40m upgrade installation plan

[Past Plans]

Main optics team

Week of 2/16-2/19

  • 2/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/17 40m meeting

  • 2/18 Power shutdown preparation

  • 2/19 No work / only papers and pens

  • 2/20 Power shutdown

Week of 2/22-2/26

  • 2/22 Power shutdown recovery

    • System recovery
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 Reserved for trouble shooting

  • 2/23 or 24 Vent

  • 2/24 40m meeting

  • 2/24-25 Input MC beam adjustment

    • beam centering to MC1/2/3 mirrors
    • moving faraday etc

  • 2/25-26 ITMX/ITMY placement

    • ==>Small Optics Suspension

    • Placement procedure
    • ITMX/Y oplev

Week of 3/1-3/5

  • 3/1-5 ITMX/ITMY placement (cont'd)

  • 3/1-5 MMT placement / initial pointing adjustment

    • MC trans beam mode measurement
    • Renew the MMT solution

    • MMT placement
      • Optics delivery (Shipping Feb 25) / baking

    • Corridor projection ~ measuremnt & adjustment

    • Initial Pointing adjustment
  • 3/3 40m meeting

Week of 3/8-3/12

  • 3/8-9 Green steering installation?

  • 3/10 40m meeting

  • 3/11-12 No work

Week of 3/15-3/19

Week of 3/22-3/26

  • 40m commisioning party!?

  • ETMY Green installation

Week of 3/29-4/2

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • ==> TT preparations

  • Closing up the vacuum

Week of 4/5-4/9


Suspension preparation

  • 2/16-26 Small Optics Suspension

    • Wed 17 Feb
      • Gluing test

        • Epoxy test. Try gluing a dumbbell to an optic. Check strength of bond. (It's good)
    • Thurs 18 Feb
      • ITMX guiderod gluing

        • Place ITMX in guiderod fixture
        • Epoxy guiderod & standoff to ITMX (Afternoon)

        • Cure epoxy (overnight)
    • Fri 19 Feb
      • Magnet-dumbbell gluing

        • Make up matching sets of magnets using gaussmeter (Morning)
        • Etch magnets and dumbbells using razor blade (Morning)
        • Epoxy magnets to dumbbells (Morning)
        • Cure epoxy (overnight)
      • ITMY guiderod gluing

        • Place ITMY in guiderod fixtrue
        • Epoxy guiderods to ITMY (Afternoon)
        • Cure epoxy (overnight)
    • Sat 20 Feb
      • No Electricity - No work
    • Sun 21 Feb
    • Mon 22 Feb
      • ITMX magnet gluing

        • Remove ITMX from guiderod fixture, place in magnet fixture
        • Epoxy magnets ITMX (Afternoon)
        • Cure epoxy (overnight)
      • EQ stop preparation

        • Talk to Zach - help him get started on this
        • Plan for viton cutting (something to help measure / keep the razor straight while cutting)
        • Cut the Viton
        • Assemble EQ stops (stick the viton in the screws)
    • Tues 23 Feb
      • EQ stop preparation

        • Zach finish making EQ stops (at least enough for the ITMs...can finish the rest later in the week)
      • Hanging preparation

        • Balance Optical Table (Morning)
        • Make HeNe OpLev (Morning)

        • Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
      • ITMY magnet gluing

        • Glue magnets to ITMY (Afternoon)
        • Cure epoxy (overnight)
    • Wed 24 Feb
      • ITMX hanging

        • Hang and balance ITMX. (All Day)
        • Epoxy wire standoffs in place after balancing
        • Cure epoxy (overnight)
    • Thurs 25 Feb
      • ITMY hanging

        • Hang and balance ITMY. (All Day)
        • Epoxy wire standoffs in place after balancing
        • Cure epoxy (overnight)
    • Fri 26 Feb
      • ITMX/ITMY baking

        • Remove both ITMs from their suspensions (Morning) 2 person job
        • Vacuum bake to clean the optics - 48 hours
        • Get RGA scan to confirm they're sparkly clean
    • Sat 27 / Sun 28 Feb
      • Vacuum bake Continued

        • Leave the 2 ITMs alone in the bake oven
    • Mon 1 Mar
      • Final Prep for Installation

        • Remove optics from the bake oven 48 hours after they were put in
        • Reinstall optics in suspensions (Definitely a 2 person job)
        • Install the OSEMs in the new suspension towers (OSEMs to be taken from current MOS ITMs)
    • Tues 2 Mar
      • Installation Day 1

        • Begin installing the ITMs
    • Wed 3 Mar
      • Installation Day 2

        • Finish installing the ITMs
  • Begin the SRM & PRM

    • Mon 8 Mar
      • Guiderods on SRM

      • Magnets to dumbbells

    • Tues 9 Mar
      • Guiderods on PRM

      • Magnets on SRM

    • Wed 10 Mar
      • Magnets on PRM

    • Thurs 11 Mar
      • Hang and Balance SRM

    • Fri 12 Mar
      • Hang and Balance PRM

    • Fri 19 Mar
      • Vacuum Bake PRM and SRM over the weekend

  • TT Suspension

    • small parts drawings
      • ECDs drawings (done)

      • wire jig
    • purchase magnets (small/large)
    • cleaning


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity
      • how to: visual alignment
    • mode matching of the green laser to the cavity
      • on the table / corridor projection test ==> sliding mount

  • after tank evacuation

    • recover IP-ANG and optical levers


CDS team

  • 2/22-3/5 Delivery of some computers? / CDS software installations?
  • -3/31 Installation for some of the suspensions?


RF team

Week of 2/22-2/26

  • Conversion of the RF Photodetectors as in the table here

    • Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
    • Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
    • Adjustment for PDs' boards for the change of capacitance due to the new diodes
    • Tune the resonant frequencies of the the old "AM Monitor PD", PD6, PD9, PD3, PD4, PD7-8

Week of 2/28-3/5

  • Modification of the demod board
    • Installation of the low/high/band pass filters
  • Prepare for building the RF Modulation Generator Box and of RF Distribution Box

    • RG-174 cables for the internal wiring
    • prepare the powering system
    • get RG-174 cables for the internal wiring
    • get 2 aluminum slabs from the machine shop

Week of 3/7-3/12

Week of 3/14-3/19

  • Rack cabling and setup
    • Clearing of the old cabling
    • Cabling to the EOM
    • Cabling to the LSC Rack
    • Installation of the new modulation and demodulation chassis

Week of 3/21-3/26

  • Installation of the new EOM
    • Set up of the system of EOM resonant amplifier and modulation combiner
    • ...


PSL table upgrade

  • Laser delivery (done)
  • New PSL layout plan
    • Mode measurements
    • Mode matching and profiles
  • Installation procedure
    • When?
    • How?