Line 8: Line 8:
29 Oct 2009 29 Oct 2009 - Most of the parts are here, only the EQ stops are left to be dealt with. Most of this stuff needs to visit Bob's lab for cleaning.

ITM Suspensions

The ITMs are being changed into SOS. For this we will need to fab 2 SOS towers. We will re-use existing OSEMs and misc in-vac hardware.

SOS Updates (Mostly ITMs, but where applicable, extra parts for other new Optics):

29 Oct 2009 - Most of the parts are here, only the EQ stops are left to be dealt with. Most of this stuff needs to visit Bob's lab for cleaning.

Item

# in Drawing D960001

DCC / Part Number

Qty Needed PER SUS

Qty Needed for Upgrade

Qty Have IN HAND

Plan

Sensor/Actuator Plate

1

D960002

2

4

4

DONE

Suspension Block

2

D960003

1

2

2

DONE

Tower Base

3

D960004

1

2

2

DONE

Right Side Plate

4

D960005

1

2

2

DONE

Left Side Plate

5

D960006

1

2

2

DONE

Upper Mirror Clamp

6

D960007

1

2

2

DONE

Lower Clamp

7

D960008-1

1

2

2

DONE

Lower Clamp, Opposite

8

D960008-2

1

2

2

DONE

Wire Clamp

9

1205308-1 (kind of #?)

1

2

3

DONE

Clamp, Suspension Block

10

D960134

2

4

5

DONE

Stiffener Plate

11

D960009

1

2

2

DONE

Dumbbell Standoff

12

D970075

6

7 optics x 6 = 42

15 in boxes from LLO, plus many in Bob's cleanroom

done?

Safety Stop, Long

13

D970313

2

Enough to replace EQ stops for ALL optics?

Buy screws from McMaster, drill holes for viton, clean&bake, insert viton

Optic

14

Various

1

DONE when delivered from ATF

Sensor/Actuator Assembly

15

D960011

5

10

6 short OSEMS in SUS Clean Plastic Box

Reuse (long) OSEMs from current ITM MOSs - DONE

Wire Standoff

16

D970187

2

7 optics x 2 + spares = 18

7

Requested 25 from Shop. Expected in 1-2 weeks

Guide Rod

17

D970188

2

7 optics x 2 + spares = 18

3

Requested 25 from Shop. Expected in 1-2 weeks

Magnet

18

D960501

6

7 optics x 6 = 42

~100 in Bob's Cleanroom

DONE - need to match sets still

Safety Stop, Small

19

D960312

4

Enough to replace EQ stops for ALL optics?

Buy screws from McMaster, drill holes for viton, clean&bake, insert viton

Safety Stop

20

D960311

4

Enough to replace EQ stops for ALL optics?

Buy screws from McMaster, drill holes for viton, clean&bake, insert viton

There is no 21

SST Spring Plunger, 10-32

22

84985A999 (McMaster Part #)

5

10

22

DONE

SST SOC HD CAP Screw

23

4-40, 3/8"

4

8

10

DONE

SST SOC HD CAP Screw

24

4-40, 1/2"

8

16

20

DONE

SST SOC HD CAP Screw

25

1/4-20, 3/4"

20

40

50

DONE

SST SOC HD CAP Screw

26

1/4-20, 1.25"

4

8

10

DONE

SST Lock Washer

27

1/4"

4

8

50

DONE

SST Washer

28

1/4"

4

8

50

DONE

Steel Music Wire

29

Diam=0.0017", CFW

DONE

Viton for EQ stops

DONE - Clean Plastic Boxes

Fixtures

@ MIT - in Progress (Rana)

Tip/Tilt Suspensions

For the PRC/SRC folding we will use Tip/Tilt stages modified to be used passively. No active damping, no coil drive. Just magnets and natural eddy current damping.

MC

We will re align the MC suspensions so that we are centered on the mirrors this time.

Others

The PRM, SRM, and BS will remain SOS. No new towers.

The ETMs will remain MOS. No new towers.