== Main optics team ==
=== Week of 2/16-2/19 ===
 * '''2/16-19 Pre-vent works'''
  * Tuning of the MC servo ~ low power MC test
  * End X/Y transmon optics relocations ~ making spaces for green
  * ITM pointing preparations ~ green/red pointers at the both ends
Line 3: Line 10:
== Main optics team ==  * '''2/17 40m meeting'''
Line 5: Line 12:
* Vent
  * What to do before the vent?
  * low power MC test
 * '''2/18 Power shutdown preparation'''
Line 9: Line 14:
* ITM placement
  * What to do before the ITM placement?
  * Suspension assembly
    * Gluing test
    * Optics cleaning
    * Gluing (magnets/standoffs/guide rods)
    * Suspending
  * procedure
* MMT placement
  * What to do before the MMT placement?
  * Optics delivery (Shipping Feb 25) / baking
 * '''2/19 No work / only papers and pens'''
Line 21: Line 16:
* SRM/PRM/BS placement  * '''2/20 Power shutdown'''
Line 23: Line 18:
* Closing up the vacuum === Week of 2/22-2/26 ===
 * '''2/22 Power shutdown recovery'''
  * System recovery

  * Check MC SOS status
   * Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)
  * Pre-vent check list
   * PZT HV / Oplevs / etc

 * '''2/23 or 24 Vent'''

 * '''2/24 40m meeting '''

 * '''2/24-25 Input MC beam adjustment'''
  * beam centering to MC1/2/3 mirrors

  * moving faraday etc ''' '''

 * '''2/25-26 ITMX/ITMY placement'''
  * '''__==>Small Optics Suspension__'''

  * Placement procedure

  * ITMX/Y oplev

=== Week of 3/1-3/5 ===
 * '''3/1-5 MMT placement / initial pointing adjustment '''
  * MC trans beam mode measurement
  * Renew the MMT solution''' '''

  * MMT placement
   * __Optics delivery (Shipping Feb 25) / baking__
  * Corridor projection ~ measuremnt & adjustment
  * Initial Pointing adjustment

 * '''3/4 40m meeting '''

=== Week of 3/8-3/12 ===
 * '''3/8-9 Green steering installation?'''
 * '''3/10 40m meeting '''
 * '''3/11-12 No work'''

=== Week of 3/15-3/19 ===
 * '''3/15-18 LVC meeting''' http://www.ligo.org/conferences/lv0310/
 * '''3/19 aLIGO ISC?'''

=== Week of 3/22-3/26 ===
 * '''40m commisioning party!?'''
 * '''ETMY Green installation'''

=== Week of 3/29-4/2 ===
 * '''SRM/PRM/BS placement'''
  * What to do before the SRM/PRM/BS placement?
  * TT
   * ==> TT preparations

 * Closing up the vacuum

=== Week of 4/5-4/9 ===
---------
== Suspension preparation ==
 * '''2/16-26 Small Optics Suspension'''
  * Wed 17 Feb
   * Plan for magnet-to-dumbbell gluing fixture (keep them axially aligned)
   * Make some kind of magnet-to-dumbbell gluing fixture - machine shop? Depends on the plan.
   * Epoxy test. Try gluing a dumbbell to an optic?
  * Thurs 18 Feb
   * Make up matching sets of magnets using gaussmeter (Morning)
   * Etch magnets and dumbbells using razor blade (Morning)
   * Epoxy magnets to dumbells (Morning)
   * Cure epoxy (overnight)
   * Place ITMX in guiderod fixture
   * Epoxy guiderods to ITMX (Afternoon)
   * Cure epoxy (overnight)
  * Fri 19 Feb
   * Remove ITMX from guiderod fixture, place in magnet fixture
   * Epoxy magnets ITMX (Morning)
   * Cure epoxy (overnight)
   * Place ITMY in guiderod fixtrue
   * Epoxy guiderods to ITMY (Afternoon)
   * Cure epoxy (overnight)
  * Sat 20 Feb
   * No Electricity - No work
  * Sun 21 Feb
   * Plan for viton cutting (something to help measure / keep the razor straight while cutting)
   * Cut the Viton
   * Assemble EQ stops (stick the viton in the screws)
  * Mon 22 Feb
   * Glue magnets to ITMY (Morning)
   * Cure epoxy (overnight)
   * Balance Optical Table (Afternoon)
   * Make HeNe OpLev (Afternoon)
   * Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
  * Tues 23 Feb
   * Hang and balance both ITMs. (All Day)
   * Epoxy wire standoffs in place after balancing
   * Cure epoxy (overnight)
  * Wed 24 Feb
   * Remove both ITMs from their suspensions (Morning)
   * Airbake to clean the optics (How long will this take? There are contradictions in the Assembly Spec Docs)
   * Reinstall optics in suspensions (Late afternoon?)
   * Install OSEMs
  * Thurs 25 Feb
   * Start installing the ITMs
  * Fri 26 Feb
   * Finish installing the ITMs

 * '''TT Suspension'''
  * small parts drawings
   * ECDs
   * wire jig
  * purchase magnets (small/large)
  * cleaning
Line 26: Line 133:
Line 28: Line 134:

* Green installation
 * ''' before vent'''
  * relocation of existing optics at the end table -''take 1.5day''
 * '''during vent'''
  * set up the green stuff onto the end table
  * align the green laser to the cavity
   * how to: visual alignment
  * mode matching of the green laser to the cavity
   * on the table / corridor projection test ==> sliding mount
 * ''' after tank evacuation'''
  * recover IP-ANG and optical levers
Line 32: Line 146:
Line 34: Line 147:

