Differences between revisions 29 and 34 (spanning 5 versions)
Revision 29 as of 2010-02-17 19:29:16
Size: 5639
Editor: KojiArai
Comment:
Revision 34 as of 2010-02-22 19:37:15
Size: 6787
Comment:
Deletions are marked like this. Additions are marked like this.
Line 84: Line 84:
   * Plan for magnet-to-dumbbell gluing fixture (keep them axially aligned)
   * Make some kind of magnet-to-dumbbell gluing fixture - machine shop? Depends on the plan.
* Epoxy test. Try gluing a dumbbell to an optic?
   * '''Gluing test'''
    * Betsy's g
oing to overnight the magnet-to-dumbbell gluing fixture
    * Epoxy test. Try gluing a dumbbell to an optic?
Line 88: Line 88:
   * Make up matching sets of magnets using gaussmeter (Morning)
   * Etch magnets and dumbbells using razor blade (Morning)
   * Epoxy magnets to dumbells (Morning)
* Cure epoxy (overnight)
   * Place ITMX in guiderod fixture
   * Epoxy guiderods to
ITMX (Afternoon)
   * Cure epoxy (overnight)
   * '''Magnet-dumbbell gluing'''
 
* Make up matching sets of magnets using gaussmeter (Morning)
    * Etch magnets and dumbbells using razor blade (Morning)
    * Epoxy magnets to dumbbells (Morning)
 
* Cure epoxy (overnight)
   * '''ITMX guiderod gluing'''
    * Place
ITMX in guiderod fixture
    * Epoxy guiderods to ITMX
(Afternoon)
    * Cure epoxy (overnight)
Line 96: Line 98:
   * Remove ITMX from guiderod fixture, place in magnet fixture
   * Epoxy magnets ITMX (Morning)
   * Cure epoxy (overnight)
   * Place ITMY in guiderod fixtrue
   * Epoxy guiderods to ITMY (Afternoon)
   * Cure epoxy (overnight)
   * '''ITMX magnet gluing'''
 
* Remove ITMX from guiderod fixture, place in magnet fixture
    * Epoxy magnets ITMX (Morning)
    * Cure epoxy (overnight)
   * '''ITMY guiderod gluing'''
    *
Place ITMY in guiderod fixtrue
    * Epoxy guiderods to ITMY (Afternoon)
    * Cure epoxy (overnight)
Line 105: Line 109:
   * Plan for viton cutting (something to help measure / keep the razor straight while cutting)
   * Cut the Viton
   * Assemble EQ stops (stick the viton in the screws)
   * '''EQ stop preparation'''
 
* Plan for viton cutting (something to help measure / keep the razor straight while cutting)
    * Cut the Viton
  * Assemble EQ stops (stick the viton in the screws)
Line 109: Line 114:
   * Glue magnets to ITMY (Morning)
   * Cure epoxy (overnight)
   * Balance Optical Table (Afternoon)
   * Make HeNe OpLev (Afternoon)
   * Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
   * '''ITMY magnet gluing'''
    * Glue magnets to ITMY
(Morning)
  * Cure epoxy (overnight)
   * '''Hanging preparation'''
 
* Balance Optical Table (Afternoon)
    * Make HeNe OpLev (Afternoon)
    * Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
Line 115: Line 122:
   * Hang and balance both ITMs. (All Day)
   * Epoxy wire standoffs in place after balancing
   * Cure epoxy (overnight)
   * '''ITMX/ITMY hanging'''
 
* Hang and balance both ITMs. (All Day)
  * Epoxy wire standoffs in place after balancing
    * Cure epoxy (overnight)
Line 119: Line 127:
   * Remove both ITMs from their suspensions (Morning)
   * Airbake to clean the optics (How long will this take? There are contradictions in the Assembly Spec Docs)
   * Reinstall optics in suspensions (Late afternoon?)
   * Install OSEMs
   * '''ITMX/ITMY baking?'''
    * Remove both ITMs from their suspensions (Morning) 2 person job
    * Airbake to clean the optics - 48 hours
Line 124: Line 131:
   * Start installing the ITMs    * '''Airbake Continued'''
    * Leave the 2 ITMs alone in the airbake oven
Line 126: Line 134:
   * Finish installing the ITMs    * '''Final Prep for Installation'''
    * Remove optics from the airbake oven 48 hours after they were put in
    * Reinstall optics in suspensions (Definitely a 2 person job)
    * Install the OSEMs in the new suspension towers (OSEMs to be taken from current MOS ITMs)
  * Mon 1 Mar
   * '''Installation Day 1'''
    * Begin installing the ITMs
  * Tues 2 Mar
   * '''Installation Day 2'''
    * Finish installing the ITMs
Line 155: Line 172:
A draft. Dates will come.

