- |
|
| Line 8: | Line 50: |
| === Overall Requirements === | |
| Line 9: | Line 52: |
| List item you need before completing this whole section * 1 GBps Ethernet cables from 1Y3 to 1X6. List every action (maybe from other sections) you need completed before completing this section * Suspending the optics === Specific tasks and details === List down the sub tasks here: ==== In-air cable procurement [Oct 4 to Oct 25] (KA) ==== Requirements: None Details of the task. Estimated time:4 weeks ==== Electronics rack work [Oct 4 to Oct 11] (PS, AG) ==== Requirements: None Details of the task: Clear the rack space in YARM 1Y3. Estimated time: 1 week ==== Vertex electronics design [Oct 4 to Oct 18] (KA) ==== Requirements: None Details of the task. Estimated time: 3 weeks ==== Vertex electronics proc [Oct 25 to Nov 1] (KA) ==== Requirements: Design needs to be finished Details of the task. Estimated time: 2 weeks ==== New Simulink models & medm screens [Oct 11 to Oct 25] (IM) ==== Requirements: None Details of the task: * Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++. * Copy the esiting suspension models from C1SUS to make C1SUS2 model. * New medm screens for the new suspensions and BHD. Estimated time: 2 weeks ==== CDS integration work [Nov 15 to Nov 22] (AG, IM) ==== Requirements: * Need to finish testing teststand * 1Y3 rack needs to be cleared up. * 1 GBps Ethernet cables from 1Y3 to 1X6. * Make sure we have all cables are there with required lengths. Details of the task: * C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack. Estimated time: 1 week ==== Damping test [Nov15 to Nov 22] (AG, PS) ==== Requirements: * All suspensions must be suspended by now. * All electronics should be in their positions with requried cabling. * C1SUS2 and C1BHD must be installed and running. * All realtime models for new suspensions must be built, installed and started. Details of the task: * Do in-air tests of suspension damping. Estimated time: 1 week ---- |
|
| Line 10: | Line 116: |
| === Overall Requirements === List item you need before completing this whole section * List every action (maybe from other sections) you need completed before completing this section * === Specific tasks and details === List down the sub tasks here: ==== End electronics Design [Oct 18 to Oct 25] (KA) ==== Requirements: None Details of the task. Estimated time: 1 week ==== End electronics proc [Oct 25 to Nov 1] (CO, KA) ==== Requirements: After designing. Details of the task. Estimated time: 2 weeks ==== End electronics fab [Nov 1 to Nov 8] (TE, PS) ==== Requirements: After procurement. Details of the task. Estimated time: 1 weeks ... ---- == BHD Tasks == === Overall Requirements === List item you need before completing this whole section * Item 1 * Item 2 List every action (maybe from other sections) you need completed before completing this section * Action 1 * Action 2 === Specific tasks and details === List down the sub tasks here: ==== Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape) ==== Requirements: Details of the task. Estimated time: ==== Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger) ==== Requirements: Details of the task. Estimated time: ... ---- |
Vent planning for Fall 2021
Clean Room SUS Work
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Gluing / SUS building [Oct 4 to Oct 11] (YD, JV, TE)
Requirements: Details of the task. Estimated time:2 weeks
Suspending [Oct 4 to Oct 11] (YD, TE)
Requirements: Details of the task. Estimated time: 2 weeks
Vent
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...
Vertex Racks
Overall Requirements
List item you need before completing this whole section
- 1 GBps Ethernet cables from 1Y3 to 1X6.
List every action (maybe from other sections) you need completed before completing this section
- Suspending the optics
Specific tasks and details
List down the sub tasks here:
In-air cable procurement [Oct 4 to Oct 25] (KA)
Requirements: None Details of the task. Estimated time:4 weeks
Electronics rack work [Oct 4 to Oct 11] (PS, AG)
Requirements: None
Details of the task: Clear the rack space in YARM 1Y3.
Estimated time: 1 week
Vertex electronics design [Oct 4 to Oct 18] (KA)
Requirements: None Details of the task. Estimated time: 3 weeks
Vertex electronics proc [Oct 25 to Nov 1] (KA)
Requirements: Design needs to be finished Details of the task. Estimated time: 2 weeks
New Simulink models & medm screens [Oct 11 to Oct 25] (IM)
Requirements: None Details of the task:
- Prepare a signal flow diagram for C1SUS2 and C1BHD models with consultation from KA ++.
- Copy the esiting suspension models from C1SUS to make C1SUS2 model.
- New medm screens for the new suspensions and BHD.
Estimated time: 2 weeks
CDS integration work [Nov 15 to Nov 22] (AG, IM)
Requirements:
- Need to finish testing teststand
- 1Y3 rack needs to be cleared up.
- 1 GBps Ethernet cables from 1Y3 to 1X6.
- Make sure we have all cables are there with required lengths.
Details of the task:
- C1SUS2, C1BHD, and their IO chasis would be moved to YARM 1Y3 rack.
Estimated time: 1 week
Damping test [Nov15 to Nov 22] (AG, PS)
Requirements:
- All suspensions must be suspended by now.
- All electronics should be in their positions with requried cabling.
- C1SUS2 and C1BHD must be installed and running.
- All realtime models for new suspensions must be built, installed and started.
Details of the task:
- Do in-air tests of suspension damping.
Estimated time: 1 week
End Racks
Overall Requirements
List item you need before completing this whole section
List every action (maybe from other sections) you need completed before completing this section
Specific tasks and details
List down the sub tasks here:
End electronics Design [Oct 18 to Oct 25] (KA)
Requirements: None Details of the task. Estimated time: 1 week
End electronics proc [Oct 25 to Nov 1] (CO, KA)
Requirements: After designing. Details of the task. Estimated time: 2 weeks
End electronics fab [Nov 1 to Nov 8] (TE, PS)
Requirements: After procurement. Details of the task. Estimated time: 1 weeks ...
BHD Tasks
Overall Requirements
List item you need before completing this whole section
- Item 1
- Item 2
List every action (maybe from other sections) you need completed before completing this section
- Action 1
- Action 2
Specific tasks and details
List down the sub tasks here:
Sub-task 1 [Oct 11 to Oct 25] (TM Riddle, S Snape)
Requirements: Details of the task. Estimated time:
Sub-task 2 [Oct 18 to Nov 1] (HJ Potter, HJ Grainger)
Requirements: Details of the task. Estimated time: ...