Differences between revisions 2 and 6 (spanning 4 versions)
Revision 2 as of 2010-02-12 00:55:35
Size: 642
Editor: KojiArai
Comment:
Revision 6 as of 2010-02-13 01:10:35
Size: 1137
Editor: KojiArai
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Vent  * '''Pre-vent works'''
  * Tuning of the MC servo ~ low power MC test
  * End transmon X/Y Optics relocations (before the vent) for green
  * ITM pointing preparations? (green/red pointers at the both ends)

 * '''Vent'''
Line 7: Line 12:
  * low power MC test   * Tuning of the MC servo ~ low power MC test
  * ITM pointing preparations? (green/red pointers at the both ends)
Line 9: Line 15:
 * ITM placement  * '''ITM placement'''
Line 18: Line 24:
 * MMT placement  * '''MMT placement'''
Line 22: Line 28:
 * SRM/PRM/BS placement  * '''Initial Pointing adjustment'''

 * '''SRM/PRM/BS placement'''
  * What to do before the SRM/PRM/BS placement?
  * TT
Line 30: Line 40:
* Green installation  * '''Green installation'''
Line 36: Line 46:
*  *

---------

== RF team ==
Line 42: Line 56:
*  * Laser delivery (done)
 *

40m upgrade installation plan

Main optics team

  • Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End transmon X/Y Optics relocations (before the vent) for green
    • ITM pointing preparations? (green/red pointers at the both ends)
  • Vent

    • What to do before the vent?
    • Tuning of the MC servo ~ low power MC test
    • ITM pointing preparations? (green/red pointers at the both ends)
  • ITM placement

    • What to do before the ITM placement?
    • Suspension assembly
      • Gluing test
      • Optics cleaning
      • Gluing (magnets/standoffs/guide rods)
      • Suspending
    • procedure
  • MMT placement

    • What to do before the MMT placement?
    • Optics delivery (Shipping Feb 25) / baking
  • Initial Pointing adjustment

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
  • Closing up the vacuum


Green team

  • Green installation


CDS team


RF team


PSL table upgrade

  • Laser delivery (done)

Upgrade_09/Installation_Plan (last edited 2012-01-03 23:02:40 by localhost)