Differences between revisions 50 and 58 (spanning 8 versions)
Revision 50 as of 2010-04-13 20:24:59
Size: 7012
Editor: KojiArai
Comment:
Revision 58 as of 2011-01-01 05:02:20
Size: 3278
Editor: KojiArai
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
=== Week of 3/15-3/19 ===
 * '''3/15-18 LVC meeting''' http://www.ligo.org/conferences/lv0310/
 * '''3/19 aLIGO ISC'''
Line 10: Line 7:
=== 4/5 ITMX/ITMY placement ===
=== 4/6 ITMY aligned ===
=== 4/12 ITMX aligned ===
=== Week of 3/1-3/5 ===
 * '''MMT Optics baking '''
Line 17: Line 9:
  * Moving faraday and input optics   * '''[DONE]''' Moving faraday and input optics
Line 20: Line 12:
  * MC trans beam mode measurement
  * Renew the MMT solution''' '''
  * '''[DONE]''' MC trans beam mode measurement
  * '''[DONE]''' Renew the MMT solution
Line 23: Line 15:
  * MMT placement
  * Corridor projection ~ measuremnt & adjustment
  * Initial Pointing adjustment
  * '''[DONE]''' MMT placement
  * '''[DONE]''' Corridor projection ~ measuremnt & adjustment
  * '''[DONE]''' Initial Pointing adjustment
Line 27: Line 19:
 * ITMX/Y oplev  * '''[DONE]''' ITMX/Y oplev
Line 30: Line 22:
  * What to do before the SRM/PRM/BS placement?
  * TT ==> TT preparations
  * '''[DONE]''' What to do before the SRM/PRM/BS placement?
  * '''[DONE]''' TT ==> TT preparations
Line 33: Line 25:
 * AUX optics alignment  * '''[DONE]''' AUX optics alignment
Line 35: Line 27:
 * Closing up the vacuum  * '''[DONE]''' Closing up the vacuum
Line 39: Line 31:
 * '''2/16-26 Small Optics Suspension'''
  * Wed 17 Feb
   * '''Gluing test'''
    * Epoxy test. Try gluing a dumbbell to an optic. Check strength of bond. (It's good)
  * Thurs 18 Feb
   * '''ITMX guiderod gluing'''
    * Place ITMX in guiderod fixture
    * Epoxy guiderod & standoff to ITMX (Afternoon)
    * Cure epoxy (overnight)
  * Fri 19 Feb
   * '''Magnet-dumbbell gluing'''
    * Make up matching sets of magnets using gaussmeter (Morning)
    * Etch magnets and dumbbells using razor blade (Morning)
    * Epoxy magnets to dumbbells (Morning)
    * Cure epoxy (overnight)
   * '''ITMY guiderod gluing'''
    * Place ITMY in guiderod fixtrue
    * Epoxy guiderods to ITMY (Afternoon)
    * Cure epoxy (overnight)
  * Sat 20 Feb
   * No Electricity - No work
  * Sun 21 Feb
  * Mon 22 Feb
   * '''ITMX magnet gluing'''
    * Remove ITMX from guiderod fixture, place in magnet fixture
    * Epoxy magnets ITMX (Afternoon)
    * Cure epoxy (overnight)
   * '''EQ stop preparation'''
    * Talk to Zach - help him get started on this
    * Plan for viton cutting (something to help measure / keep the razor straight while cutting)
    * Cut the Viton
    * Assemble EQ stops (stick the viton in the screws)
  * Tues 23 Feb
   * '''EQ stop preparation'''
    * Zach finish making EQ stops (at least enough for the ITMs...can finish the rest later in the week)
   * '''Hanging preparation'''
    * Balance Optical Table (Morning)
    * Make HeNe OpLev (Morning)
    * Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
   * '''ITMY magnet gluing'''
    * Glue magnets to ITMY (Afternoon)
    * Cure epoxy (overnight)
  * Wed 24 Feb
   * '''ITMX hanging'''
    * Hang and balance ITMX. (All Day)
    * Epoxy wire standoffs in place after balancing
    * Cure epoxy (overnight)
  * Thurs 25 Feb
   * '''ITMY hanging'''
    * Hang and balance ITMY. (All Day)
    * Epoxy wire standoffs in place after balancing
    * Cure epoxy (overnight)
  * Fri 26 Feb
   * '''ITMX/ITMY baking'''
    * Remove both ITMs from their suspensions (Morning) 2 person job
    * Vacuum bake to clean the optics - 48 hours
    * Get RGA scan to confirm they're sparkly clean
  * Sat 27 / Sun 28 Feb
   * '''Vacuum bake Continued'''
    * Leave the 2 ITMs alone in the bake oven
  * Mon 1 Mar
   * '''Final Prep for Installation'''
    * Remove optics from the bake oven 48 hours after they were put in
    * Reinstall optics in suspensions (Definitely a 2 person job)
    * Install the OSEMs in the new suspension towers (OSEMs to be taken from current MOS ITMs)
  * Tues 2 Mar
   * '''Installation Day 1'''
    * Begin installing the ITMs
  * Wed 3 Mar
   * '''Installation Day 2'''
    * Finish installing the ITMs
 * '''Begin the SRM & PRM'''
  * Mon 8 Mar
   * '''Guiderods on SRM'''
   * '''Magnets to dumbbells'''
  * Tues 9 Mar
   * '''Guiderods on PRM'''
   * '''Magnets on SRM'''
  * Wed 10 Mar
   * '''Magnets on PRM'''
  * Thurs 11 Mar
   * '''Hang and Balance SRM'''
  * Fri 12 Mar
   * '''Hang and Balance PRM'''
  * Fri 19 Mar
   * '''Vacuum Bake PRM and SRM over the weekend'''
Line 126: Line 32:
 * '''TT Suspension'''
  * small parts drawings
   * ECDs drawings '''(done)'''
   * wire jig
  * purchase magnets (small/large)
  * cleaning
attachment:StatusTable.png
Line 138: Line 39:
  * PLL measurement (9 Mar - 9? Apr)
Line 153: Line 55:
=== Week of 3/22-3/26 ===
Line 160: Line 62:
=== Week of 3/29-4/5 ===
Line 169: Line 71:
=== Week of 4/12-4/15 ===
Line 176: Line 77:
=== Week of 4/19-4/25 ===
Line 182: Line 82:
=== Week of 4/26-5/2 ===
Line 185: Line 84:
=== Week of 5/3-5/9 ===
Line 189: Line 87:
=== Week of 5/10-5/16 ===
Line 193: Line 90:
=== Week of 5/17-5/23 ===
Line 201: Line 97:
=== Week of 5/31-6/6 ===
Line 203: Line 98:

