== Main optics team ==
 * '''3/16-19 Pre-vent works'''
  * Tuning of the MC servo ~ low power MC test
  * End X/Y transmon optics relocations ~ making spaces for green
  * ITM pointing preparations ~ green/red pointers at the both ends
Line 3: Line 8:
== Main optics team ==  * '''3/19 Power shutdown preparation'''
Line 5: Line 10:
* Vent
  * What to do before the vent?
  * low power MC test
 * '''3/20 Power shutdown'''
Line 9: Line 12:
* ITM placement
  * What to do before the ITM placement?
  * Suspension assembly
    * Gluing test
    * Optics cleaning
    * Gluing (magnets/standoffs/guide rods)
    * Suspending
  * procedure
* MMT placement
 * '''3/22 Power shutdown recovery'''
  * System recovery from power shutdown
  * Check MC SOS status
   * Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)
  * Pre-vent check list
    * PZT HV / Oplevs / etc

 * '''3/23 Vent'''
  * ITM pointing preparations? (green/red pointers at the both ends)

 * '''ITM placement'''
  * '''==>Small Optics Suspension'''
  * Placement procedure

 * '''MMT placement'''
Line 20: Line 29:
  * corridor projection test
Line 21: Line 31:
* SRM/PRM/BS placement  * '''Initial Pointing adjustment'''
Line 23: Line 33:
* Closing up the vacuum  * '''SRM/PRM/BS placement'''
  * What to do before the SRM/PRM/BS placement?
  * TT
   * purchase magnets (small/large)

 * Closing up the vacuum
Line 26: Line 41:
== Suspension preparation ==
 * '''Small Optics Suspension'''
  * gluing test
  * magnet-dumbbell gluing
  * dumbbell-mirror gluing
  * mirror hanging
Line 27: Line 48:
== Green team ==

* Green installation
 * '''TT Suspension'''
  * small parts drawings
    * ECDs
    * wire jig
  * cleaning
    * ECDs
    * wire jig
Line 32: Line 57:

== CDS team ==

*
== Green team ==
 * ''' before vent'''
  * relocation of existing optics at the end table -''take 1.5day''
 * '''during vent'''
  * set up the green stuff onto the end table
  * align the green laser to the cavity (how to ?)
  * mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount
 * ''' after closing the tanks'''
  * recover IP-ANG and optical levers
Line 38: Line 68:
== CDS team ==
 *
Line 39: Line 71:
---------
== RF team ==
---------
Line 40: Line 75:

*
 * Laser delivery (done)
 *

40m upgrade installation plan

Main optics team

  • 3/16-19 Pre-vent works

    • Tuning of the MC servo ~ low power MC test
    • End X/Y transmon optics relocations ~ making spaces for green
    • ITM pointing preparations ~ green/red pointers at the both ends
  • 3/19 Power shutdown preparation

  • 3/20 Power shutdown

  • 3/22 Power shutdown recovery

    • System recovery from power shutdown
    • Check MC SOS status
      • Low power MC mode ~ P(intra_cav)<10W at the resonance (~10mW incident)

    • Pre-vent check list
      • PZT HV / Oplevs / etc
  • 3/23 Vent

    • ITM pointing preparations? (green/red pointers at the both ends)
  • ITM placement

    • ==>Small Optics Suspension

    • Placement procedure
  • MMT placement

    • What to do before the MMT placement?
    • Optics delivery (Shipping Feb 25) / baking
    • corridor projection test
  • Initial Pointing adjustment

  • SRM/PRM/BS placement

    • What to do before the SRM/PRM/BS placement?
    • TT
      • purchase magnets (small/large)
  • Closing up the vacuum


Suspension preparation

  • Small Optics Suspension

    • gluing test
    • magnet-dumbbell gluing
    • dumbbell-mirror gluing
    • mirror hanging
  • TT Suspension

    • small parts drawings
      • ECDs
      • wire jig
    • cleaning
      • ECDs
      • wire jig


Green team

  • before vent

    • relocation of existing optics at the end table -take 1.5day

  • during vent

    • set up the green stuff onto the end table
    • align the green laser to the cavity (how to ?)
    • mode matching of the green laser to the cavity (on the table / corridor projection test) ==> sliding mount

  • after closing the tanks

    • recover IP-ANG and optical levers


CDS team


RF team


PSL table upgrade

  • Laser delivery (done)