== Main optics team ==
=== Week of 2/16-2/19 ===
 * '''2/16-19 Pre-vent works'''
  * Tuning of the MC servo ~ low power MC test
  * End X/Y transmon optics relocations ~ making spaces for green
  * ITM pointing preparations ~ green/red pointers at the both ends
Line 3: Line 10:
== Main optics team ==  * '''2/17 40m meeting'''
Line 5: Line 12:
 * Vent
  * What to do before the vent?
  * low power MC test
  * ITM pointing preparations? (green pointers at the both ends)
 * '''2/19 Power shutdown preparation'''
Line 10: Line 14:
 * ITM placement
  * What to do before the ITM placement?
  * Suspension assembly
    * Gluing test
    * Optics cleaning
    * Gluing (magnets/standoffs/guide rods)
    * Suspending
  * procedure
 * '''2/20 Power shutdown'''
Line 19: Line 16:
 * MMT placement
  * What to do before the MMT placement?
  * Optics delivery (Shipping Feb 25) / baking
=== Week of 2/22-2/26 ===
 * '''2/22 Power shutdown recovery'''
  * System recovery
Line 23: Line 20:
 * Initial Pointing adjustment   * Check MC SOS status
   * Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)
  * Pre-vent check list
   * PZT HV / Oplevs / etc
Line 25: Line 25:
 * SRM/PRM/BS placement  * '''2/23 Vent'''

 * '''2/24 40m meeting '''

 * '''2/24-25 Input MC beam adjustment'''
  * beam centering to MC1/2/3 mirrors

  * moving faraday etc ''' '''

 * '''2/25-26 ITMX/ITMY placement'''
  * '''__==>Small Optics Suspension__'''

  * Placement procedure

  * ITMX/Y oplev

=== Week of 3/1-3/5 ===
 * '''3/1-5 MMT placement / initial pointing adjustment '''
  * MC trans beam mode measurement
  * Renew the MMT solution''' '''

  * MMT placement
   * __Optics delivery (Shipping Feb 25) / baking__
  * Corridor projection ~ measuremnt & adjustment
  * Initial Pointing adjustment

 * '''3/7 40m meeting '''

=== Week of 3/8-3/12 ===
 * '''3/8-9 Green steering installation?'''
 * '''3/10 40m meeting '''
 * '''3/11-12 No work'''

=== Week of 3/15-3/19 ===
 * '''3/15-18 LVC meeting''' http://www.ligo.org/conferences/lv0310/
 * '''3/19 aLIGO ISC?'''

=== Week of 3/22-3/26 ===
 * '''40m commisioning party!?'''
 * '''ETMY Green installation'''

=== Week of 3/29-4/2 ===
 * '''SRM/PRM/BS placement'''
  * What to do before the SRM/PRM/BS placement?
  * TT
   * ==> TT preparations
Line 29: Line 74:
=== Week of 4/5-4/9 ===
Line 30: Line 76:
== Suspension preparation ==
 * '''3/16-26 Small Optics Suspension'''
  * gluing test
  * magnet-dumbbell gluing
  * dumbbell-mirror gluing
  * mirror hanging
Line 31: Line 83:
== Green team ==

* Green installation
 * '''TT Suspension'''
  * small parts drawings
   * ECDs
   * wire jig
  * purchase magnets (small/large)
  * cleaning
Line 36: Line 91:

== CDS team ==

*
== Green team ==
 * ''' before vent'''
  * relocation of existing optics at the end table -''take 1.5day''
 * '''during vent'''
  * set up the green stuff onto the end table
  * align the green laser to the cavity
   * how to: visual alignment
  * mode matching of the green laser to the cavity
   * on the table / corridor projection test ==> sliding mount
 * ''' after tank evacuation'''
  * recover IP-ANG and optical levers
Line 42: Line 104:
== CDS team ==
 *
Line 43: Line 107:
---------
== RF team ==
 *

---------
Line 44: Line 113:

*
 * Laser delivery (done)

40m upgrade installation plan

Main optics team

Week of 2/16-2/19

  • 2/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/17 40m meeting

  • 2/19 Power shutdown preparation

  • 2/20 Power shutdown

Week of 2/22-2/26

  • 2/22 Power shutdown recovery

    • System recovery
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 Vent

  • 2/24 40m meeting

  • 2/24-25 Input MC beam adjustment

    • beam centering to MC1/2/3 mirrors
    • moving faraday etc

  • 2/25-26 ITMX/ITMY placement

    • ==>Small Optics Suspension

    • Placement procedure
    • ITMX/Y oplev

Week of 3/1-3/5

  • 3/1-5 MMT placement / initial pointing adjustment

    • MC trans beam mode measurement
    • Renew the MMT solution

    • MMT placement
      • Optics delivery (Shipping Feb 25) / baking

    • Corridor projection ~ measuremnt & adjustment

    • Initial Pointing adjustment
  • 3/7 40m meeting

Week of 3/8-3/12

  • 3/8-9 Green steering installation?

  • 3/10 40m meeting

  • 3/11-12 No work

Week of 3/15-3/19

Week of 3/22-3/26

  • 40m commisioning party!?

  • ETMY Green installation

Week of 3/29-4/2

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • ==> TT preparations

  • Closing up the vacuum

Week of 4/5-4/9


Suspension preparation

  • 3/16-26 Small Optics Suspension

    • gluing test
    • magnet-dumbbell gluing
    • dumbbell-mirror gluing
    • mirror hanging
  • TT Suspension

    • small parts drawings
      • ECDs
      • wire jig
    • purchase magnets (small/large)
    • cleaning


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity
      • how to: visual alignment
    • mode matching of the green laser to the cavity
      • on the table / corridor projection test ==> sliding mount

  • after tank evacuation

    • recover IP-ANG and optical levers


CDS team


RF team


PSL table upgrade

  • Laser delivery (done)