 * Building of the [[Upgrade_09/RF_System/RF_Modulation_Generator|RF Modulation Generator Box]]
  * Order 2U chassis from Metalcraft
  * Get an aluminum slab from the machine shop
  * Design and order front and back panels
  * Design the powering
  * Design and order RG-174 cables for the internal wiring
  * ...
 * Modification of the RF Photodetectors
  * Replace the photodiodes and adjust for the changed impedances

=== Week of 2/22-2/26 ===
 * Conversion of the RF Photodetectors as in the table [[Upgrade_09/RF_System|here]]
  * Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
  * Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
  * Adjustment for PDs' boards for the change of capacitance due to the new diodes
  * Tune the resonant frequencies of the the old "AM Monitor PD", PD6, PD9, PD3, PD4, PD7-8

=== Week of 2/28-3/5 ===
Line 168: Line 183:
 * Cabling to the EOM
 * Cabling to the LSC Rack
 * Building of the [[Upgrade_09/RF_System/RF_Distribution_Box|RF Distribution Box]] for the LSC rack
  * Order 1U chassis from Metalcraft
  * Get an aluminum slab from the machine shop
  * Design and order front and back panels
  * Design the powering
  * Design and order RG-174 cables for the internal wiring
  * ...
 * Prepare for building the [[Upgrade_09/RF_System/RF_Modulation_Generator|RF Modulation Generator Box]] and of [[Upgrade_09/RF_System/RF_Distribution_Box|RF Distribution Box]]
  * RG-174 cables for the internal wiring
  * prepare the powering system
  * get RG-174 cables for the internal wiring
  * get 2 aluminum slabs from the machine shop

=== Week of 3/7-3/12 ===
 * Arrival of the Wenzel Crystal Oscillator
 * Arrival of the Metalcraft chassis
 * Assempling of the [[Upgrade_09/RF_System/RF_Modulation_Generator|RF Modulation Generator Box]] and of the [[Upgrade_09/RF_System/RF_Distribution_Box|RF Distribution Box]]
  
=== Week of 3/14-3/19
 * Rack cabling and system setup
  * Cabling to the EOM
  * Cabling to the LSC Rack

40m upgrade installation plan

Main optics team

Week of 2/16-2/19

  • 2/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/17 40m meeting

  • 2/18 Power shutdown preparation

  • 2/19 No work / only papers and pens

  • 2/20 Power shutdown

Week of 2/22-2/26

  • 2/22 Power shutdown recovery

    • System recovery
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 Reserved for trouble shooting

  • 2/23 or 24 Vent

  • 2/24 40m meeting

  • 2/24-25 Input MC beam adjustment

    • beam centering to MC1/2/3 mirrors
    • moving faraday etc

  • 2/25-26 ITMX/ITMY placement

    • ==>Small Optics Suspension

    • Placement procedure
    • ITMX/Y oplev

Week of 3/1-3/5

  • 3/1-5 ITMX/ITMY placement (cont'd)

  • 3/1-5 MMT placement / initial pointing adjustment

    • MC trans beam mode measurement
    • Renew the MMT solution

    • MMT placement
      • Optics delivery (Shipping Feb 25) / baking

    • Corridor projection ~ measuremnt & adjustment

    • Initial Pointing adjustment
  • 3/3 40m meeting

Week of 3/8-3/12

  • 3/8-9 Green steering installation?

  • 3/10 40m meeting

  • 3/11-12 No work

Week of 3/15-3/19

Week of 3/22-3/26

  • 40m commisioning party!?

