40m upgrade installation plan
Main optics team
Pre-vent works
- Tuning of the MC servo ~ low power MC test
- End transmon X/Y Optics relocations (before the vent) for green
- ITM pointing preparations? (green/red pointers at the both ends)
Vent
- What to do before the vent?
- Tuning of the MC servo ~ low power MC test
- ITM pointing preparations? (green/red pointers at the both ends)
ITM placement
- What to do before the ITM placement?
- Suspension assembly
- Gluing test
- Optics cleaning
- Gluing (magnets/standoffs/guide rods)
- Suspending
- procedure
MMT placement
- What to do before the MMT placement?
- Optics delivery (Shipping Feb 25) / baking
- corridor projection test
Initial Pointing adjustment
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
- TT
- purchase magnets (small/large)
- Closing up the vacuum
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- set up the green stuff onto the end table
- align the green laser to the cavity (how to ?)
mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount
after closing the tanks
- recover IP-ANG and optical levers
CDS team
RF team
PSL table upgrade
- Laser delivery (done)