Line 10: Line 10:
 * '''2/17 40m meeting'''
Line 16: Line 18:
  * System recovery from power shutdown   * System recovery
Line 23: Line 26:
  * ITM pointing preparations? (green/red pointers at the both ends)
Line 25: Line 27:
 * '''ITM placement'''
  * '''==>Small Optics Suspension'''
 * '''2/24 40m meeting '''

 * '''2/24-25 Input MC beam adjustment'''
  * beam centering to MC1/2/3 mirrors

  * moving faraday etc ''' '''

 * '''2/25-26 ITMX/ITMY placement'''
  * '''__==>Small Optics Suspension__'''
Line 29: Line 39:
  * ITMX/Y oplev
Line 30: Line 42:
 * '''MMT placement'''
  * What to do before the MMT placement?
  * Optics delivery (Shipping Feb 25) / baking
  * corridor projection test
Line 35: Line 43:
 * '''Initial Pointing adjustment'''  * '''3/1-5 MMT placement / initial pointing adjustment '''
  * MC trans beam mode measurement
  * Renew the MMT solution''' '''

  * MMT placement
   * __Optics delivery (Shipping Feb 25) / baking__
  * Corridor projection ~ measuremnt & adjustment
  * Initial Pointing adjustment
Line 38: Line 53:
Line 81: Line 97:
 *  * 

40m upgrade installation plan

Main optics team

Week of 2/16-2/19

  • 2/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/17 40m meeting

  • 2/19 Power shutdown preparation

  • 2/20 Power shutdown

Week of 2/22-2/26

  • 2/22 Power shutdown recovery

    • System recovery
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 Vent

  • 2/24 40m meeting

  • 2/24-25 Input MC beam adjustment

    • beam centering to MC1/2/3 mirrors
    • moving faraday etc

  • 2/25-26 ITMX/ITMY placement

    • ==>Small Optics Suspension

    • Placement procedure
    • ITMX/Y oplev

Week of 3/1-3/5

  • 3/1-5 MMT placement / initial pointing adjustment

    • MC trans beam mode measurement
    • Renew the MMT solution

    • MMT placement
      • Optics delivery (Shipping Feb 25) / baking

    • Corridor projection ~ measuremnt & adjustment

    • Initial Pointing adjustment

Week of 3/8-3/12

Week of 3/15-3/19

Week of 3/22-3/26

  • 40m commisioning party!?

Week of 3/29-4/2

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • purchase magnets (small/large)
  • Closing up the vacuum

Week of 4/5-4/9


Suspension preparation

  • 3/16-26 Small Optics Suspension

    • gluing test
    • magnet-dumbbell gluing
    • dumbbell-mirror gluing
    • mirror hanging
  • TT Suspension

    • small parts drawings
      • ECDs
      • wire jig
    • cleaning


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity (how to ?)
    • mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount

  • after closing the tanks

    • recover IP-ANG and optical levers


CDS team


RF team


PSL table upgrade

  • Laser delivery (done)