Line 2: Line 2:
Line 4: Line 3:
Line 18: Line 16:
  * Gluing test
  * Optics cleaning
  * Gluing (magnets/standoffs/guide rods)
    * Suspending
  * procedure  
   * Gluing test
   * Optics cleaning
   * Gluing (magnets/standoffs/guide rods)
   * Suspending
  * procedure
Line 33: Line 31:
   * purchase magnets (small/large)
Line 37: Line 36:
== Green team ==
 * ''' before vent'''
  * relocation of existing optics at the end table -''take 1.5day''
 * '''during vent'''
  * set up the green stuff onto the end table
  * align the green laser to the cavity (how to ?)
  * mode matching of the green laser to the cavity
 * ''' after closing the tanks'''
  * recover IP-ANG and optical levers
Line 38: Line 46:
== Green team ==

 * ''' before vent'''
   * relocation of existing optics at the end table
 * '''during vent'''
   * set up the green stuff onto the end table
   * align the green laser to the cavity (how to ?)
   * mode matching of the green laser to the cavity
 * ''' after closing the tanks'''
   * recover IP-ANG and optical levers
Line 49: Line 47:
Line 51: Line 48:
Line 55: Line 51:
Line 57: Line 52:
Line 59: Line 53:
Line 61: Line 54:

40m upgrade installation plan

Main optics team

  • Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End transmon X/Y Optics relocations (before the vent) for green
    • ITM pointing preparations? (green/red pointers at the both ends)
  • Vent

    • What to do before the vent?
    • Tuning of the MC servo ~ low power MC test
    • ITM pointing preparations? (green/red pointers at the both ends)
  • ITM placement

    • What to do before the ITM placement?
    • Suspension assembly
      • Gluing test
      • Optics cleaning
      • Gluing (magnets/standoffs/guide rods)
      • Suspending
    • procedure
  • MMT placement

    • What to do before the MMT placement?
    • Optics delivery (Shipping Feb 25) / baking
  • Initial Pointing adjustment

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • purchase magnets (small/large)
  • Closing up the vacuum


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity (how to ?)
    • mode matching of the green laser to the cavity
  • after closing the tanks

    • recover IP-ANG and optical levers


CDS team


RF team


PSL table upgrade

  • Laser delivery (done)