Line 3: Line 3:
[[Past Plans]]
Line 4: Line 6:
=== Week of 2/16-2/19 ===
 * '''2/16-19 Pre-vent works'''
  * Tuning of the MC servo ~ low power MC test
  * End X/Y transmon optics relocations ~ making spaces for green
  * ITM pointing preparations ~ green/red pointers at the both ends
Line 10: Line 7:
 * '''2/17 40m meeting'''
Line 12: Line 8:
 * '''2/18 Power shutdown preparation'''  * '''IOO work'''
  * '''[DONE]''' Moving faraday and input optics
Line 14: Line 11:
 * '''2/19 No work / only papers and pens'''  * '''MMT placement / initial pointing adjustment'''
  * '''[DONE]''' MC trans beam mode measurement
  * '''[DONE]''' Renew the MMT solution
Line 16: Line 15:
 * '''2/20 Power shutdown'''

=== Week of 2/22-2/26 ===
 * '''2/22 Power shutdown recovery'''
  * System recovery

  * Check MC SOS status
   * Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)
  * Pre-vent check list
   * PZT HV / Oplevs / etc

 * '''2/23 Reserved for trouble shooting'''

 * '''2/23 or 24 Vent'''

 * '''2/24 40m meeting '''

 * '''2/24-25 Input MC beam adjustment'''
  * beam centering to MC1/2/3 mirrors

  * moving faraday etc ''' '''

 * '''2/25-26 ITMX/ITMY placement'''
  * '''__==>Small Optics Suspension__'''

  * Placement procedure

  * ITMX/Y oplev

=== Week of 3/1-3/5 ===
 * '''3/1-5 ITMX/ITMY placement''' (cont'd)
 * '''3/1-5 MMT placement / initial pointing adjustment '''
  * MC trans beam mode measurement
  * Renew the MMT solution''' '''

  * MMT placement
   * __Optics delivery (Shipping Feb 25) / baking__
  * Corridor projection ~ measuremnt & adjustment
  * '''[DONE]''' MMT placement
  * '''[DONE]''' Corridor projection ~ measuremnt & adjustment
Line 56: Line 19:
 * '''3/3 40m meeting '''  * ITMX/Y oplev
Line 58: Line 21:
=== Week of 3/8-3/12 ===
 * '''3/8-9 Green steering installation?'''
 * '''3/10 40m meeting '''
 * '''3/11-12 No work'''

=== Week of 3/15-3/19 ===
 * '''3/15-18 LVC meeting''' http://www.ligo.org/conferences/lv0310/
 * '''3/19 aLIGO ISC?'''

=== Week of 3/22-3/26 ===
 * '''40m commisioning party!?'''
 * '''ETMY Green installation'''

=== Week of 3/29-4/2 ===
Line 74: Line 23:
  * TT
   *
==> TT preparations
  * '''[DONE]''' TT ==> TT preparations

 * AUX optics alignment
Line 79: Line 29:
=== Week of 4/5-4/9 ===
Line 82: Line 31:
 * '''2/16-26 Small Optics Suspension'''
  * Wed 17 Feb
   * '''Gluing test'''
    * Betsy's going to overnight the magnet-to-dumbbell gluing fixture
    * Epoxy test. Try gluing a dumbbell to an optic?
  * Thurs 18 Feb
   * '''Magnet-dumbbell gluing'''
    * Make up matching sets of magnets using gaussmeter (Morning)
    * Etch magnets and dumbbells using razor blade (Morning)
    * Epoxy magnets to dumbbells (Morning)
    * Cure epoxy (overnight)
   * '''ITMX guiderod gluing'''
    * Place ITMX in guiderod fixture
    * Epoxy guiderods to ITMX (Afternoon)
    * Cure epoxy (overnight)
  * Fri 19 Feb
   * '''ITMX magnet gluing'''
    * Remove ITMX from guiderod fixture, place in magnet fixture
    * Epoxy magnets ITMX (Morning)
    * Cure epoxy (overnight)
   * '''ITMY guiderod gluing'''
    * Place ITMY in guiderod fixtrue
    * Epoxy guiderods to ITMY (Afternoon)
    * Cure epoxy (overnight)
  * Sat 20 Feb
   * No Electricity - No work
  * Sun 21 Feb
   * '''EQ stop preparation'''
    * Plan for viton cutting (something to help measure / keep the razor straight while cutting)
    * Cut the Viton
    * Assemble EQ stops (stick the viton in the screws)
  * Mon 22 Feb
   * '''ITMY magnet gluing'''
    * Glue magnets to ITMY (Morning)
    * Cure epoxy (overnight)
   * '''Hanging preparation'''
    * Balance Optical Table (Afternoon)
    * Make HeNe OpLev (Afternoon)
    * Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
  * Tues 23 Feb
   * '''ITMX/ITMY hanging'''
    * Hang and balance both ITMs. (All Day)
    * Epoxy wire standoffs in place after balancing
    * Cure epoxy (overnight)
  * Wed 24 Feb
   * '''ITMX/ITMY baking?'''
   * Remove both ITMs from their suspensions (Morning)
   * Airbake to clean the optics (How long will this take? There are contradictions in the Assembly Spec Docs)
   * Reinstall optics in suspensions (Late afternoon?)
   * Install OSEMs(?)
  * Thurs 25 Feb
   * '''Installation1'''
    * Start installing the ITMs
  * Fri 26 Feb
   * '''Installation2'''
    * Finish installing the ITMs
Line 139: Line 32:
 * '''TT Suspension'''
  * small parts drawings
   * ECDs drawings '''(done)'''
   * wire jig
  * purchase magnets (small/large)
  * cleaning
attachment:StatusTable.png
Line 151: Line 39:
  * PLL measurement (9 Mar - 9? Apr)
Line 162: Line 51:
 * -3/31 Installation for some of the suspensions?   * -3/31 Installation for some of the suspensions?
Line 166: Line 55:
A draft. Dates will come. === Week of 3/22-3/26 ===
 * Conversion of the RF Photodetectors as in the table [[Upgrade 09/RF System|here]]
  * Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
  * Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
  * Adjustment for PDs' boards for the change of capacitance due to the new diodes
  * Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8
Line 168: Line 62:
 * Building of the [[Upgrade_09/RF_System/RF_Modulation_Generator|RF Modulation Generator Box]]
  * Order 2U chassis from Metalcraft
  * Get an aluminum slab from the machine shop
  * Design and order front and back panels
  * Design the powering
  * Design and order RG-174 cables for the internal wiring
  * ...
 * Modification of the RF Photodetectors
  * Replace the photodiodes and adjust for the changed impedances
=== Week of 3/29-4/5 ===
Line 179: Line 65:
 * Cabling to the EOM
 * Cabling to the LSC Rack
 * Building of the [[Upgrade_09/RF_System/RF_Distribution_Box|RF Distribution Box]] for the LSC rack
  * Order 1U chassis from Metalcraft
  * Get an aluminum slab from the machine shop
  * Design and order front and back panels
  * Design the powering
  * Design and order RG-174 cables for the internal wiring
  * ...
 * Prepare for building the [[Upgrade 09/RF System/RF Modulation Generator|RF Modulation Generator Box]] and of [[Upgrade 09/RF System/RF Distribution Box|RF Distribution Box]]
  * RG-174 cables for the internal wiring
  * prepare the powering system
  * get RG-174 cables for the internal wiring
  * get 2 aluminum slabs from the machine shop

