| == Main optics team == * '''Pre-vent works''' * Tuning of the MC servo ~ low power MC test * End transmon X/Y Optics relocations (before the vent) for green * ITM pointing preparations? (green/red pointers at the both ends) |
|
| Line 3: | Line 8: |
| == Main optics team == | * '''Vent''' * What to do before the vent? * Tuning of the MC servo ~ low power MC test * ITM pointing preparations? (green/red pointers at the both ends) |
| Line 5: | Line 13: |
| * Vent * What to do before the vent? * low power MC test * ITM pointing preparations? (green pointers at the both ends) * ITM placement |
* '''ITM placement''' |
| Line 13: | Line 16: |
| * Gluing test * Optics cleaning * Gluing (magnets/standoffs/guide rods) * Suspending * procedure |
* Gluing test * Optics cleaning * Gluing (magnets/standoffs/guide rods) * Suspending * procedure |
| Line 19: | Line 22: |
| * MMT placement | * '''MMT placement''' |
| Line 23: | Line 26: |
| * Initial Pointing adjustment | * '''Initial Pointing adjustment''' |
| Line 25: | Line 28: |
| * SRM/PRM/BS placement | * '''SRM/PRM/BS placement''' * What to do before the SRM/PRM/BS placement? * TT * purchase magnets (small/large) |
| Line 30: | Line 36: |
| Line 32: | Line 37: |
* Green installation |
* ''' before vent''' * relocation of existing optics at the end table -''take 1.5day'' * '''during vent''' * set up the green stuff onto the end table * align the green laser to the cavity (how to ?) * mode matching of the green laser to the cavity * ''' after closing the tanks''' * recover IP-ANG and optical levers |
| Line 36: | Line 47: |
| Line 38: | Line 48: |
| Line 42: | Line 51: |
| == RF team == --------- |
|
| Line 44: | Line 54: |
40m upgrade installation plan
Main optics team
Pre-vent works
- Tuning of the MC servo ~ low power MC test
- End transmon X/Y Optics relocations (before the vent) for green
- ITM pointing preparations? (green/red pointers at the both ends)
Vent
- What to do before the vent?
- Tuning of the MC servo ~ low power MC test
- ITM pointing preparations? (green/red pointers at the both ends)
ITM placement
- What to do before the ITM placement?
- Suspension assembly
- Gluing test
- Optics cleaning
- Gluing (magnets/standoffs/guide rods)
- Suspending
- procedure
MMT placement
- What to do before the MMT placement?
- Optics delivery (Shipping Feb 25) / baking
Initial Pointing adjustment
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
- TT
- purchase magnets (small/large)
- Closing up the vacuum
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- set up the green stuff onto the end table
- align the green laser to the cavity (how to ?)
- mode matching of the green laser to the cavity
after closing the tanks
- recover IP-ANG and optical levers
CDS team
RF team
PSL table upgrade
- Laser delivery (done)