Mon Oct 18th, 2021
Line 18: Line 19:
{{attachment:VentTrendFall2021.png}} {{attachment:VentScreenFall2021.png}} {{attachment:VentTrendFall2021.png|Trend|width=500}} {{attachment:VentScreenFall2021.png|Screen|width=500}}

== Part I: Optics removal on westside of BS Table ==

== Part II: Relocation of TT2 and MMT1/2 alignment to TT2 ==

== Part III: PRC Folding mirror placement ==

== Part IV: SR3 replacement ==
 * Clear East side of BS table

== Part V: SRM Oplev setup ==

== Part VI: POY Path setup ==

== Part VII: LO Path up to LO2 setup ==

== Part VIII: AS Path setup ==

 * Clear the ITMY table. Following optics need to be removed:
   * POYM1
   * ITMY OL1
   * ITMY OL2
  ...


== Part IX: BHDBS Path setup ==

 * Setting up LO3, LO4, BHDBS

== Part X: POP Path setup ==

== Part XI: POX Path setup ==

== Part XII: AS RFPD Path setup ==

== Part XIII: Green transmission paths ==

== Part XIV: ITMX oplevs ==

Can we push the mirrors back to keep more clearance?

== Part XV: ITMY oplevs ==

== Part XVI: Place PRM and SRM ==

== Part XVII: BS, PRM oplevs ==

== Part XVIII: Pre-pump alignment and clearance check ==

== Pump down ==





== Elog posts ==

* [[https://nodus.ligo.caltech.edu:8081/40m/16410|40m/16410: Vent Started/Completed]]

BHR Upgrade Phase I - Vent of Fall 2021

Venting process

Mon Oct 18th, 2021

  • Checked the main volume is isolated.
  • TP1 and TP2 were made isolated from other volumes. Stopped TP1. Closed V4 to isolate TP1 from TP2.
  • TP3 was made isolated. TP3 was stopped.
  • We wanted to vent annuli, but it was not allowed as VA6 was open. We closed VA6 and vented the annuli with VAVEE.
  • We wanted to vent the volume between VA6, V5, VM3, V7 together with TP1. So V7 was opened. This did not change the TP1 pressure (P2 = 1.7mmTorr) .
  • We wanted to connect the TP1 volume with the main volume. But this was not allowed as TP1 was not rotating. We will vent TP1 through TP2 once the vent of the main volume is done.
  • Started venting the main volume@Oct 18, 2021 9:45AM PDT
  • We started from 10mTorr/min, and increased the vent speed to 200mTorr/min, 700mTorr/min, and now it is 1Torr/min @ 20Torr
  • 280Torr @11:50AM
  • 1atm @~2PM

We wanted to vent TP1. We rerun the TP2 and tried to slowly introduce the air via TP2. But the interlock prevents the action.

Trend Screen

Part I: Optics removal on westside of BS Table

Part II: Relocation of TT2 and MMT1/2 alignment to TT2

Part III: PRC Folding mirror placement

Part IV: SR3 replacement

  • Clear East side of BS table

Part V: SRM Oplev setup

Part VI: POY Path setup

Part VII: LO Path up to LO2 setup

Part VIII: AS Path setup

  • Clear the ITMY table. Following optics need to be removed:
    • POYM1
    • ITMY OL1
    • ITMY OL2
    • ..

Part IX: BHDBS Path setup

  • Setting up LO3, LO4, BHDBS

Part X: POP Path setup

Part XI: POX Path setup

Part XII: AS RFPD Path setup

Part XIII: Green transmission paths

Part XIV: ITMX oplevs

Can we push the mirrors back to keep more clearance?

Part XV: ITMY oplevs

Part XVI: Place PRM and SRM

Part XVII: BS, PRM oplevs

Part XVIII: Pre-pump alignment and clearance check

Pump down

Elog posts

* 40m/16410: Vent Started/Completed