 * Vent
  * What to do before the vent?
  * low power MC test
  * ITM pointing preparations? (green pointers at the both ends)
Line 10: Line 8:
 * ITM placement
  * What to do before the ITM placement?
  * Suspension assembly
    * Gluing test
    * Optics cleaning
    * Gluing (magnets/standoffs/guide rods)
    * Suspending
  * procedure
 * '''IOO work'''
  * Moving faraday and input optics
Line 19: Line 11:
 * MMT placement
  * What to do before the MMT placement?
  * Optics delivery (Shipping Feb 25) / baking
 * '''MMT placement / initial pointing adjustment'''
  * MC trans beam mode measurement
  * Renew the MMT solution''' '''
Line 23: Line 15:
 * Initial Pointing adjustment   * MMT placement
  * Corridor projection ~ measuremnt & adjustment
  * Initial Pointing adjustment
Line 25: Line 19:
 * SRM/PRM/BS placement  * ITMX/Y oplev

 * '''SRM/PRM/BS placement'''
  * What to do before the SRM/PRM/BS placement?
  * TT ==> TT preparations

 * AUX optics alignment
Line 30: Line 30:
== Suspension preparation ==
Line 31: Line 32:
== Green team == attachment:StatusTable.png
Line 33: Line 34:
* Green installation  * ?? Mar SRM magnet glueing
 * ?? Mar PRM magnet glueing
 * 27 Mar SRM/PRM side magnet glueing
 * 29 Mar gluing finished

 * ?? Apr
  * '''Remove the SOSs from the chamber'''
 * ?? Apr
  * '''Hang and Balance SRM'''
  * '''Hang and Balance PRM'''
 * ?? Apr
  * '''Stand off glueing'''
 * Fri 19 Mar * '''Vacuum Bake PRM and SRM over the weekend'''

 * '''TT Suspension'''
  * small parts drawings
   * ECDs drawings '''(done - Feb ??)'''
   * wire jig
  * purchase magnets (small/large) - in process
  * cleaning baking (done - Mar 23)
  * 29 Mar TT structure assembly (partial)
Line 36: Line 57:

== CDS team ==

*
== Green team ==
 * ''' before vent'''
  * relocation of existing optics at the end table -''take 1.5day''
 * '''during vent'''
  * PLL measurement (9 Mar - 9? Apr)
  * set up the green stuff onto the end table
  * align the green laser to the cavity
   * how to: visual alignment
  * mode matching of the green laser to the cavity
   * on the table / corridor projection test ==> sliding mount
 * ''' after tank evacuation'''
  * recover IP-ANG and optical levers
Line 42: Line 71:
== CDS team ==
 * 2/22-3/5 Delivery of some computers? / CDS software installations?
 * -3/31 Installation for some of the suspensions?
Line 43: Line 75:
---------
== RF team ==
=== Week of 3/22-3/26 ===
 * Conversion of the RF Photodetectors as in the table [[Upgrade 09/RF System|here]]
  * Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
  * Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
  * Adjustment for PDs' boards for the change of capacitance due to the new diodes
  * Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8

=== Week of 3/29-4/5 ===
 * Modification of the demod board
  * Installation of the low/high/band pass filters
 * Prepare for building the [[Upgrade 09/RF System/RF Modulation Generator|RF Modulation Generator Box]] and of [[Upgrade 09/RF System/RF Distribution Box|RF Distribution Box]]
  * RG-174 cables for the internal wiring
  * prepare the powering system
  * get RG-174 cables for the internal wiring
  * get 2 aluminum slabs from the machine shop

=== Week of 4/12-4/15 ===
 * Commissioning of AS55 PD
 * Improvement of the REFL55 PD response
 * Improvement of REFL11 PD by introducing and additional notch at 55MHz
 * Commissioning of POX and POY PDs
 * Design and commissioning of SPOB

=== Week of 4/19-4/25 ===
 * Design and commissioning of 3f PDs:
  * REFL33
  * REFL165
  * AS165

=== Week of 4/26-5/2 ===
 * Construction of the frequency generation box

=== Week of 5/3-5/9 ===
 * Continuing construction of frequency generation box
 * Commissioning of the frequency generation

