Differences between revisions 2 and 14 (spanning 12 versions)
Revision 2 as of 2010-02-12 00:55:35
Size: 642
Editor: KojiArai
Comment:
Revision 14 as of 2010-02-15 00:50:19
Size: 2199
Editor: KojiArai
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
<<TableOfContents(2)>>
Line 2: Line 4:
== Main optics team ==
=== Week of 2/16-19 ===
* '''2/16-19 Pre-vent works'''
 * * Tuning of the MC servo ~ low power MC test
  * End X/Y transmon optics relocations ~ making spaces for green
  * ITM pointing preparations ~ green/red pointers at the both ends
Line 3: Line 11:
== Main optics team ==  * '''2/19 Power shutdown preparation'''
Line 5: Line 13:
 * Vent
  * What to do before the vent?
  * low power MC test
 * '''2/20 Power shutdown'''
Line 9: Line 15:
 * ITM placement
  * What to do before the ITM placement?
  * Suspension assembly
    * Gluing test
    * Optics cleaning
    * Gluing (magnets/standoffs/guide rods)
    * Suspending
  * procedure
=== Week of 2/22-26 ===
 * '''2/22 Power shutdown recovery'''
  * System recovery from power shutdown
  * Check MC SOS status
   * Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)
  * Pre-vent check list
   * PZT HV / Oplevs / etc
Line 18: Line 23:
 * MMT placement  * '''2/23 Vent'''
  * ITM pointing preparations? (green/red pointers at the both ends)

 * '''ITM placement'''
  * '''==>Small Optics Suspension'''
  * Placement procedure

=== Week of 3/1-3/5 ===
 * '''MMT placement'''
Line 21: Line 34:
  * corridor projection test
Line 22: Line 36:
 * SRM/PRM/BS placement  * '''Initial Pointing adjustment'''

=== Week of 3/8-3/12 ===

=== Week of 3/15-3/19 ===
 * 3/15-18 LVC meeting http://www.ligo.org/conferences/lv0310/
 * 3/19 aLIGO ISC?

=== Week of 3/22-3/26 ===
 * 40m commisioning party!?

=== Week of 3/29-4/2 ===
 * '''SRM/PRM/BS placement'''
  * What to do before the SRM/PRM/BS placement?
  * TT
   * purchase magnets (small/large)
Line 26: Line 55:
---------

== Green team ==

* Green installation
=== Week of 4/5-4/9 ===
Line 33: Line 58:
== Suspension preparation ==
 * '''3/16-26 Small Optics Suspension'''
  * gluing test
  * magnet-dumbbell gluing
  * dumbbell-mirror gluing
  * mirror hanging
Line 34: Line 65:
== CDS team ==

*
 * '''TT Suspension'''
  * small parts drawings
   * ECDs
   * wire jig
  * cleaning
Line 39: Line 72:
== Green team ==
 * ''' before vent'''
  * relocation of existing optics at the end table -''take 1.5day''
 * '''during vent'''
  * set up the green stuff onto the end table
  * align the green laser to the cavity (how to ?)
  * mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount
 * ''' after closing the tanks'''
  * recover IP-ANG and optical levers
Line 40: Line 82:
---------
== CDS team ==
 *

---------
== RF team ==
---------
Line 41: Line 90:

*
 * Laser delivery (done)

40m upgrade installation plan

Main optics team

Week of 2/16-19

* 2/16-19 Pre-vent works

  • * Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/19 Power shutdown preparation

  • 2/20 Power shutdown

Week of 2/22-26

  • 2/22 Power shutdown recovery

    • System recovery from power shutdown
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 Vent

    • ITM pointing preparations? (green/red pointers at the both ends)
  • ITM placement

    • ==>Small Optics Suspension

    • Placement procedure

Week of 3/1-3/5

  • MMT placement

    • What to do before the MMT placement?
    • Optics delivery (Shipping Feb 25) / baking
    • corridor projection test
  • Initial Pointing adjustment

Week of 3/8-3/12

Week of 3/15-3/19

Week of 3/22-3/26

  • 40m commisioning party!?

Week of 3/29-4/2

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • purchase magnets (small/large)
  • Closing up the vacuum

Week of 4/5-4/9


Suspension preparation

  • 3/16-26 Small Optics Suspension

    • gluing test
    • magnet-dumbbell gluing
    • dumbbell-mirror gluing
    • mirror hanging
  • TT Suspension

    • small parts drawings
      • ECDs
      • wire jig
    • cleaning


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity (how to ?)
    • mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount

  • after closing the tanks

    • recover IP-ANG and optical levers


CDS team


RF team


PSL table upgrade

  • Laser delivery (done)

Upgrade_09/Installation_Plan (last edited 2012-01-03 23:02:40 by localhost)