| Line 3: | Line 3: |
[:Past Plans] |
[[Past Plans]] |
| Line 7: | Line 6: |
| === Week of 3/1-3/5 === * moving faraday etc ''' ''' |
|
| Line 10: | Line 7: |
| * '''2/25-26 ITMX/ITMY placement''' * '''__==>Small Optics Suspension__''' |
|
| Line 13: | Line 8: |
| * Placement procedure | * '''IOO work''' * '''[DONE]''' Moving faraday and input optics |
| Line 15: | Line 11: |
| * ITMX/Y oplev | * '''MMT placement / initial pointing adjustment''' * '''[DONE]''' MC trans beam mode measurement * '''[DONE]''' Renew the MMT solution |
| Line 17: | Line 15: |
| * '''3/1-5 ITMX/ITMY placement''' (cont'd) * '''3/1-5 MMT placement / initial pointing adjustment ''' * MC trans beam mode measurement * Renew the MMT solution''' ''' |
* '''[DONE]''' MMT placement * '''[DONE]''' Corridor projection ~ measuremnt & adjustment * '''[DONE]''' Initial Pointing adjustment |
| Line 22: | Line 19: |
| * MMT placement * __Optics delivery (Shipping Feb 25) / baking__ * Corridor projection ~ measuremnt & adjustment * Initial Pointing adjustment |
* '''[DONE]''' ITMX/Y oplev |
| Line 27: | Line 21: |
| * '''3/3 40m meeting ''' | * '''SRM/PRM/BS placement''' * '''[DONE]''' What to do before the SRM/PRM/BS placement? * '''[DONE]''' TT ==> TT preparations |
| Line 29: | Line 25: |
| === Week of 3/8-3/12 === * '''3/8-9 Green steering installation?''' * '''3/10 40m meeting ''' * '''3/11-12 No work''' |
* '''[DONE]''' AUX optics alignment |
| Line 34: | Line 27: |
| === Week of 3/15-3/19 === * '''3/15-18 LVC meeting''' http://www.ligo.org/conferences/lv0310/ * '''3/19 aLIGO ISC?''' |
* '''[DONE]''' Closing up the vacuum |
| Line 38: | Line 29: |
| === Week of 3/22-3/26 === * '''40m commisioning party!?''' * '''ETMY Green installation''' === Week of 3/29-4/2 === * '''SRM/PRM/BS placement''' * What to do before the SRM/PRM/BS placement? * TT * ==> TT preparations * Closing up the vacuum === Week of 4/5-4/9 === |
|
| Line 53: | Line 31: |
| * '''2/16-26 Small Optics Suspension''' * Wed 17 Feb * '''Gluing test''' * Epoxy test. Try gluing a dumbbell to an optic. Check strength of bond. (It's good) * Thurs 18 Feb * '''ITMX guiderod gluing''' * Place ITMX in guiderod fixture * Epoxy guiderod & standoff to ITMX (Afternoon) * Cure epoxy (overnight) * Fri 19 Feb * '''Magnet-dumbbell gluing''' * Make up matching sets of magnets using gaussmeter (Morning) * Etch magnets and dumbbells using razor blade (Morning) * Epoxy magnets to dumbbells (Morning) * Cure epoxy (overnight) * '''ITMY guiderod gluing''' * Place ITMY in guiderod fixtrue * Epoxy guiderods to ITMY (Afternoon) * Cure epoxy (overnight) * Sat 20 Feb * No Electricity - No work * Sun 21 Feb * Mon 22 Feb * '''ITMX magnet gluing''' * Remove ITMX from guiderod fixture, place in magnet fixture * Epoxy magnets ITMX (Afternoon) * Cure epoxy (overnight) * '''EQ stop preparation''' * Talk to Zach - help him get started on this * Plan for viton cutting (something to help measure / keep the razor straight while cutting) * Cut the Viton * Assemble EQ stops (stick the viton in the screws) * Tues 23 Feb * '''EQ stop preparation''' * Zach finish making EQ stops (at least enough for the ITMs...can finish the rest later in the week) * '''Hanging preparation''' * Balance Optical Table (Morning) * Make HeNe OpLev (Morning) * Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics * '''ITMY magnet gluing''' * Glue magnets to ITMY (Afternoon) * Cure epoxy (overnight) * Wed 24 Feb * '''ITMX hanging''' * Hang and balance ITMX. (All Day) * Epoxy wire standoffs in place after balancing * Cure epoxy (overnight) * Thurs 25 Feb * '''ITMY hanging''' * Hang and balance ITMY. (All Day) * Epoxy wire standoffs in place after balancing * Cure epoxy (overnight) * Fri 26 Feb * '''ITMX/ITMY baking''' * Remove both ITMs from their suspensions (Morning) 2 person job * Vacuum bake to clean the optics - 48 hours * Get RGA scan to confirm they're sparkly clean * Sat 27 / Sun 28 Feb * '''Vacuum bake Continued''' * Leave the 2 ITMs alone in the bake oven * Mon 1 Mar * '''Final Prep for Installation''' * Remove optics from the bake oven 48 hours after they were put in * Reinstall optics in suspensions (Definitely a 2 person job) * Install the OSEMs in the new suspension towers (OSEMs to be taken from current MOS ITMs) * Tues 2 Mar * '''Installation Day 1''' * Begin installing the ITMs * Wed 3 Mar * '''Installation Day 2''' * Finish installing the ITMs * '''Begin the SRM & PRM''' * Mon 8 Mar * '''Guiderods on SRM''' * '''Magnets to dumbbells''' * Tues 9 Mar * '''Guiderods on PRM''' * '''Magnets on SRM''' * Wed 10 Mar * '''Magnets on PRM''' * Thurs 11 Mar * '''Hang and Balance SRM''' * Fri 12 Mar * '''Hang and Balance PRM''' * Fri 19 Mar * '''Vacuum Bake PRM and SRM over the weekend''' |
|
| Line 140: | Line 32: |
* '''TT Suspension''' * small parts drawings * ECDs drawings '''(done)''' * wire jig * purchase magnets (small/large) * cleaning |
attachment:StatusTable.png |
| Line 153: | Line 39: |
