40m upgrade installation plan

Main optics team

  • Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End transmon X/Y Optics relocations (before the vent) for green
    • ITM pointing preparations? (green/red pointers at the both ends)
  • Vent

    • What to do before the vent?
    • Tuning of the MC servo ~ low power MC test
    • ITM pointing preparations? (green/red pointers at the both ends)
  • ITM placement

    • What to do before the ITM placement?
    • Suspension assembly
      • Gluing test
      • Optics cleaning
      • Gluing (magnets/standoffs/guide rods)
      • Suspending
    • procedure
  • MMT placement

    • What to do before the MMT placement?
    • Optics delivery (Shipping Feb 25) / baking
    • corridor projection test
  • Initial Pointing adjustment

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • purchase magnets (small/large)
  • Closing up the vacuum


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity (how to ?)
    • mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount

  • after closing the tanks

    • recover IP-ANG and optical levers


CDS team


RF team


PSL table upgrade

  • Laser delivery (done)