| * '''Vent''' * What to do before the vent? * Tuning of the MC servo ~ low power MC test * ITM pointing preparations? (green/red pointers at the both ends) * ITM pointing preparations? (green/red pointers at the both ends) |
|
| Line 11: | Line 8: |
| * '''ITM placement''' * What to do before the ITM placement? * Suspension assembly * Gluing test * Optics cleaning * Gluing (magnets/standoffs/guide rods) * Suspending * procedure |
* '''IOO work''' * '''[DONE]''' Moving faraday and input optics |
| Line 20: | Line 11: |
| * '''MMT placement''' * What to do before the MMT placement? * Optics delivery (Shipping Feb 25) / baking |
* '''MMT placement / initial pointing adjustment''' * '''[DONE]''' MC trans beam mode measurement * '''[DONE]''' Renew the MMT solution |
| Line 24: | Line 15: |
| * '''Initial Pointing adjustment''' | * '''[DONE]''' MMT placement * '''[DONE]''' Corridor projection ~ measuremnt & adjustment * Initial Pointing adjustment * ITMX/Y oplev |
| Line 28: | Line 23: |
| * TT | * '''[DONE]''' TT ==> TT preparations * AUX optics alignment |
| Line 33: | Line 30: |
| == Suspension preparation == | |
| Line 34: | Line 32: |
| == Green team == * '''Green installation''' |
attachment:StatusTable.png |
| Line 39: | Line 35: |
== CDS team == * |
== Green team == * ''' before vent''' * relocation of existing optics at the end table -''take 1.5day'' * '''during vent''' * PLL measurement (9 Mar - 9? Apr) * set up the green stuff onto the end table * align the green laser to the cavity * how to: visual alignment * mode matching of the green laser to the cavity * on the table / corridor projection test ==> sliding mount * ''' after tank evacuation''' * recover IP-ANG and optical levers |
| Line 45: | Line 49: |
== RF team == |
== CDS team == * 2/22-3/5 Delivery of some computers? / CDS software installations? * -3/31 Installation for some of the suspensions? |
| Line 49: | Line 54: |
| == RF team == === Week of 3/22-3/26 === * Conversion of the RF Photodetectors as in the table [[Upgrade 09/RF System|here]] * Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8) * Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8) * Adjustment for PDs' boards for the change of capacitance due to the new diodes * Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8 |
|
| Line 50: | Line 62: |
| === Week of 3/29-4/5 === * Modification of the demod board * Installation of the low/high/band pass filters * Prepare for building the [[Upgrade 09/RF System/RF Modulation Generator|RF Modulation Generator Box]] and of [[Upgrade 09/RF System/RF Distribution Box|RF Distribution Box]] * RG-174 cables for the internal wiring * prepare the powering system * get RG-174 cables for the internal wiring * get 2 aluminum slabs from the machine shop === Week of 4/12-4/15 === * Commissioning of AS55 PD * Improvement of the REFL55 PD response * Improvement of REFL11 PD by introducing and additional notch at 55MHz * Commissioning of POX and POY PDs * Design and commissioning of SPOB === Week of 4/19-4/25 === * Design and commissioning of 3f PDs: * REFL33 * REFL165 * AS165 === Week of 4/26-5/2 === * Construction of the frequency generation box === Week of 5/3-5/9 === * Continuing construction of frequency generation box * Commissioning of the frequency generation === Week of 5/10-5/16 === * construction and commissioning of the frequency ''distribution'' box for the LSC rack * modification of the demod boards === Week of 5/17-5/23 === * commissioning of the frequency distribution system * LSC rack cabling and setup * Clearing of the old cabling * Cabling to the EOM * Cabling to the LSC Rack * Installation of the new modulation and demodulation chassis === Week of 5/31-6/6 === * EOM installation --------- |
|
| Line 51: | Line 108: |
| Line 53: | Line 109: |
| * | * New PSL layout plan * Mode measurements * Mode matching and profiles * Installation procedure * When? * How? |
Contents
40m upgrade installation plan
Main optics team
IOO work
[DONE] Moving faraday and input optics
MMT placement / initial pointing adjustment
[DONE] MC trans beam mode measurement
[DONE] Renew the MMT solution
[DONE] MMT placement
[DONE] Corridor projection ~ measuremnt & adjustment
- Initial Pointing adjustment
- ITMX/Y oplev
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
[DONE] TT ==> TT preparations
- AUX optics alignment
- Closing up the vacuum
Suspension preparation
attachment:StatusTable.png
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- PLL measurement (9 Mar - 9? Apr)
- set up the green stuff onto the end table
- align the green laser to the cavity
- how to: visual alignment
- mode matching of the green laser to the cavity
on the table / corridor projection test ==> sliding mount
after tank evacuation
- recover IP-ANG and optical levers
CDS team
- 2/22-3/5 Delivery of some computers? / CDS software installations?
- -3/31 Installation for some of the suspensions?
RF team
Week of 3/22-3/26
Conversion of the RF Photodetectors as in the table here
- Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
- Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
- Adjustment for PDs' boards for the change of capacitance due to the new diodes
- Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8
Week of 3/29-4/5
- Modification of the demod board
- Installation of the low/high/band pass filters
Prepare for building the RF Modulation Generator Box and of RF Distribution Box
- RG-174 cables for the internal wiring
- prepare the powering system
- get RG-174 cables for the internal wiring
- get 2 aluminum slabs from the machine shop
Week of 4/12-4/15
- Commissioning of AS55 PD
- Improvement of the REFL55 PD response
- Improvement of REFL11 PD by introducing and additional notch at 55MHz
- Commissioning of POX and POY PDs
- Design and commissioning of SPOB
Week of 4/19-4/25
- Design and commissioning of 3f PDs:
- REFL33
- REFL165
- AS165
Week of 4/26-5/2
- Construction of the frequency generation box
Week of 5/3-5/9
- Continuing construction of frequency generation box
- Commissioning of the frequency generation
Week of 5/10-5/16
construction and commissioning of the frequency distribution box for the LSC rack
- modification of the demod boards
Week of 5/17-5/23
- commissioning of the frequency distribution system
- LSC rack cabling and setup
- Clearing of the old cabling
- Cabling to the EOM
- Cabling to the LSC Rack
- Installation of the new modulation and demodulation chassis
Week of 5/31-6/6
- EOM installation
PSL table upgrade
- Laser delivery (done)
- New PSL layout plan
- Mode measurements
- Mode matching and profiles
- Installation procedure
- When?
- How?