Vent plan for July 2011
Overview
Major tasks for vent:
- Optimize cavity lengths: PRC, SRC, MICH, arms, etc.
- This will involve moving at least (but hopefully at most) one ITM to adjust the MICH Schnupp asymmetry. We will then need to move the ETMs and P/SRMs accordingly to set the proper arm/recycling cavity lengths.
See wiki page on cavity lengths: IFO Modeling/RC lengths
- Extract Y green beam from vacuum
- The green locking beam from the Y-arm is currently not making it out of the vacuum. We need to fix this by adjusting the green periscope. We will then need to adjust the X-arm green beam as well.
- Align pick-off port: POX, POY, POP
- Make sure all of these beams are cleaning making it out of the vacuum on to the PO PDs.
- Align IPANG QPD (eliminate clipping)
- Cleanly position the IPANG beam on the IPANG QPD.
- Replace green steering mirrors PR3/SR3 with optics with better coatings.
Maybe:
- Adjust OSEM rotation to minimize unwanted couplings.
- Install green light beam dumps.
- Replace PR2 for better green transmission.
Preparation
We need precise measurements of the cavity lengths in order to determine where exactly we need to move the test masses.
[http://nodus.ligo.caltech.edu:8080/40m/4821 Michelson Schnupp asymmetry]
- Power recycling cavity (PRCL)
- Signal recycling cavity (SRCL)
Measurements:
MICH = lx - ly = 3.62 cm PRCL = (lx+ly)/2 + lsr = ? SRCL = (lx+ly)/2 + lpr = ?
Questions:
- What are all of the current cavity lengths, and what should they be?
- Which ITM do we need to move, and by how much?
- Where do we need to move ETMX/Y, P/SRM?
- Do we need to move the BS?
- How exactly do we move the suspended optics? How will we know they're in the right place?
- Do we need better optics for the green beams? Are the AR coatings of the current ones ok?
- Where do we need to install beam dumps?
- Do we need more black glass or polished stainless beam dumps?
- How do we test the OSEM positioning?
Vent
door removal
- BSC north
- ITMYC north
- ITMXC west
- ETMYC north
- ETMXC west
Procedure
This is a preliminary procedure plan:
CR:
- Lock Y-arm green
- Reduce power to mode cleaner (appropriate level for in-air MC locking)
IOOC north access:
- Adjust green periscope to extract Y green transmission
CR:
- Lock X green
IOOC north access:
- Align X green trans through green periscope
BSC north access:
- Adjust IPANG
CR:
- Misalign PRM
ITMYC north access:
- Move ITMY into position
ITMXC west access:
- Move ITMX into position
CR:
- Realign PRM
ETMYC north access:
- Move ETMY for YARM
ETMXC west access:
- Move ETMX for XARM
BSC north access:
- Move PRM for PRC
BSC north access:
- Move SRM for SRC
- Align pick-offs