40m upgrade installation plan
Main optics team
IOO work
- Moving faraday and input optics
MMT placement / initial pointing adjustment
- MC trans beam mode measurement
Renew the MMT solution
- MMT placement
Corridor projection ~ measuremnt & adjustment
- Initial Pointing adjustment
- ITMX/Y oplev
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
TT ==> TT preparations
- AUX optics alignment
- Closing up the vacuum
Suspension preparation
- ?? Mar SRM magnet glueing
- ?? Mar PRM magnet glueing
- 27 Mar SRM/PRM side magnet glueing
- 29 Mar gluing finished
- ?? Apr
Remove the SOSs from the chamber
- ?? Apr
Hang and Balance SRM
Hang and Balance PRM
- ?? Apr
Stand off glueing
Fri 19 Mar * Vacuum Bake PRM and SRM over the weekend
TT Suspension
- small parts drawings
ECDs drawings (done - Feb ??)
- wire jig
- purchase magnets (small/large) - in process
- cleaning baking (done - Mar 23)
- 29 Mar TT structure assembly (partial)
- small parts drawings
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- PLL measurement (9 Mar - 9? Apr)
- set up the green stuff onto the end table
- align the green laser to the cavity
- how to: visual alignment
- mode matching of the green laser to the cavity
on the table / corridor projection test ==> sliding mount
after tank evacuation
- recover IP-ANG and optical levers
CDS team
- 2/22-3/5 Delivery of some computers? / CDS software installations?
- -3/31 Installation for some of the suspensions?
RF team
Week of 3/22-3/26
Conversion of the RF Photodetectors as in the table here
- Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
- Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
- Adjustment for PDs' boards for the change of capacitance due to the new diodes
- Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8
Week of 3/29-4/5
- Modification of the demod board
- Installation of the low/high/band pass filters
Prepare for building the RF Modulation Generator Box and of RF Distribution Box
- RG-174 cables for the internal wiring
- prepare the powering system
- get RG-174 cables for the internal wiring
- get 2 aluminum slabs from the machine shop
Week of 4/12-4/15
- Commissioning of AS55 PD
- Improvement of the REFL55 PD response
- Improvement of REFL11 PD by introducing and additional notch at 55MHz
- Commissioning of POX and POY PDs
- Design and commissioning of SPOB
Week of 4/19-4/25
- Design and commissioning of 3f PDs:
- REFL33
- REFL165
- AS165
Week of 4/26-5/2
- Construction of the frequency generation box
Week of 5/3-5/9
- Continuing construction of frequency generation box
- Commissioning of the frequency generation
Week of 5/10-5/16
construction and commissioning of the frequency distribution box for the LSC rack
- modification of the demod boards
Week of 5/17-5/23
- commissioning of the frequency distribution system
- LSC rack cabling and setup
- Clearing of the old cabling
- Cabling to the EOM
- Cabling to the LSC Rack
- Installation of the new modulation and demodulation chassis
Week of 5/31-6/6
- EOM installation
PSL table upgrade
- Laser delivery (done)
- New PSL layout plan
- Mode measurements
- Mode matching and profiles
- Installation procedure
- When?
- How?