=== Week of 4/12-4/15 ===
 * Commissioning of AS55 PD
 * Improvement of the REFL55 PD response
 * Improvement of REFL11 PD by introducing and additional notch at 55MHz
 * Commissioning of POX and POY PDs
 * Design and commissioning of SPOB

=== Week of 4/19-4/25 ===
 * Design and commissioning of 3f PDs:
  * REFL33
  * REFL165
  * AS165

=== Week of 4/26-5/2 ===
 * Construction of the frequency generation box

=== Week of 5/3-5/9 ===
 * Continuing construction of frequency generation box
 * Commissioning of the frequency generation

=== Week of 5/10-5/16 ===
 * construction and commissioning of the frequency ''distribution'' box for the LSC rack
 * modification of the demod boards

=== Week of 5/17-5/23 ===
 * commissioning of the frequency distribution system
 * LSC rack cabling and setup
  * Clearing of the old cabling
  * Cabling to the EOM
  * Cabling to the LSC Rack
  * Installation of the new modulation and demodulation chassis

=== Week of 5/31-6/6 ===
 * EOM installation

40m upgrade installation plan

Past Plans

Main optics team

  • IOO work

    • [DONE] Moving faraday and input optics

  • MMT placement / initial pointing adjustment

    • [DONE] MC trans beam mode measurement

    • [DONE] Renew the MMT solution

    • [DONE] MMT placement

    • [DONE] Corridor projection ~ measuremnt & adjustment

    • Initial Pointing adjustment
  • ITMX/Y oplev
  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • [DONE] TT ==> TT preparations

  • AUX optics alignment
  • Closing up the vacuum


Suspension preparation

attachment:StatusTable.png


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • PLL measurement (9 Mar - 9? Apr)
    • set up the green stuff onto the end table
    • align the green laser to the cavity
      • how to: visual alignment
    • mode matching of the green laser to the cavity
      • on the table / corridor projection test ==> sliding mount

  • after tank evacuation

    • recover IP-ANG and optical levers


CDS team

  • 2/22-3/5 Delivery of some computers? / CDS software installations?
  • -3/31 Installation for some of the suspensions?


RF team

Week of 3/22-3/26

  • Conversion of the RF Photodetectors as in the table here

    • Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
    • Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
    • Adjustment for PDs' boards for the change of capacitance due to the new diodes
    • Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8

Week of 3/29-4/5

  • Modification of the demod board
    • Installation of the low/high/band pass filters
  • Prepare for building the RF Modulation Generator Box and of RF Distribution Box

    • RG-174 cables for the internal wiring
    • prepare the powering system
    • get RG-174 cables for the internal wiring
    • get 2 aluminum slabs from the machine shop

Week of 4/12-4/15

  • Commissioning of AS55 PD
  • Improvement of the REFL55 PD response
  • Improvement of REFL11 PD by introducing and additional notch at 55MHz
  • Commissioning of POX and POY PDs
  • Design and commissioning of SPOB

Week of 4/19-4/25

  • Design and commissioning of 3f PDs:
    • REFL33
    • REFL165
    • AS165

Week of 4/26-5/2

  • Construction of the frequency generation box

Week of 5/3-5/9

  • Continuing construction of frequency generation box
  • Commissioning of the frequency generation

Week of 5/10-5/16

  • construction and commissioning of the frequency distribution box for the LSC rack

  • modification of the demod boards

Week of 5/17-5/23

  • commissioning of the frequency distribution system
  • LSC rack cabling and setup
    • Clearing of the old cabling
    • Cabling to the EOM
    • Cabling to the LSC Rack
    • Installation of the new modulation and demodulation chassis

Week of 5/31-6/6

  • EOM installation


PSL table upgrade

  • Laser delivery (done)
  • New PSL layout plan
    • Mode measurements
    • Mode matching and profiles
  • Installation procedure
    • When?
    • How?