== Part I: Optics removal on westside of BS Table == == Part II: Relocation of TT2 and MMT1/2 alignment to TT2 == == Part III: PRC Folding mirror placement == == Part IV: SR3 replacement == == Part V: LO Path up to LO2 setup == == Part : AS Path setup == == Part : BS Path setup == == Part : POP Path setup == == Part : POX Path setup == == Part : POY Path setup == == Part : AS RFPD Path setup == == Part : Green transmission paths == == Part : ITMX oplevs == Can we push the mirrors back to keep more clearance? == Part : ITMY oplevs == == Part : BS, PRM SRM oplevs == == Part : Place PRM and SRM == == Part : Pre-pump alignment and clearance check == == Pump down == == Elog posts == * [[https://nodus.ligo.caltech.edu:8081/40m/16410|40m/16410: Vent Started/Completed]] |
BHR Upgrade Phase I - Vent of Fall 2021
Venting process
Mon Oct 18th, 2021
- Checked the main volume is isolated.
- TP1 and TP2 were made isolated from other volumes. Stopped TP1. Closed V4 to isolate TP1 from TP2.
- TP3 was made isolated. TP3 was stopped.
- We wanted to vent annuli, but it was not allowed as VA6 was open. We closed VA6 and vented the annuli with VAVEE.
- We wanted to vent the volume between VA6, V5, VM3, V7 together with TP1. So V7 was opened. This did not change the TP1 pressure (P2 = 1.7mmTorr) .
- We wanted to connect the TP1 volume with the main volume. But this was not allowed as TP1 was not rotating. We will vent TP1 through TP2 once the vent of the main volume is done.
- Started venting the main volume@Oct 18, 2021 9:45AM PDT
- We started from 10mTorr/min, and increased the vent speed to 200mTorr/min, 700mTorr/min, and now it is 1Torr/min @ 20Torr
- 280Torr @11:50AM
- 1atm @~2PM
We wanted to vent TP1. We rerun the TP2 and tried to slowly introduce the air via TP2. But the interlock prevents the action.
Part I: Optics removal on westside of BS Table
Part II: Relocation of TT2 and MMT1/2 alignment to TT2
Part III: PRC Folding mirror placement
Part IV: SR3 replacement
Part V: LO Path up to LO2 setup
Part : AS Path setup
Part : BS Path setup
Part : POP Path setup
Part : POX Path setup
Part : POY Path setup
Part : AS RFPD Path setup
Part : Green transmission paths
Part : ITMX oplevs
Can we push the mirrors back to keep more clearance?
Part : ITMY oplevs
Part : BS, PRM SRM oplevs
Part : Place PRM and SRM
Part : Pre-pump alignment and clearance check
Pump down