*
 * 2/22-3/5 Delivery of some computers? / CDS software installations?
 * -3/31 Installation for some of the suspensions?
Line 38: Line 151:
== RF team ==
A draft. Dates will come.
Line 39: Line 154:
 * Assembling of the RF frequency Generator
  * Order 2U chassis from Metalcraft
  * Get an aluminum slab from the machine shop
  * Design and order front and back panels
  * Design and order RG-174 cables for the internal wiring
  * ...
 * Modification of the RF Photodetectors
  * replace the photodiodes and adjust for the changed impedances
 * Modification of the demod board
  * installation of the low/band/high pass filters
 *

---------
Line 40: Line 168:

*
 * Laser delivery (done)

40m upgrade installation plan

Main optics team

Week of 2/16-2/19

  • 2/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 2/17 40m meeting

  • 2/18 Power shutdown preparation

  • 2/19 No work / only papers and pens

  • 2/20 Power shutdown

Week of 2/22-2/26

  • 2/22 Power shutdown recovery

    • System recovery
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 2/23 or 24 Vent

  • 2/24 40m meeting

  • 2/24-25 Input MC beam adjustment

    • beam centering to MC1/2/3 mirrors
    • moving faraday etc

  • 2/25-26 ITMX/ITMY placement

    • ==>Small Optics Suspension

    • Placement procedure
    • ITMX/Y oplev

Week of 3/1-3/5

  • 3/1-5 MMT placement / initial pointing adjustment

    • MC trans beam mode measurement
    • Renew the MMT solution

    • MMT placement
      • Optics delivery (Shipping Feb 25) / baking

    • Corridor projection ~ measuremnt & adjustment

    • Initial Pointing adjustment
  • 3/4 40m meeting

Week of 3/8-3/12

  • 3/8-9 Green steering installation?

  • 3/10 40m meeting

  • 3/11-12 No work

Week of 3/15-3/19

Week of 3/22-3/26

  • 40m commisioning party!?

  • ETMY Green installation

Week of 3/29-4/2

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • ==> TT preparations

  • Closing up the vacuum

Week of 4/5-4/9


Suspension preparation

  • 2/16-26 Small Optics Suspension

    • Wed 17 Feb
      • Plan for magnet-to-dumbbell gluing fixture (keep them axially aligned)
      • Make some kind of magnet-to-dumbbell gluing fixture - machine shop? Depends on the plan.
      • Epoxy test. Try gluing a dumbbell to an optic?
    • Thurs 18 Feb
      • Make up matching sets of magnets using gaussmeter (Morning)
      • Etch magnets and dumbbells using razor blade (Morning)
      • Epoxy magnets to dumbells (Morning)
      • Cure epoxy (overnight)
      • Place ITMX in guiderod fixture
      • Epoxy guiderods to ITMX (Afternoon)
      • Cure epoxy (overnight)
    • Fri 19 Feb
      • Remove ITMX from guiderod fixture, place in magnet fixture
      • Epoxy magnets ITMX (Morning)
      • Cure epoxy (overnight)
      • Place ITMY in guiderod fixtrue
      • Epoxy guiderods to ITMY (Afternoon)
      • Cure epoxy (overnight)
    • Sat 20 Feb
      • No Electricity - No work
    • Sun 21 Feb
      • Plan for viton cutting (something to help measure / keep the razor straight while cutting)
      • Cut the Viton
      • Assemble EQ stops (stick the viton in the screws)
    • Mon 22 Feb
      • Glue magnets to ITMY (Morning)
      • Cure epoxy (overnight)
      • Balance Optical Table (Afternoon)
      • Make HeNe OpLev (Afternoon)

      • Ensure OSEM satellite box is ready, PZT buzzer is ready, and all other preparations for hanging optics
    • Tues 23 Feb
      • Hang and balance both ITMs. (All Day)
      • Epoxy wire standoffs in place after balancing
      • Cure epoxy (overnight)
    • Wed 24 Feb
      • Remove both ITMs from their suspensions (Morning)
      • Airbake to clean the optics (How long will this take? There are contradictions in the Assembly Spec Docs)
      • Reinstall optics in suspensions (Late afternoon?)
      • Install OSEMs
    • Thurs 25 Feb
      • Start installing the ITMs
    • Fri 26 Feb
      • Finish installing the ITMs
  • TT Suspension

    • small parts drawings
      • ECDs
      • wire jig
    • purchase magnets (small/large)
    • cleaning


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity
      • how to: visual alignment
    • mode matching of the green laser to the cavity
      • on the table / corridor projection test ==> sliding mount

  • after tank evacuation

    • recover IP-ANG and optical levers


CDS team

  • 2/22-3/5 Delivery of some computers? / CDS software installations?
  • -3/31 Installation for some of the suspensions?


RF team

A draft. Dates will come.

  • Assembling of the RF frequency Generator
    • Order 2U chassis from Metalcraft
    • Get an aluminum slab from the machine shop
    • Design and order front and back panels
    • Design and order RG-174 cables for the internal wiring
    • ...
  • Modification of the RF Photodetectors
    • replace the photodiodes and adjust for the changed impedances
  • Modification of the demod board
    • installation of the low/band/high pass filters


PSL table upgrade

  • Laser delivery (done)