| Describe Upgrade 09/PSL here. | == Overview == 1. We will be removing the MOPA and replacing it with a 2W NPRO. 1. Instead of current shunt, we will change to use an AOM for the fast power stabilization actuator. 1. We may decide to use a DC coupled servo, with a remotely programmable offset point to be more like the aLIGO system. 1. Move the reference cavity and its optics to a different pickoff point. 1. Move the ISS to the end of the PSL table. 1. Re-engineer the optics for the PSL_POS and PSL_ANG QPDs. 1. New EOM for triple modulation. 1. Change the FSS modulation frequency? 1. Change the FSS RFPD to have a low Q? 1. Remove the PMC RF modulation (apply it via the NPRO)? 1. Steel enclosure for the PMC to do temperature stabilization? attachment:newlayout.png === FSS === === New NPRO === === PMC === === ISS === === Modulator === |
Overview
- We will be removing the MOPA and replacing it with a 2W NPRO.
- Instead of current shunt, we will change to use an AOM for the fast power stabilization actuator.
- We may decide to use a DC coupled servo, with a remotely programmable offset point to be more like the aLIGO system.
- Move the reference cavity and its optics to a different pickoff point.
- Move the ISS to the end of the PSL table.
- Re-engineer the optics for the PSL_POS and PSL_ANG QPDs.
- New EOM for triple modulation.
- Change the FSS modulation frequency?
- Change the FSS RFPD to have a low Q?
- Remove the PMC RF modulation (apply it via the NPRO)?
- Steel enclosure for the PMC to do temperature stabilization?