=== Week of 5/10-5/16 ===
 * construction and commissioning of the frequency ''distribution'' box for the LSC rack
 * modification of the demod boards

=== Week of 5/17-5/23 ===
 * commissioning of the frequency distribution system
 * LSC rack cabling and setup
  * Clearing of the old cabling
  * Cabling to the EOM
  * Cabling to the LSC Rack
  * Installation of the new modulation and demodulation chassis

=== Week of 5/31-6/6 ===
 * EOM installation

---------
Line 44: Line 130:

*
 * Laser delivery (done)
 * New PSL layout plan
  * Mode measurements
  * Mode matching and profiles
 * Installation procedure
  * When?
  * How?

40m upgrade installation plan

Past Plans

Main optics team

  • IOO work

    • Moving faraday and input optics
  • MMT placement / initial pointing adjustment

    • MC trans beam mode measurement
    • Renew the MMT solution

    • MMT placement
    • Corridor projection ~ measuremnt & adjustment

    • Initial Pointing adjustment
  • ITMX/Y oplev
  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT ==> TT preparations

  • AUX optics alignment
  • Closing up the vacuum


Suspension preparation

attachment:StatusTable.png

  • ?? Mar SRM magnet glueing
  • ?? Mar PRM magnet glueing
  • 27 Mar SRM/PRM side magnet glueing
  • 29 Mar gluing finished
  • ?? Apr
    • Remove the SOSs from the chamber

  • ?? Apr
    • Hang and Balance SRM

    • Hang and Balance PRM

  • ?? Apr
    • Stand off glueing

  • Fri 19 Mar * Vacuum Bake PRM and SRM over the weekend

  • TT Suspension

    • small parts drawings
      • ECDs drawings (done - Feb ??)

      • wire jig
    • purchase magnets (small/large) - in process
    • cleaning baking (done - Mar 23)
    • 29 Mar TT structure assembly (partial)


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • PLL measurement (9 Mar - 9? Apr)
    • set up the green stuff onto the end table
    • align the green laser to the cavity
      • how to: visual alignment
    • mode matching of the green laser to the cavity
      • on the table / corridor projection test ==> sliding mount

  • after tank evacuation

    • recover IP-ANG and optical levers


CDS team

  • 2/22-3/5 Delivery of some computers? / CDS software installations?
  • -3/31 Installation for some of the suspensions?


RF team

Week of 3/22-3/26

  • Conversion of the RF Photodetectors as in the table here

    • Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
    • Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
    • Adjustment for PDs' boards for the change of capacitance due to the new diodes
    • Tune the resonant frequencies of the the old SPOB66, PD6, PD9, PD3, PD4, PD7-8

Week of 3/29-4/5

  • Modification of the demod board
    • Installation of the low/high/band pass filters
  • Prepare for building the RF Modulation Generator Box and of RF Distribution Box

    • RG-174 cables for the internal wiring
    • prepare the powering system
    • get RG-174 cables for the internal wiring
    • get 2 aluminum slabs from the machine shop

Week of 4/12-4/15

  • Commissioning of AS55 PD
  • Improvement of the REFL55 PD response
  • Improvement of REFL11 PD by introducing and additional notch at 55MHz
  • Commissioning of POX and POY PDs
  • Design and commissioning of SPOB

Week of 4/19-4/25

  • Design and commissioning of 3f PDs:
    • REFL33
    • REFL165
    • AS165

Week of 4/26-5/2

  • Construction of the frequency generation box

Week of 5/3-5/9

  • Continuing construction of frequency generation box
  • Commissioning of the frequency generation

Week of 5/10-5/16

  • construction and commissioning of the frequency distribution box for the LSC rack

  • modification of the demod boards

Week of 5/17-5/23

  • commissioning of the frequency distribution system
  • LSC rack cabling and setup
    • Clearing of the old cabling
    • Cabling to the EOM
    • Cabling to the LSC Rack
    • Installation of the new modulation and demodulation chassis

Week of 5/31-6/6

  • EOM installation


PSL table upgrade

  • Laser delivery (done)
  • New PSL layout plan
    • Mode measurements
    • Mode matching and profiles
  • Installation procedure
    • When?
    • How?