== Main optics team ==
 * '''Pre-vent works'''
  * Tuning of the MC servo ~ low power MC test
  * End transmon X/Y Optics relocations (before the vent) for green
  * ITM pointing preparations? (green/red pointers at the both ends)
Line 3: Line 8:
== Main optics team ==  * '''Vent'''
  * What to do before the vent?
  * Tuning of the MC servo ~ low power MC test
  * ITM pointing preparations? (green/red pointers at the both ends)
Line 5: Line 13:
 * Vent
  * What to do before the vent?
  * low power MC test

 * ITM placement
 * '''ITM placement'''
Line 12: Line 16:
  * Gluing test
  * Optics cleaning
  * Gluing (magnets/standoffs/guide rods)
    * Suspending
  * procedure  
   * Gluing test
   * Optics cleaning
   * Gluing (magnets/standoffs/guide rods)
   * Suspending
  * procedure
Line 18: Line 22:
 * MMT placement  * '''MMT placement'''
Line 21: Line 25:
  * corridor projection test
Line 22: Line 27:
 * SRM/PRM/BS placement  * '''Initial Pointing adjustment'''

 * '''SRM/PRM/BS placement'''
  * What to do before the SRM/PRM/BS placement?
  * TT
   * purchase magnets (small/large)
Line 27: Line 37:
Line 29: Line 38:

* Green installation
 * ''' before vent'''
  * relocation of existing optics at the end table -''take 1.5day''
 * '''during vent'''
  * set up the green stuff onto the end table
  * align the green laser to the cavity (how to ?)
  * mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount
 * ''' after closing the tanks'''
  * recover IP-ANG and optical levers
Line 33: Line 48:
Line 35: Line 49:

*
 *
Line 39: Line 52:
== RF team ==
---------
Line 41: Line 55:

*
 * Laser delivery (done)
 *

40m upgrade installation plan

Main optics team

  • Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End transmon X/Y Optics relocations (before the vent) for green
    • ITM pointing preparations? (green/red pointers at the both ends)
  • Vent

    • What to do before the vent?
    • Tuning of the MC servo ~ low power MC test
    • ITM pointing preparations? (green/red pointers at the both ends)
  • ITM placement

    • What to do before the ITM placement?
    • Suspension assembly
      • Gluing test
      • Optics cleaning
      • Gluing (magnets/standoffs/guide rods)
      • Suspending
    • procedure
  • MMT placement

    • What to do before the MMT placement?
    • Optics delivery (Shipping Feb 25) / baking
    • corridor projection test
  • Initial Pointing adjustment

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • purchase magnets (small/large)
  • Closing up the vacuum


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity (how to ?)
    • mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount

  • after closing the tanks

    • recover IP-ANG and optical levers


CDS team


RF team


PSL table upgrade

  • Laser delivery (done)