Line 154: Line 154:
 * Assembling of the RF frequency Generator  * Building of the [[Upgrade_09/RF_System/RF_Modulation_Generator|RF Modulation Generator Box]]
Line 158: Line 158:
  * Design the powering
Line 161: Line 162:
  * replace the photodiodes and adjust for the changed impedances   * Replace the photodiodes and adjust for the changed impedances
Line 163: Line 164:
  * installation of the low/band/high pass filters
 *
  * Installation of the low/high/band pass filters
 * Cabling to the EOM
 * Cabling to the LSC Rack
 * Building of the [[Upgrade_09/RF_System/RF_Distribution_Box|RF Distribution Box]] for the LSC rack
  * Order 1U chassis from Metalcraft
  * Get an aluminum slab from the machine shop
  * Design and order front and back panels
  * Design the powering
  * Design and order RG-174 cables for the internal wiring
  * ...

40m upgrade installation plan

Main optics team

Week of 2/16-2/19

  • 2/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/17 40m meeting

  • 2/18 Power shutdown preparation

  • 2/19 No work / only papers and pens

  • 2/20 Power shutdown

Week of 2/22-2/26

  • 2/22 Power shutdown recovery

    • System recovery
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 or 24 Vent

  • 2/24 40m meeting

  • 2/24-25 Input MC beam adjustment

    • beam centering to MC1/2/3 mirrors
    • moving faraday etc

  • 2/25-26 ITMX/ITMY placement

    • ==>Small Optics Suspension

    • Placement procedure
    • ITMX/Y oplev

Week of 3/1-3/5

  • 3/1-5 MMT placement / initial pointing adjustment

    • MC trans beam mode measurement
    • Renew the MMT solution

    • MMT placement
      • Optics delivery (Shipping Feb 25) / baking

    • Corridor projection ~ measuremnt & adjustment

    • Initial Pointing adjustment
  • 3/4 40m meeting

Week of 3/8-3/12

  • 3/8-9 Green steering installation?

  • 3/10 40m meeting

  • 3/11-12 No work

Week of 3/15-3/19

Week of 3/22-3/26

  • 40m commisioning party!?

  • ETMY Green installation

Week of 3/29-4/2

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • ==> TT preparations

  • Closing up the vacuum

Week of 4/5-4/9


Suspension preparation

  • 2/16-26 Small Optics Suspension

    • Wed 17 Feb
      • Plan for magnet-to-dumbbell gluing fixture (keep them axially aligned)
      • Make some kind of magnet-to-dumbbell gluing fixture - machine shop? Depends on the plan.
      • Epoxy test. Try gluing a dumbbell to an optic?
    • Thurs 18 Feb
      • Make up matching sets of magnets using gaussmeter (Morning)
      • Etch magnets and dumbbells using razor blade (Morning)
      • Epoxy magnets to dumbells (Morning)
      • Cure epoxy (overnight)
      • Place ITMX in guiderod fixture
      • Epoxy guiderods to ITMX (Afternoon)
      • Cure epoxy (overnight)
    • Fri 19 Feb
      • Remove ITMX from guiderod fixture, place in magnet fixture
      • Epoxy magnets ITMX (Morning)
      • Cure epoxy (overnight)
      • Place ITMY in guiderod fixtrue
      • Epoxy guiderods to ITMY (Afternoon)
      • Cure epoxy (overnight)
    • Sat 20 Feb
      • No Electricity - No work
    • Sun 21 Feb
      • Plan for viton cutting (something to help measure / keep the razor straight while cutting)
      • Cut the Viton
      • Assemble EQ stops (stick the viton in the screws)
    • Mon 22 Feb
      • Glue magnets to ITMY (Morning)
      • Cure epoxy (overnight)
      • Balance Optical Table (Afternoon)
      • Make HeNe OpLev (Afternoon)

      • Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
    • Tues 23 Feb
      • Hang and balance both ITMs. (All Day)
      • Epoxy wire standoffs in place after balancing
      • Cure epoxy (overnight)
    • Wed 24 Feb
      • Remove both ITMs from their suspensions (Morning)
      • Airbake to clean the optics (How long will this take? There are contradictions in the Assembly Spec Docs)
      • Reinstall optics in suspensions (Late afternoon?)
      • Install OSEMs
    • Thurs 25 Feb
      • Start installing the ITMs
    • Fri 26 Feb
      • Finish installing the ITMs
  • TT Suspension

    • small parts drawings
      • ECDs
      • wire jig
    • purchase magnets (small/large)
    • cleaning


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity
      • how to: visual alignment
    • mode matching of the green laser to the cavity
      • on the table / corridor projection test ==> sliding mount

  • after tank evacuation

    • recover IP-ANG and optical levers


CDS team

  • 2/22-3/5 Delivery of some computers? / CDS software installations?
  • -3/31 Installation for some of the suspensions?


RF team

A draft. Dates will come.

  • Building of the RF Modulation Generator Box

    • Order 2U chassis from Metalcraft
    • Get an aluminum slab from the machine shop
    • Design and order front and back panels
    • Design the powering
    • Design and order RG-174 cables for the internal wiring
    • ...
  • Modification of the RF Photodetectors
    • Replace the photodiodes and adjust for the changed impedances
  • Modification of the demod board
    • Installation of the low/high/band pass filters
  • Cabling to the EOM
  • Cabling to the LSC Rack
  • Building of the RF Distribution Box for the LSC rack

    • Order 1U chassis from Metalcraft
    • Get an aluminum slab from the machine shop
    • Design and order front and back panels
    • Design the powering
    • Design and order RG-174 cables for the internal wiring
    • ...


PSL table upgrade

  • Laser delivery (done)