| === Week of 2/16-19 === | === Week of 2/16-2/19 === |
| Line 7: | Line 6: |
| * * Tuning of the MC servo ~ low power MC test | * Tuning of the MC servo ~ low power MC test |
| Line 10: | Line 9: |
* '''2/17 40m meeting''' |
|
| Line 15: | Line 16: |
| === Week of 2/22-26 === | === Week of 2/22-2/26 === |
| Line 17: | Line 18: |
| * System recovery from power shutdown | * System recovery |
| Line 24: | Line 26: |
| * ITM pointing preparations? (green/red pointers at the both ends) | |
| Line 26: | Line 27: |
| * '''ITM placement''' * '''==>Small Optics Suspension''' |
* '''2/24 40m meeting ''' * '''2/24-25 Input MC beam adjustment''' * beam centering to MC1/2/3 mirrors * moving faraday etc ''' ''' * '''2/25-26 ITMX/ITMY placement''' * '''__==>Small Optics Suspension__''' |
| Line 30: | Line 39: |
| * ITMX/Y oplev |
|
| Line 31: | Line 42: |
| * '''MMT placement''' * What to do before the MMT placement? * Optics delivery (Shipping Feb 25) / baking * corridor projection test |
|
| Line 36: | Line 43: |
| * '''Initial Pointing adjustment''' | * '''3/1-5 MMT placement / initial pointing adjustment ''' * MC trans beam mode measurement * Renew the MMT solution''' ''' * MMT placement * __Optics delivery (Shipping Feb 25) / baking__ * Corridor projection ~ measuremnt & adjustment * Initial Pointing adjustment |
| Line 56: | Line 70: |
Contents
40m upgrade installation plan
Main optics team
Week of 2/16-2/19
2/16-19 Pre-vent works
- Tuning of the MC servo ~ low power MC test
- End X/Y transmon optics relocations ~ making spaces for green
- ITM pointing preparations ~ green/red pointers at the both ends
2/17 40m meeting
2/19 Power shutdown preparation
2/20 Power shutdown
Week of 2/22-2/26
2/22 Power shutdown recovery
- System recovery
- Check MC SOS status
Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)
- Pre-vent check list
- PZT HV / Oplevs / etc
2/23 Vent
2/24 40m meeting
2/24-25 Input MC beam adjustment
- beam centering to MC1/2/3 mirrors
moving faraday etc
2/25-26 ITMX/ITMY placement
==>Small Optics Suspension
- Placement procedure
- ITMX/Y oplev
Week of 3/1-3/5
3/1-5 MMT placement / initial pointing adjustment
- MC trans beam mode measurement
Renew the MMT solution
- MMT placement
Optics delivery (Shipping Feb 25) / baking
Corridor projection ~ measuremnt & adjustment
- Initial Pointing adjustment
Week of 3/8-3/12
Week of 3/15-3/19
3/15-18 LVC meeting http://www.ligo.org/conferences/lv0310/
- 3/19 aLIGO ISC?
Week of 3/22-3/26
- 40m commisioning party!?
Week of 3/29-4/2
SRM/PRM/BS placement
- What to do before the SRM/PRM/BS placement?
- TT
- purchase magnets (small/large)
- Closing up the vacuum
Week of 4/5-4/9
Suspension preparation
3/16-26 Small Optics Suspension
- gluing test
- magnet-dumbbell gluing
- dumbbell-mirror gluing
- mirror hanging
TT Suspension
- small parts drawings
- ECDs
- wire jig
- cleaning
- small parts drawings
Green team
before vent
relocation of existing optics at the end table -take 1.5day
during vent
- set up the green stuff onto the end table
- align the green laser to the cavity (how to ?)
mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount
after closing the tanks
- recover IP-ANG and optical levers
CDS team
RF team
PSL table upgrade
- Laser delivery (done)