|
Size: 993
Comment:
|
Size: 2199
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 1: | Line 1: |
| <<TableOfContents(3)>> | |
| Line 2: | Line 3: |
| == Main optics team == === Week of 2/16-2/19 === * '''2/16-19 Pre-vent works''' * Tuning of the MC servo ~ low power MC test * End X/Y transmon optics relocations ~ making spaces for green * ITM pointing preparations ~ green/red pointers at the both ends |
|
| Line 3: | Line 10: |
| == Main optics team == | * '''2/19 Power shutdown preparation''' |
| Line 5: | Line 12: |
| * '''Vent''' * What to do before the vent? * Tuning of the MC servo ~ low power MC test * ITM pointing preparations? (green/red pointers at the both ends) |
* '''2/20 Power shutdown''' === Week of 2/22-2/26 === * '''2/22 Power shutdown recovery''' * System recovery from power shutdown * Check MC SOS status * Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident) * Pre-vent check list * PZT HV / Oplevs / etc * '''2/23 Vent''' |
| Line 12: | Line 26: |
| * What to do before the ITM placement? * Suspension assembly * Gluing test * Optics cleaning * Gluing (magnets/standoffs/guide rods) * Suspending * procedure |
* '''==>Small Optics Suspension''' * Placement procedure |
| Line 20: | Line 29: |
| === Week of 3/1-3/5 === | |
| Line 23: | Line 33: |
| * corridor projection test | |
| Line 26: | Line 37: |
| === Week of 3/8-3/12 === === Week of 3/15-3/19 === * 3/15-18 LVC meeting http://www.ligo.org/conferences/lv0310/ * 3/19 aLIGO ISC? === Week of 3/22-3/26 === * 40m commisioning party!? === Week of 3/29-4/2 === |
|
| Line 29: | Line 49: |
| * purchase magnets (small/large) | |
| Line 32: | Line 53: |
| === Week of 4/5-4/9 === | |
| Line 33: | Line 55: |
| == Suspension preparation == * '''3/16-26 Small Optics Suspension''' * gluing test * magnet-dumbbell gluing * dumbbell-mirror gluing * mirror hanging |
|
| Line 34: | Line 62: |
| == Green team == * '''Green installation''' |
* '''TT Suspension''' * small parts drawings * ECDs * wire jig * cleaning |
| Line 39: | Line 69: |
== CDS team == * |
== Green team == * ''' before vent''' * relocation of existing optics at the end table -''take 1.5day'' * '''during vent''' * set up the green stuff onto the end table * align the green laser to the cavity (how to ?) * mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount * ''' after closing the tanks''' * recover IP-ANG and optical levers |
| Line 45: | Line 80: |
== RF team == |
== CDS team == * |
| Line 49: | Line 84: |
| == RF team == --------- |
|
| Line 51: | Line 87: |
| Line 53: | Line 88: |
| * |
Contents
40m upgrade installation plan
Main optics team
Week of 2/16-2/19
2/16-19 Pre-vent works
- Tuning of the MC servo ~ low power MC test
- End X/Y transmon optics relocations ~ making spaces for green
- ITM pointing preparations ~ green/red pointers at the both ends
2/19 Power shutdown preparation
2/20 Power shutdown
Week of 2/22-2/26
2/22 Power shutdown recovery
- System recovery from power shutdown
- Check MC SOS status
Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)
- Pre-vent check list
- PZT HV / Oplevs / etc
2/23 Vent
- ITM pointing preparations? (green/red pointers at the both ends)
ITM placement
==>Small Optics Suspension
- Placement procedure
Week of 3/1-3/5
MMT placement
- What to do before the MMT placement?
- Optics delivery (Shipping Feb 25) / baking
- corridor projection test
Initial Pointing adjustment
Week of 3/8-3/12
Week of 3/15-3/19
3/15-18 LVC meeting http://www.ligo.org/conferences/lv0310/
- 3/19 aLIGO ISC?
Week of 3/22-3/26
- 40m commisioning party!?
Week of 3/29-4/2
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
- TT
- purchase magnets (small/large)
- Closing up the vacuum
Week of 4/5-4/9
Suspension preparation
3/16-26 Small Optics Suspension
- gluing test
- magnet-dumbbell gluing
- dumbbell-mirror gluing
- mirror hanging
TT Suspension
- small parts drawings
- ECDs
- wire jig
- cleaning
- small parts drawings
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- set up the green stuff onto the end table
- align the green laser to the cavity (how to ?)
mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount
after closing the tanks
- recover IP-ANG and optical levers
CDS team
RF team
PSL table upgrade
- Laser delivery (done)
