Overview

  1. We will be removing the MOPA and replacing it with a 2W NPRO.
  2. Instead of current shunt, we will change to use an AOM for the fast power stabilization actuator.
  3. We may decide to use a DC coupled servo, with a remotely programmable offset point to be more like the aLIGO system.
  4. Move the reference cavity and its optics to a different pickoff point.
  5. Move the ISS to the end of the PSL table.
  6. Re-engineer the optics for the PSL_POS and PSL_ANG QPDs.
  7. New EOM for triple modulation.
  8. Change the FSS modulation frequency?
  9. Change the FSS RFPD to have a low Q?
  10. Remove the PMC RF modulation (apply it via the NPRO)?
  11. Steel enclosure for the PMC to do temperature stabilization?

Upgrade 09/PSL

FSS

New NPRO

2W Innolight manual (PDF)

2W Innolight data sheet (PDF)

2W Innolight item list (PDF)

"Upgrade 09/PSL"

PMC

ISS

Modulator

Upgrade_09/PSL (last edited 2012-01-03 23:03:06 by localhost)