| === Week of 3/22-3/26 === | |
| Line 62: | Line 62: |
| === Week of 3/29-4/5 === | |
| Line 71: | Line 71: |
| === Week of 4/12-4/15 === | |
| Line 78: | Line 77: |
| === Week of 4/19-4/25 === | |
| Line 84: | Line 82: |
| === Week of 4/26-5/2 === | |
| Line 87: | Line 84: |
| === Week of 5/3-5/9 === | |
| Line 91: | Line 87: |
| === Week of 5/10-5/16 === | |
| Line 95: | Line 90: |
| === Week of 5/17-5/23 === | |
| Line 103: | Line 97: |
| === Week of 5/31-6/6 === | |
| Line 105: | Line 98: |
--------- == PSL table upgrade == * Laser delivery (done) * New PSL layout plan * Mode measurements * Mode matching and profiles * Installation procedure * When? * How? |
Contents
40m upgrade installation plan
Main optics team
IOO work
[DONE] Moving faraday and input optics
MMT placement / initial pointing adjustment
[DONE] MC trans beam mode measurement
[DONE] Renew the MMT solution
[DONE] MMT placement
[DONE] Corridor projection ~ measuremnt & adjustment
- Initial Pointing adjustment
- ITMX/Y oplev
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
[DONE] TT ==> TT preparations
- AUX optics alignment
- Closing up the vacuum
Suspension preparation
attachment:StatusTable.png
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- PLL measurement (9 Mar - 9? Apr)
- set up the green stuff onto the end table
- align the green laser to the cavity
- how to: visual alignment
- mode matching of the green laser to the cavity
on the table / corridor projection test ==> sliding mount
after tank evacuation
- recover IP-ANG and optical levers
CDS team
- 2/22-3/5 Delivery of some computers? / CDS software installations?
- -3/31 Installation for some of the suspensions?
RF team
Conversion of the RF Photodetectors as in the table here
- Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
- Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
- Adjustment for PDs' boards for the change of capacitance due to the new diodes
- Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8
- Modification of the demod board
- Installation of the low/high/band pass filters
Prepare for building the RF Modulation Generator Box and of RF Distribution Box
- RG-174 cables for the internal wiring
- prepare the powering system
- get RG-174 cables for the internal wiring
- get 2 aluminum slabs from the machine shop
- Commissioning of AS55 PD
- Improvement of the REFL55 PD response
- Improvement of REFL11 PD by introducing and additional notch at 55MHz
- Commissioning of POX and POY PDs
- Design and commissioning of SPOB
- Design and commissioning of 3f PDs:
- REFL33
- REFL165
- AS165
- Construction of the frequency generation box
- Continuing construction of frequency generation box
- Commissioning of the frequency generation
construction and commissioning of the frequency distribution box for the LSC rack
- modification of the demod boards
- commissioning of the frequency distribution system
- LSC rack cabling and setup
- Clearing of the old cabling
- Cabling to the EOM
- Cabling to the LSC Rack
- Installation of the new modulation and demodulation chassis
- EOM installation