This is a preliminary procedure plan:

Vent plan for July 2011

Overview

Major tasks for vent:

  • Optimize cavity lengths: PRC, SRC, MICH, arms, etc.
    • This will involve moving at least (but hopefully at most) one ITM to adjust the MICH Schnupp asymmetry. We will then need to move the ETMs and P/SRMs accordingly to set the proper arm/recycling cavity lengths.
    • See wiki page on cavity lengths: IFO Modeling/RC lengths

  • Extract Y green beam from vacuum
    • The green locking beam from the Y-arm is currently not making it out of the vacuum. We need to fix this by adjusting the green periscope. We will then need to adjust the X-arm green beam as well.
  • Align pick-off port: POX, POY, POP
    • Make sure all of these beams are cleaning making it out of the vacuum on to the PO PDs.
  • Align IPANG QPD (eliminate clipping)
    • Cleanly position the IPANG beam on the IPANG QPD.
  • Replace green steering mirrors PR3/SR3 with optics with better coatings.

Maybe:

  • Adjust OSEM rotation to minimize unwanted couplings.
  • Install green light beam dumps.
  • Replace PR2 for better green transmission.

Preparation

We need precise measurements of the cavity lengths in order to determine where exactly we need to move the test masses.

Measurements:

MICH = lx - ly = 3.62 cm
PRCL = (lx+ly)/2 + lsr = ?
SRCL = (lx+ly)/2 + lpr = ?

Questions:

  • What are all of the current cavity lengths, and what should they be?
  • Which ITM do we need to move, and by how much?
  • Where do we need to move ETMX/Y, P/SRM?
  • Do we need to move the BS?
  • How exactly do we move the suspended optics? How will we know they're in the right place?
  • Do we need better optics for the green beams? Are the AR coatings of the current ones ok?
  • Where do we need to install beam dumps?
  • Do we need more black glass or polished stainless beam dumps?
  • How do we test the OSEM positioning?

Vent

door removal

  1. BSC north
  2. ITMYC north
  3. ITMXC west
  4. ETMYC north
  5. ETMXC west

Procedure

This is a preliminary procedure plan:

CR:

  1. Lock Y-arm green
  2. Reduce power to mode cleaner (appropriate level for in-air MC locking)

IOOC north access:

  1. Adjust green periscope to extract Y green transmission

CR:

  1. Lock X green

IOOC north access:

  1. Align X green trans through green periscope

BSC north access:

  1. Adjust IPANG

CR:

  1. Misalign PRM

ITMYC north access:

  1. Move ITMY into position

ITMXC west access:

  1. Move ITMX into position

CR:

  1. Realign PRM

ETMYC north access:

  1. Move ETMY for YARM

ETMXC west access:

  1. Move ETMX for XARM

BSC north access:

  1. Move PRM for PRC

BSC north access:

  1. Move SRM for SRC
  2. Align pick-offs

Equipment list