  • ETMY Green installation

Week of 3/29-4/2

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • ==> TT preparations

  • Closing up the vacuum

Week of 4/5-4/9


Suspension preparation

  • 2/16-26 Small Optics Suspension

    • Wed 17 Feb
      • Gluing test

        • Betsy's going to overnight the magnet-to-dumbbell gluing fixture
        • Epoxy test. Try gluing a dumbbell to an optic?
    • Thurs 18 Feb
      • Magnet-dumbbell gluing

        • Make up matching sets of magnets using gaussmeter (Morning)
        • Etch magnets and dumbbells using razor blade (Morning)
        • Epoxy magnets to dumbbells (Morning)
        • Cure epoxy (overnight)
      • ITMX guiderod gluing

        • Place ITMX in guiderod fixture
        • Epoxy guiderods to ITMX (Afternoon)
        • Cure epoxy (overnight)
    • Fri 19 Feb
      • ITMX magnet gluing

        • Remove ITMX from guiderod fixture, place in magnet fixture
        • Epoxy magnets ITMX (Morning)
        • Cure epoxy (overnight)
      • ITMY guiderod gluing

        • Place ITMY in guiderod fixtrue
        • Epoxy guiderods to ITMY (Afternoon)
        • Cure epoxy (overnight)
    • Sat 20 Feb
      • No Electricity - No work
    • Sun 21 Feb
      • EQ stop preparation

        • Plan for viton cutting (something to help measure / keep the razor straight while cutting)
        • Cut the Viton
        • Assemble EQ stops (stick the viton in the screws)
    • Mon 22 Feb
      • ITMY magnet gluing

        • Glue magnets to ITMY (Morning)
        • Cure epoxy (overnight)
      • Hanging preparation

        • Balance Optical Table (Afternoon)
        • Make HeNe OpLev (Afternoon)

        • Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
    • Tues 23 Feb
      • ITMX/ITMY hanging

        • Hang and balance both ITMs. (All Day)
        • Epoxy wire standoffs in place after balancing
        • Cure epoxy (overnight)
    • Wed 24 Feb
      • ITMX/ITMY baking?

        • Remove both ITMs from their suspensions (Morning) 2 person job
        • Airbake to clean the optics - 48 hours
    • Thurs 25 Feb
      • Airbake Continued

        • Leave the 2 ITMs alone in the airbake oven
    • Fri 26 Feb
      • Final Prep for Installation

        • Remove optics from the airbake oven 48 hours after they were put in
        • Reinstall optics in suspensions (Definitely a 2 person job)
        • Install the OSEMs in the new suspension towers (OSEMs to be taken from current MOS ITMs)
    • Mon 1 Mar
      • Installation Day 1

        • Begin installing the ITMs
    • Tues 2 Mar
      • Installation Day 2

        • Finish installing the ITMs
  • TT Suspension

    • small parts drawings
      • ECDs drawings (done)

      • wire jig
    • purchase magnets (small/large)
    • cleaning


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity
      • how to: visual alignment
    • mode matching of the green laser to the cavity
      • on the table / corridor projection test ==> sliding mount

  • after tank evacuation

    • recover IP-ANG and optical levers


CDS team

  • 2/22-3/5 Delivery of some computers? / CDS software installations?
  • -3/31 Installation for some of the suspensions?


RF team

Week of 2/22-2/26

  • Conversion of the RF Photodetectors as in the table here

    • Removal of the photodetectors from the optics tables: REFL33 (PD2), REFL199 (PD6), REFL166 (PD11), AS166 (PD1), AS133 (PD9), POX33 (PD3), POY33 (PD4), PO133 (PD7-8), PO199 (PD7-8)
    • Replacement of the diodes: 2mm PDs for REFL11 (AM Monitor PD), REFL33 (PD2), REFL55 (PD6), AS55 (PD9) , POX11 (PD3) , POY11 (PD4); 1mm for REFL166(PD11), AS166(PD1), POP22-POP110(PD7-8)
    • Adjustment for PDs' boards for the change of capacitance due to the new diodes
    • Tune the resonant frequencies of the the old "AM Monitor PD", PD6, PD9, PD3, PD4, PD7-8

Week of 2/28-3/5

  • Modification of the demod board
    • Installation of the low/high/band pass filters
  • Prepare for building the RF Modulation Generator Box and of RF Distribution Box

    • RG-174 cables for the internal wiring
    • prepare the powering system
    • get RG-174 cables for the internal wiring
    • get 2 aluminum slabs from the machine shop

Week of 3/7-3/12

=== Week of 3/14-3/19

  • Rack cabling and system setup
    • Cabling to the EOM
    • Cabling to the LSC Rack


PSL table upgrade

  • Laser delivery (done)
  • New PSL layout plan
    • Mode measurements
    • Mode matching and profiles
  • Installation procedure
    • When?
    • How?

Upgrade_09/Installation_Plan (last edited 2012-01-03 23:02:40 by localhost)