| * PLL measurement (9 Mar - 9? Apr) | |
| Line 164: | Line 51: |
| * -3/31 Installation for some of the suspensions? | * -3/31 Installation for some of the suspensions? |
| Line 169: | Line 56: |
| === Week of 2/22-2/26 === * Conversion of the RF Photodetectors as in the table [[Upgrade_09/RF_System|here]] |
* Conversion of the RF Photodetectors as in the table [[Upgrade 09/RF System|here]] |
| Line 172: | Line 58: |
| * Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8) | * Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8) |
| Line 174: | Line 60: |
| * Tune the resonant frequencies of the the old "AM Monitor PD", PD6, PD9, PD3, PD4, PD7-8 | * Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8 |
| Line 176: | Line 62: |
| === Week of 2/28-3/5 === | |
| Line 179: | Line 65: |
| * Prepare for building the [[Upgrade_09/RF_System/RF_Modulation_Generator|RF Modulation Generator Box]] and of [[Upgrade_09/RF_System/RF_Distribution_Box|RF Distribution Box]] | * Prepare for building the [[Upgrade 09/RF System/RF Modulation Generator|RF Modulation Generator Box]] and of [[Upgrade 09/RF System/RF Distribution Box|RF Distribution Box]] |
| Line 185: | Line 71: |
| === Week of 3/7-3/12 === * Arrival of the Wenzel Crystal Oscillators * Arrival of the Metalcraft chassis * Assembling of the [[Upgrade_09/RF_System/RF_Modulation_Generator|RF Modulation Generator Box]] and of the [[Upgrade_09/RF_System/RF_Distribution_Box|RF Distribution Box]] === Week of 3/14-3/19 === * Rack cabling and setup |
* Commissioning of AS55 PD * Improvement of the REFL55 PD response * Improvement of REFL11 PD by introducing and additional notch at 55MHz * Commissioning of POX and POY PDs * Design and commissioning of SPOB * Design and commissioning of 3f PDs: * REFL33 * REFL165 * AS165 * Construction of the frequency generation box * Continuing construction of frequency generation box * Commissioning of the frequency generation * construction and commissioning of the frequency ''distribution'' box for the LSC rack * modification of the demod boards * commissioning of the frequency distribution system * LSC rack cabling and setup |
| Line 197: | Line 97: |
| === Week of 3/21-3/26 === * Installation of the new EOM * Set up of the system of EOM resonant amplifier and modulation combiner * ... --------- == PSL table upgrade == * Laser delivery (done) * New PSL layout plan * Mode measurements * Mode matching and profiles * Installation procedure * When? * How? |
* EOM installation |
Contents
40m upgrade installation plan
Main optics team
IOO work
[DONE] Moving faraday and input optics
MMT placement / initial pointing adjustment
[DONE] MC trans beam mode measurement
[DONE] Renew the MMT solution
[DONE] MMT placement
[DONE] Corridor projection ~ measuremnt & adjustment
[DONE] Initial Pointing adjustment
[DONE] ITMX/Y oplev
SRM/PRM/BS placement
[DONE] What to do before the SRM/PRM/BS placement?
[DONE] TT ==> TT preparations
[DONE] AUX optics alignment
[DONE] Closing up the vacuum
Suspension preparation
attachment:StatusTable.png
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- PLL measurement (9 Mar - 9? Apr)
- set up the green stuff onto the end table
- align the green laser to the cavity
- how to: visual alignment
- mode matching of the green laser to the cavity
on the table / corridor projection test ==> sliding mount
after tank evacuation
- recover IP-ANG and optical levers
CDS team
- 2/22-3/5 Delivery of some computers? / CDS software installations?
- -3/31 Installation for some of the suspensions?
RF team
Conversion of the RF Photodetectors as in the table here
- Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
- Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
- Adjustment for PDs' boards for the change of capacitance due to the new diodes
- Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8
- Modification of the demod board
- Installation of the low/high/band pass filters
Prepare for building the RF Modulation Generator Box and of RF Distribution Box
- RG-174 cables for the internal wiring
- prepare the powering system
- get RG-174 cables for the internal wiring
- get 2 aluminum slabs from the machine shop
- Commissioning of AS55 PD
- Improvement of the REFL55 PD response
- Improvement of REFL11 PD by introducing and additional notch at 55MHz
- Commissioning of POX and POY PDs
- Design and commissioning of SPOB
- Design and commissioning of 3f PDs:
- REFL33
- REFL165
- AS165
- Construction of the frequency generation box
- Continuing construction of frequency generation box
- Commissioning of the frequency generation
construction and commissioning of the frequency distribution box for the LSC rack
- modification of the demod boards
- commissioning of the frequency distribution system
- LSC rack cabling and setup
- Clearing of the old cabling
- Cabling to the EOM
- Cabling to the LSC Rack
- Installation of the new modulation and demodulation chassis
- EOM installation