| == Main optics team == * '''Pre-vent works''' * Tuning of the MC servo ~ low power MC test * End transmon X/Y Optics relocations (before the vent) for green * ITM pointing preparations? (green/red pointers at the both ends) |
|
| Line 3: | Line 8: |
| == Main optics team == | * '''Vent''' * What to do before the vent? * Tuning of the MC servo ~ low power MC test * ITM pointing preparations? (green/red pointers at the both ends) |
| Line 5: | Line 13: |
| * Vent * What to do before the vent? * low power MC test * ITM placement |
* '''ITM placement''' |
| Line 12: | Line 16: |
| * Gluing test * Optics cleaning * Gluing (magnets/standoffs/guide rods) * Suspending * procedure |
* Gluing test * Optics cleaning * Gluing (magnets/standoffs/guide rods) * Suspending * procedure |
| Line 18: | Line 22: |
| * MMT placement | * '''MMT placement''' |
| Line 21: | Line 25: |
| * corridor projection test | |
| Line 22: | Line 27: |
| * SRM/PRM/BS placement | * '''Initial Pointing adjustment''' * '''SRM/PRM/BS placement''' * What to do before the SRM/PRM/BS placement? * TT * purchase magnets (small/large) |
| Line 27: | Line 37: |
| Line 29: | Line 38: |
* Green installation |
* ''' before vent''' * relocation of existing optics at the end table -''take 1.5day'' * '''during vent''' * set up the green stuff onto the end table * align the green laser to the cavity (how to ?) * mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount * ''' after closing the tanks''' * recover IP-ANG and optical levers |
| Line 33: | Line 48: |
| Line 35: | Line 49: |
* |
* |
| Line 39: | Line 52: |
| == RF team == --------- |
|
| Line 41: | Line 55: |
* |
* Laser delivery (done) * |
40m upgrade installation plan
Main optics team
Pre-vent works
- Tuning of the MC servo ~ low power MC test
- End transmon X/Y Optics relocations (before the vent) for green
- ITM pointing preparations? (green/red pointers at the both ends)
Vent
- What to do before the vent?
- Tuning of the MC servo ~ low power MC test
- ITM pointing preparations? (green/red pointers at the both ends)
ITM placement
- What to do before the ITM placement?
- Suspension assembly
- Gluing test
- Optics cleaning
- Gluing (magnets/standoffs/guide rods)
- Suspending
- procedure
MMT placement
- What to do before the MMT placement?
- Optics delivery (Shipping Feb 25) / baking
- corridor projection test
Initial Pointing adjustment
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
- TT
- purchase magnets (small/large)
- Closing up the vacuum
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- set up the green stuff onto the end table
- align the green laser to the cavity (how to ?)
mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount
after closing the tanks
- recover IP-ANG and optical levers
CDS team
RF team
PSL table upgrade
- Laser delivery (done)