Differences between revisions 7 and 59 (spanning 52 versions)
Revision 7 as of 2010-02-13 03:16:30
Size: 1433
Editor: KiwamuIzumi
Comment:
Revision 59 as of 2012-01-03 23:02:40
Size: 3379
Editor: localhost
Comment: converted to 1.6 markup
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
<<TableOfContents(3)>>
Line 2: Line 3:
[[Past_Plans]]
Line 5: Line 7:
 * '''Pre-vent works'''
  * Tuning of the MC servo ~ low power MC test
  * End transmon X/Y Optics relocations (before the vent) for green
  * ITM pointing preparations? (green/red pointers at the both ends)
Line 10: Line 8:
 * '''Vent'''
  * What to do before the vent?
  * Tuning of the MC servo ~ low power MC test
  * ITM pointing preparations? (green/red pointers at the both ends)
 * '''IOO work'''
  * '''[DONE]''' Moving faraday and input optics
Line 15: Line 11:
 * '''ITM placement'''
  * What to do before the ITM placement?
  * Suspension assembly
    * Gluing test
    * Optics cleaning
    * Gluing (magnets/standoffs/guide rods)
    * Suspending
  * procedure
 * '''MMT placement / initial pointing adjustment'''
  * '''[DONE]''' MC trans beam mode measurement
  * '''[DONE]''' Renew the MMT solution
Line 24: Line 15:
 * '''MMT placement'''
  * What to do before the MMT placement?
  * Optics delivery (Shipping Feb 25) / baking
  * '''[DONE]''' MMT placement
  * '''[DONE]''' Corridor projection ~ measuremnt & adjustment
  * '''[DONE]''' Initial Pointing adjustment
Line 28: Line 19:
 * '''Initial Pointing adjustment'''  * '''[DONE]''' ITMX/Y oplev
Line 31: Line 22:
  * What to do before the SRM/PRM/BS placement?
  * TT
  * '''[DONE]''' What to do before the SRM/PRM/BS placement?
  * '''[DONE]''' TT ==> TT preparations
Line 34: Line 25:
 * Closing up the vacuum  * '''[DONE]''' AUX optics alignment

 * '''[DONE]''' Closing up the vacuum
Line 37: Line 30:
== Suspension preparation ==
Line 38: Line 32:
== Green team ==

 * ''' before vent'''
   * relocation of existing optics at the end table
 * '''during vent'''
   * set up the green stuff onto the end table
   * align the green laser to the cavity (how to ?)
   * mode matching of the green laser to the cavity
 * ''' after closing the tanks'''
   * recover IP-ANG and optical levers
---------

== CDS team ==

 *
{{attachment:StatusTable.png}}
Line 55: Line 35:
== Green team ==
 * ''' before vent'''
  * relocation of existing optics at the end table -''take 1.5day''
 * '''during vent'''
  * PLL measurement (9 Mar - 9? Apr)
  * set up the green stuff onto the end table
  * align the green laser to the cavity
   * how to: visual alignment
  * mode matching of the green laser to the cavity
   * on the table / corridor projection test ==> sliding mount
 * ''' after tank evacuation'''
  * recover IP-ANG and optical levers
Line 56: Line 48:
---------
== CDS team ==
 * 2/22-3/5 Delivery of some computers? / CDS software installations?
 * -3/31 Installation for some of the suspensions?

---------
Line 58: Line 56:
---------  * Conversion of the RF Photodetectors as in the table [[Upgrade 09/RF System|here]]
  * Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
  * Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
  * Adjustment for PDs' boards for the change of capacitance due to the new diodes
  * Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8
Line 60: Line 62:
== PSL table upgrade ==
Line 62: Line 63:
 * Laser delivery (done)
 *
 * Modification of the demod board
  * Installation of the low/high/band pass filters
 * Prepare for building the [[Upgrade_09/RF_System/RF_Modulation_Generator|RF Modulation Generator Box]] and of [[Upgrade_09/RF_System/RF_Distribution_Box|RF Distribution Box]]
  * RG-174 cables for the internal wiring
  * prepare the powering system
  * get RG-174 cables for the internal wiring
  * get 2 aluminum slabs from the machine shop

 * Commissioning of AS55 PD
 * Improvement of the REFL55 PD response
 * Improvement of REFL11 PD by introducing and additional notch at 55MHz
 * Commissioning of POX and POY PDs
 * Design and commissioning of SPOB

 * Design and commissioning of 3f PDs:
  * REFL33
  * REFL165
  * AS165

 * Construction of the frequency generation box

 * Continuing construction of frequency generation box
 * Commissioning of the frequency generation

 * construction and commissioning of the frequency ''distribution'' box for the LSC rack
 * modification of the demod boards

 * commissioning of the frequency distribution system
 * LSC rack cabling and setup
  * Clearing of the old cabling
  * Cabling to the EOM
  * Cabling to the LSC Rack
  * Installation of the new modulation and demodulation chassis

 * EOM installation

40m upgrade installation plan

Past_Plans

Main optics team

  • IOO work

    • [DONE] Moving faraday and input optics

  • MMT placement / initial pointing adjustment

    • [DONE] MC trans beam mode measurement

    • [DONE] Renew the MMT solution

    • [DONE] MMT placement

    • [DONE] Corridor projection ~ measuremnt & adjustment

    • [DONE] Initial Pointing adjustment

  • [DONE] ITMX/Y oplev

  • SRM/PRM/BS placement

    • [DONE] What to do before the SRM/PRM/BS placement?

    • [DONE] TT ==> TT preparations

  • [DONE] AUX optics alignment

  • [DONE] Closing up the vacuum


Suspension preparation

StatusTable.png


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • PLL measurement (9 Mar - 9? Apr)
    • set up the green stuff onto the end table
    • align the green laser to the cavity
      • how to: visual alignment
    • mode matching of the green laser to the cavity
      • on the table / corridor projection test ==> sliding mount

  • after tank evacuation

    • recover IP-ANG and optical levers


CDS team

  • 2/22-3/5 Delivery of some computers? / CDS software installations?
  • -3/31 Installation for some of the suspensions?


RF team

  • Conversion of the RF Photodetectors as in the table here

    • Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
    • Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
    • Adjustment for PDs' boards for the change of capacitance due to the new diodes
    • Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8
  • Modification of the demod board
    • Installation of the low/high/band pass filters
  • Prepare for building the RF Modulation Generator Box and of RF Distribution Box

    • RG-174 cables for the internal wiring
    • prepare the powering system
    • get RG-174 cables for the internal wiring
    • get 2 aluminum slabs from the machine shop
  • Commissioning of AS55 PD
  • Improvement of the REFL55 PD response
  • Improvement of REFL11 PD by introducing and additional notch at 55MHz
  • Commissioning of POX and POY PDs
  • Design and commissioning of SPOB
  • Design and commissioning of 3f PDs:
    • REFL33
    • REFL165
    • AS165
  • Construction of the frequency generation box
  • Continuing construction of frequency generation box
  • Commissioning of the frequency generation
  • construction and commissioning of the frequency distribution box for the LSC rack

  • modification of the demod boards
  • commissioning of the frequency distribution system
  • LSC rack cabling and setup
    • Clearing of the old cabling
    • Cabling to the EOM
    • Cabling to the LSC Rack
    • Installation of the new modulation and demodulation chassis
  • EOM installation

Upgrade_09/Installation_Plan (last edited 2012-01-03 23:02:40 by localhost)