Size: 771
Comment:
|
Size: 1452
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 5: | Line 5: |
| * Vent | * '''Pre-vent works''' * Tuning of the MC servo ~ low power MC test * End transmon X/Y Optics relocations (before the vent) for green * ITM pointing preparations? (green/red pointers at the both ends) * '''Vent''' |
| Line 7: | Line 12: |
| * low power MC test * ITM pointing preparations? (green pointers at the both ends) |
* Tuning of the MC servo ~ low power MC test * ITM pointing preparations? (green/red pointers at the both ends) |
| Line 10: | Line 15: |
| * ITM placement | * '''ITM placement''' |
| Line 19: | Line 24: |
| * MMT placement | * '''MMT placement''' |
| Line 23: | Line 28: |
| * Initial Pointing adjustment | * '''Initial Pointing adjustment''' |
| Line 25: | Line 30: |
| * SRM/PRM/BS placement | * '''SRM/PRM/BS placement''' * What to do before the SRM/PRM/BS placement? * TT |
| Line 33: | Line 40: |
| * Green installation |
* ''' before vent''' * relocation of existing optics at the end table -''take 1.5day'' * '''during vent''' * set up the green stuff onto the end table * align the green laser to the cavity (how to ?) * mode matching of the green laser to the cavity * ''' after closing the tanks''' * recover IP-ANG and optical levers |
| Line 43: | Line 56: |
| == RF team == --------- |
40m upgrade installation plan
Main optics team
Pre-vent works
- Tuning of the MC servo ~ low power MC test
- End transmon X/Y Optics relocations (before the vent) for green
- ITM pointing preparations? (green/red pointers at the both ends)
Vent
- What to do before the vent?
- Tuning of the MC servo ~ low power MC test
- ITM pointing preparations? (green/red pointers at the both ends)
ITM placement
- What to do before the ITM placement?
- Suspension assembly
- Gluing test
- Optics cleaning
- Gluing (magnets/standoffs/guide rods)
- Suspending
- procedure
MMT placement
- What to do before the MMT placement?
- Optics delivery (Shipping Feb 25) / baking
Initial Pointing adjustment
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
- TT
- Closing up the vacuum
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- set up the green stuff onto the end table
- align the green laser to the cavity (how to ?)
- mode matching of the green laser to the cavity
after closing the tanks
- recover IP-ANG and optical levers
CDS team
RF team
PSL table upgrade
- Laser delivery (done)