---------
== PSL table upgrade ==
 * Laser delivery (done)
 * New PSL layout plan
  * Mode measurements
  * Mode matching and profiles
 * Installation procedure
  * When?
  * How?

40m upgrade installation plan

Past Plans

Main optics team

  • IOO work

    • [DONE] Moving faraday and input optics

  • MMT placement / initial pointing adjustment

    • [DONE] MC trans beam mode measurement

    • [DONE] Renew the MMT solution

    • [DONE] MMT placement

    • [DONE] Corridor projection ~ measuremnt & adjustment

    • [DONE] Initial Pointing adjustment

  • [DONE] ITMX/Y oplev

  • SRM/PRM/BS placement

    • [DONE] What to do before the SRM/PRM/BS placement?

    • [DONE] TT ==> TT preparations

  • [DONE] AUX optics alignment

  • [DONE] Closing up the vacuum


Suspension preparation

attachment:StatusTable.png


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • PLL measurement (9 Mar - 9? Apr)
    • set up the green stuff onto the end table
    • align the green laser to the cavity
      • how to: visual alignment
    • mode matching of the green laser to the cavity
      • on the table / corridor projection test ==> sliding mount

  • after tank evacuation

    • recover IP-ANG and optical levers


CDS team

  • 2/22-3/5 Delivery of some computers? / CDS software installations?
  • -3/31 Installation for some of the suspensions?


RF team

  • Conversion of the RF Photodetectors as in the table here

    • Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
    • Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
    • Adjustment for PDs' boards for the change of capacitance due to the new diodes
    • Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8
  • Modification of the demod board
    • Installation of the low/high/band pass filters
  • Prepare for building the RF Modulation Generator Box and of RF Distribution Box

    • RG-174 cables for the internal wiring
    • prepare the powering system
    • get RG-174 cables for the internal wiring
    • get 2 aluminum slabs from the machine shop
  • Commissioning of AS55 PD
  • Improvement of the REFL55 PD response
  • Improvement of REFL11 PD by introducing and additional notch at 55MHz
  • Commissioning of POX and POY PDs
  • Design and commissioning of SPOB
  • Design and commissioning of 3f PDs:
    • REFL33
    • REFL165
    • AS165
  • Construction of the frequency generation box
  • Continuing construction of frequency generation box
  • Commissioning of the frequency generation
  • construction and commissioning of the frequency distribution box for the LSC rack

  • modification of the demod boards
  • commissioning of the frequency distribution system
  • LSC rack cabling and setup
    • Clearing of the old cabling
    • Cabling to the EOM
    • Cabling to the LSC Rack
    • Installation of the new modulation and demodulation chassis
  • EOM installation

Upgrade_09/Installation_Plan (last edited 2012-01-03 23:02:40 by localhost)