Size: 771
Comment:
|
Size: 1966
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 2: | Line 2: |
| == Main optics team == * '''3/16-19 Pre-vent works''' * Tuning of the MC servo ~ low power MC test * End X/Y transmon optics relocations ~ making spaces for green * ITM pointing preparations ~ green/red pointers at the both ends |
|
| Line 3: | Line 8: |
| == Main optics team == | * '''3/19 Power shutdown preparation''' |
| Line 5: | Line 10: |
| * Vent * What to do before the vent? * low power MC test * ITM pointing preparations? (green pointers at the both ends) |
* '''3/20 Power shutdown''' |
| Line 10: | Line 12: |
| * ITM placement * What to do before the ITM placement? * Suspension assembly * Gluing test * Optics cleaning * Gluing (magnets/standoffs/guide rods) * Suspending * procedure |
* '''3/22 Power shutdown recovery''' * System recovery from power shutdown * Check MC SOS status * Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident) * Pre-vent check list * PZT HV / Oplevs / etc |
| Line 19: | Line 19: |
| * MMT placement | * '''3/23 Vent''' * ITM pointing preparations? (green/red pointers at the both ends) * '''ITM placement''' * '''==>Small Optics Suspension''' * Placement procedure * '''MMT placement''' |
| Line 22: | Line 29: |
| * corridor projection test | |
| Line 23: | Line 31: |
| * Initial Pointing adjustment | * '''Initial Pointing adjustment''' |
| Line 25: | Line 33: |
| * SRM/PRM/BS placement | * '''SRM/PRM/BS placement''' * What to do before the SRM/PRM/BS placement? * TT * purchase magnets (small/large) |
| Line 30: | Line 41: |
| == Suspension preparation == * '''Small Optics Suspension''' * gluing test * magnet-dumbbell gluing * dumbbell-mirror gluing * mirror hanging |
|
| Line 31: | Line 48: |
| == Green team == * Green installation |
* '''TT Suspension''' * small parts drawings * ECDs * wire jig * cleaning * ECDs * wire jig |
| Line 36: | Line 57: |
| == Green team == * ''' before vent''' * relocation of existing optics at the end table -''take 1.5day'' * '''during vent''' * set up the green stuff onto the end table * align the green laser to the cavity (how to ?) * mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount * ''' after closing the tanks''' * recover IP-ANG and optical levers |
|
| Line 37: | Line 67: |
| --------- | |
| Line 38: | Line 69: |
| Line 42: | Line 72: |
| == RF team == --------- |
|
| Line 44: | Line 75: |
40m upgrade installation plan
Main optics team
3/16-19 Pre-vent works
- Tuning of the MC servo ~ low power MC test
- End X/Y transmon optics relocations ~ making spaces for green
- ITM pointing preparations ~ green/red pointers at the both ends
3/19 Power shutdown preparation
3/20 Power shutdown
3/22 Power shutdown recovery
- System recovery from power shutdown
- Check MC SOS status
Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)
- Pre-vent check list
- PZT HV / Oplevs / etc
3/23 Vent
- ITM pointing preparations? (green/red pointers at the both ends)
ITM placement
==>Small Optics Suspension
- Placement procedure
MMT placement
- What to do before the MMT placement?
- Optics delivery (Shipping Feb 25) / baking
- corridor projection test
Initial Pointing adjustment
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
- TT
- purchase magnets (small/large)
- Closing up the vacuum
Suspension preparation
Small Optics Suspension
- gluing test
- magnet-dumbbell gluing
- dumbbell-mirror gluing
- mirror hanging
TT Suspension
- small parts drawings
- ECDs
- wire jig
- cleaning
- ECDs
- wire jig
- small parts drawings
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- set up the green stuff onto the end table
- align the green laser to the cavity (how to ?)
mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount
after closing the tanks
- recover IP-ANG and optical levers
CDS team
RF team
PSL table upgrade
- Laser delivery (done)